CL C Conc (Abut) (Item 420-7012): TxDOT Unit Price History

1,253 bids · 165 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure CY

TxDOT 420-7012 · CL C CONC (ABUT) · Unit: CY

Low bid
$1,100.00/CY
Quantity-weighted median of winning unit prices
Weighted median
$1,250.00/CY
Quantity-weighted median of every bid
Engineer’s estimate
$1,350.00/CY
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-10%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$1,000.00$1,500.00$2,000.00$2,500.00$3,000.001101001K10KQuantity (CY), log scaleUnit price ($/CY)
Winning (low) bid Other bid Fitted price curve (ln price = 7.48 − 0.058·ln qty, R² 0.02)320 plotted bids, 4 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 420-7012 (CL C Conc (Abut)) is measured in CY. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,253 bids for it on 165 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 709 bids was $1,250.00 per CY, and the winning low bidders priced it at a weighted median of $1,100.00 per CY.

TxDOT's engineer's estimate for the same lines had a weighted median of $1,350.00 per CY, so winning bids came in 18.5% below the estimate.

By calendar year, the median bid moved from $1,500.00 in 2025 (558 bids) to $1,345.00 in 2026 (644 bids), down 10.3%. The middle half of 2026 bids fell between $1,100.00 and $1,700.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 10%.

Quantity matters for this item. Lines of 1 to 49.3 CY had a weighted median of $1,500.00, while lines above 92.2 CY had $1,300.00, a 13% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 165 lines where both a winning and a second-place bid were published, the median winning unit price was $1,250.00 against $1,300.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 20 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($1,094.40) and Childress the highest ($1,900.00). The busiest district for this item was Yoakum.

The most recent letting with this item was on Nov 4, 2026 in Brazos County, where Fluor Enterprises, Inc. was the low bidder at $1,047.00 per CY for 347.5 CY against an estimate of $1,000.00.

4 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 416-7006 Drill Shaft (36 IN) (weighted median $270.00 per LF); 416-7040 Drill Shaft (Rdwy ILL Pole) (30 IN) (weighted median $255.00 per LF); 429-7007 Conc STR Repair (Vertical & Overhead) (weighted median $150.00 per SF); 432-7013 Riprap (MOW Strip)(4 IN) (weighted median $645.00 per CY).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
2024517$1,628.25$1,560.80$1,600.00$1,347.30$1,950.00
202555877$1,595.51$1,400.00$1,500.00$1,241.25$2,000.00
202664482$1,361.25$1,250.00$1,345.00$1,100.00$1,700.00

Quantity bands

BandQuantity (CY)BidsWeighted avgWeighted median25th–75th pct
Small1–49.3425$1,723.23$1,500.00$1,300.00–$2,020.85
Medium51–89.2411$1,526.87$1,400.00$1,190.05–$1,774.59
Large92.2–1,253.2417$1,403.21$1,300.00$1,100.00–$1,635.00

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$1,250.00
Median second-low unit price
$1,300.00
Median engineer’s estimate
$1,400.00
Median gap, second vs. low
+0%

165 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District

Line quantity 347.5 CY · Engineer’s estimate $1,000/CY

  • 1. Fluor Enterprises, Inc.

    LOW BID · WINNER
    Unit price
    $1,047.00/CY
    Extension
    $363,832.50
    Proposal total
    $30,209,876
    Money left on the table
    $2,977,718 (9.86%)
    vs. engineer’s estimate
    +4.7%
  • Unit price
    $1,400.00/CY
    Extension
    $486,500.00
    Proposal total
    $33,187,594
    vs. low bid
    +$2,977,718
    vs. engineer’s estimate
    +40%
  • Unit price
    $1,050.00/CY
    Extension
    $364,875.00
    Proposal total
    $33,911,798
    vs. low bid
    +$3,701,922
    vs. engineer’s estimate
    +5%
  • Unit price
    $830.00/CY
    Extension
    $288,425.00
    Proposal total
    $34,862,676
    vs. low bid
    +$4,652,800
    vs. engineer’s estimate
    -17%
  • Unit price
    $1,007.31/CY
    Extension
    $350,040.23
    Proposal total
    $39,237,828
    vs. low bid
    +$9,027,952
    vs. engineer’s estimate
    +0.7%
  • Unit price
    $1,345.00/CY
    Extension
    $467,387.50
    Proposal total
    $39,562,405
    vs. low bid
    +$9,352,529
    vs. engineer’s estimate
    +34.5%
  • Unit price
    $1,600.00/CY
    Extension
    $556,000.00
    Proposal total
    $39,630,699
    vs. low bid
    +$9,420,823
    vs. engineer’s estimate
    +60%
  • Unit price
    $800.00/CY
    Extension
    $278,000.00
    Proposal total
    $39,994,995
    vs. low bid
    +$9,785,119
    vs. engineer’s estimate
    -20%
  • 9. Zachry Construction Corporation

    Unit price
    $1,137.84/CY
    Extension
    $395,399.40
    Proposal total
    $42,444,061
    vs. low bid
    +$12,234,185
    vs. engineer’s estimate
    +13.8%
  • 10. Brizo Construction, LLC

    Unit price
    $800.00/CY
    Extension
    $278,000.00
    Proposal total
    $43,708,350
    vs. low bid
    +$13,498,474
    vs. engineer’s estimate
    -20%
  • Unit price
    $1,187.00/CY
    Extension
    $412,482.50
    Proposal total
    $44,387,970
    vs. low bid
    +$14,178,094
    vs. engineer’s estimate
    +18.7%
  • Unit price
    $2,173.00/CY
    Extension
    $755,117.50
    Proposal total
    $48,396,973
    vs. low bid
    +$18,187,097
    vs. engineer’s estimate
    +117.3%

Proposal 0922-33-234 · let Nov 4, 2026 · Webb County, Laredo District

Line quantity 83.4 CY · Engineer’s estimate $1,500/CY

  • 1. Stx Civil

    LOW BID · WINNER
    Unit price
    $1,039.46/CY
    Extension
    $86,690.96
    Proposal total
    $2,866,785
    Money left on the table
    $83,215 (2.9%)
    vs. engineer’s estimate
    -30.7%
  • Unit price
    $1,750.00/CY
    Extension
    $145,950.00
    Proposal total
    $2,950,000
    vs. low bid
    +$83,215
    vs. engineer’s estimate
    +16.7%
  • 3. Acee Construction LLC.

    Unit price
    $1,222.05/CY
    Extension
    $101,918.97
    Proposal total
    $3,033,273
    vs. low bid
    +$166,488
    vs. engineer’s estimate
    -18.5%
  • Unit price
    $1,297.16/CY
    Extension
    $108,183.14
    Proposal total
    $3,261,472
    vs. low bid
    +$394,687
    vs. engineer’s estimate
    -13.5%
  • Unit price
    $1,345.00/CY
    Extension
    $112,173.00
    Proposal total
    $3,270,969
    vs. low bid
    +$404,184
    vs. engineer’s estimate
    -10.3%
  • Unit price
    $2,300.00/CY
    Extension
    $191,820.00
    Proposal total
    $3,466,015
    vs. low bid
    +$599,230
    vs. engineer’s estimate
    +53.3%
  • Unit price
    $4,000.00/CY
    Extension
    $333,600.00
    Proposal total
    $5,083,300
    vs. low bid
    +$2,216,516
    vs. engineer’s estimate
    +166.7%

Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District

Line quantity 768.9 CY · Engineer’s estimate $1,497/CY

  • Unit price
    $1,397.34/CY
    Extension
    $1,074,414.73
    Proposal total
    $412,233,374
    Money left on the table
    $3,506,193 (0.85%)
    vs. engineer’s estimate
    -6.7%
  • 2. Pulice Construction, Inc.

    Unit price
    $1,400.00/CY
    Extension
    $1,076,460.00
    Proposal total
    $415,739,567
    vs. low bid
    +$3,506,193
    vs. engineer’s estimate
    -6.5%
  • 3. Fluor Enterprises, Inc.

    Unit price
    $1,404.31/CY
    Extension
    $1,079,773.96
    Proposal total
    $473,353,333
    vs. low bid
    +$61,119,959
    vs. engineer’s estimate
    -6.2%
  • 4. Harper Brothers Construction LLC

    Unit price
    $2,115.00/CY
    Extension
    $1,626,223.50
    Proposal total
    $477,550,553
    vs. low bid
    +$65,317,180
    vs. engineer’s estimate
    +41.3%
  • Unit price
    $2,616.47/CY
    Extension
    $2,011,803.78
    Proposal total
    $477,564,067
    vs. low bid
    +$65,330,694
    vs. engineer’s estimate
    +74.8%
  • 6. Balfour Beatty Infrastructure, Inc.

    Unit price
    $1,578.87/CY
    Extension
    $1,213,993.14
    Proposal total
    $492,134,823
    vs. low bid
    +$79,901,450
    vs. engineer’s estimate
    +5.5%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040212-03-058BrazosBryan347.512Fluor Enterprises, Inc.$1,047.00$1,000.00
2026-11-040922-33-234WebbLaredo83.47Stx Civil$1,039.46$1,500.00
2026-11-030015-13-432TravisAustin768.96Austin Bridge & Road Services, LP$1,397.34$1,497.00
2026-11-030917-30-068BurlesonBryan37.815C & W Southern LLC$1,100.00$1,000.00
2026-10-070200-01-093AngelinaLufkin1167Longview Bridge and Road, Ltd.$1,465.00$1,300.00
2026-10-070922-20-030La SalleLaredo17.66Presidio Contracting, LLC$1,190.00$1,600.00
2026-10-060912-34-209Fort BendHouston579Garret Shields Infrastructure$1,200.00$1,715.02
2026-09-030722-03-016Red RiverParis56.28Longview Bridge and Road, Ltd.$900.00$1,400.00
2026-09-030844-04-011CollingsworthChildress40.97Coppell Construction Co., Inc.$1,350.00$1,600.00
2026-09-030901-19-198GraysonParis94.68Rb Contracting, LLC$975.00$1,200.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene21$950.00$1,320.00$1,800.00—
Amarillo34$1,800.00$1,800.00$1,550.00-26.53%
Atlanta13$950.00$1,100.00$1,100.00—
Austin44$1,397.34$1,491.59$1,497.00—
Beaumont43$1,200.00$1,200.00$1,200.00-12.01%
Brownwood9$1,500.00$1,891.00$1,800.00—
Bryan92$1,047.00$1,187.00$1,000.00-28.82%
Childress31$1,350.00$1,900.00$1,510.00-13.64%
Corpus Christi92$1,500.00$1,500.00$1,500.00-11.76%
Fort Worth9$1,100.00$1,400.00$1,800.00—
Houston71$827.15$1,200.00$1,400.00—
Laredo50$1,330.00$1,345.00$1,300.00—
Lubbock13$1,800.00$1,600.00$400.00—
Lufkin69$1,465.00$1,210.00$1,300.00-10.36%
Odessa9$1,540.00$1,117.20$1,500.00—
Paris96$975.00$1,100.00$1,200.00-18.22%
Pharr45$1,000.00$1,094.40$1,350.00-1.9%
San Angelo26$1,800.00$1,500.00$1,500.00-16.67%
San Antonio72$1,050.00$1,151.99$1,200.00-1.86%
Tyler66$1,050.00$1,122.00$1,600.00-18.23%
Waco57$1,200.00$1,325.00$1,400.00-27.71%
Wichita Falls27$1,250.00$1,250.00$2,000.00—
Yoakum264$1,300.00$1,300.00$1,250.00-2.39%

Related items

Is your price for item 420-7012 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.