CL C Conc (Abut) (Item 420-7012): TxDOT Unit Price History
1,253 bids · 165 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure CY
TxDOT 420-7012 · CL C CONC (ABUT) · Unit: CY
- Low bid
- $1,100.00/CY
- Quantity-weighted median of winning unit prices
- Weighted median
- $1,250.00/CY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $1,350.00/CY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -10%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 420-7012 (CL C Conc (Abut)) is measured in CY. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,253 bids for it on 165 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 709 bids was $1,250.00 per CY, and the winning low bidders priced it at a weighted median of $1,100.00 per CY.
TxDOT's engineer's estimate for the same lines had a weighted median of $1,350.00 per CY, so winning bids came in 18.5% below the estimate.
By calendar year, the median bid moved from $1,500.00 in 2025 (558 bids) to $1,345.00 in 2026 (644 bids), down 10.3%. The middle half of 2026 bids fell between $1,100.00 and $1,700.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 10%.
Quantity matters for this item. Lines of 1 to 49.3 CY had a weighted median of $1,500.00, while lines above 92.2 CY had $1,300.00, a 13% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 165 lines where both a winning and a second-place bid were published, the median winning unit price was $1,250.00 against $1,300.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 20 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($1,094.40) and Childress the highest ($1,900.00). The busiest district for this item was Yoakum.
The most recent letting with this item was on Nov 4, 2026 in Brazos County, where Fluor Enterprises, Inc. was the low bidder at $1,047.00 per CY for 347.5 CY against an estimate of $1,000.00.
4 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 416-7006 Drill Shaft (36 IN) (weighted median $270.00 per LF); 416-7040 Drill Shaft (Rdwy ILL Pole) (30 IN) (weighted median $255.00 per LF); 429-7007 Conc STR Repair (Vertical & Overhead) (weighted median $150.00 per SF); 432-7013 Riprap (MOW Strip)(4 IN) (weighted median $645.00 per CY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 51 | 7 | $1,628.25 | $1,560.80 | $1,600.00 | $1,347.30 | $1,950.00 |
| 2025 | 558 | 77 | $1,595.51 | $1,400.00 | $1,500.00 | $1,241.25 | $2,000.00 |
| 2026 | 644 | 82 | $1,361.25 | $1,250.00 | $1,345.00 | $1,100.00 | $1,700.00 |
Quantity bands
| Band | Quantity (CY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–49.3 | 425 | $1,723.23 | $1,500.00 | $1,300.00–$2,020.85 |
| Medium | 51–89.2 | 411 | $1,526.87 | $1,400.00 | $1,190.05–$1,774.59 |
| Large | 92.2–1,253.2 | 417 | $1,403.21 | $1,300.00 | $1,100.00–$1,635.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $1,250.00
- Median second-low unit price
- $1,300.00
- Median engineer’s estimate
- $1,400.00
- Median gap, second vs. low
- +0%
165 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 347.5 CY · Engineer’s estimate $1,000/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $1,047.00/CY | $363,832.50 | — | +4.7% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $1,400.00/CY | $486,500.00 | +$122,668 | +40% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $1,050.00/CY | $364,875.00 | +$1,043 | +5% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $830.00/CY | $288,425.00 | -$75,408 | -17% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $1,007.31/CY | $350,040.23 | -$13,792 | +0.7% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $1,345.00/CY | $467,387.50 | +$103,555 | +34.5% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $1,600.00/CY | $556,000.00 | +$192,168 | +60% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $800.00/CY | $278,000.00 | -$85,833 | -20% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $1,137.84/CY | $395,399.40 | +$31,567 | +13.8% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $800.00/CY | $278,000.00 | -$85,833 | -20% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $1,187.00/CY | $412,482.50 | +$48,650 | +18.7% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $2,173.00/CY | $755,117.50 | +$391,285 | +117.3% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $1,047.00/CY
- Extension
- $363,832.50
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- +4.7%
- Unit price
- $1,400.00/CY
- Extension
- $486,500.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- +40%
- Unit price
- $1,050.00/CY
- Extension
- $364,875.00
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- +5%
- Unit price
- $830.00/CY
- Extension
- $288,425.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- -17%
- Unit price
- $1,007.31/CY
- Extension
- $350,040.23
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- +0.7%
- Unit price
- $1,345.00/CY
- Extension
- $467,387.50
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- +34.5%
- Unit price
- $1,600.00/CY
- Extension
- $556,000.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- +60%
- Unit price
- $800.00/CY
- Extension
- $278,000.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- -20%
9. Zachry Construction Corporation
- Unit price
- $1,137.84/CY
- Extension
- $395,399.40
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- +13.8%
10. Brizo Construction, LLC
- Unit price
- $800.00/CY
- Extension
- $278,000.00
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- -20%
- Unit price
- $1,187.00/CY
- Extension
- $412,482.50
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- +18.7%
- Unit price
- $2,173.00/CY
- Extension
- $755,117.50
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- +117.3%
Proposal 0922-33-234 · let Nov 4, 2026 · Webb County, Laredo District
Line quantity 83.4 CY · Engineer’s estimate $1,500/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Stx CivilLOW BID | $1,039.46/CY | $86,690.96 | — | -30.7% | $2,866,785 | $83,215 (2.9%) left on table |
| 2 | Delgado's Contractors, LLC | $1,750.00/CY | $145,950.00 | +$59,259 | +16.7% | $2,950,000 | +$83,215 |
| 3 | Acee Construction LLC. | $1,222.05/CY | $101,918.97 | +$15,228 | -18.5% | $3,033,273 | +$166,488 |
| 4 | James Construction Group, LLC | $1,297.16/CY | $108,183.14 | +$21,492 | -13.5% | $3,261,472 | +$394,687 |
| 5 | E-Z Bel Construction, LLC | $1,345.00/CY | $112,173.00 | +$25,482 | -10.3% | $3,270,969 | +$404,184 |
| 6 | Lucania Contractors LLC | $2,300.00/CY | $191,820.00 | +$105,129 | +53.3% | $3,466,015 | +$599,230 |
| 7 | Foremost Paving, Inc. | $4,000.00/CY | $333,600.00 | +$246,909 | +166.7% | $5,083,300 | +$2,216,516 |
1. Stx Civil
LOW BID · WINNER- Unit price
- $1,039.46/CY
- Extension
- $86,690.96
- Proposal total
- $2,866,785
- Money left on the table
- $83,215 (2.9%)
- vs. engineer’s estimate
- -30.7%
- Unit price
- $1,750.00/CY
- Extension
- $145,950.00
- Proposal total
- $2,950,000
- vs. low bid
- +$83,215
- vs. engineer’s estimate
- +16.7%
3. Acee Construction LLC.
- Unit price
- $1,222.05/CY
- Extension
- $101,918.97
- Proposal total
- $3,033,273
- vs. low bid
- +$166,488
- vs. engineer’s estimate
- -18.5%
- Unit price
- $1,297.16/CY
- Extension
- $108,183.14
- Proposal total
- $3,261,472
- vs. low bid
- +$394,687
- vs. engineer’s estimate
- -13.5%
- Unit price
- $1,345.00/CY
- Extension
- $112,173.00
- Proposal total
- $3,270,969
- vs. low bid
- +$404,184
- vs. engineer’s estimate
- -10.3%
- Unit price
- $2,300.00/CY
- Extension
- $191,820.00
- Proposal total
- $3,466,015
- vs. low bid
- +$599,230
- vs. engineer’s estimate
- +53.3%
- Unit price
- $4,000.00/CY
- Extension
- $333,600.00
- Proposal total
- $5,083,300
- vs. low bid
- +$2,216,516
- vs. engineer’s estimate
- +166.7%
Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District
Line quantity 768.9 CY · Engineer’s estimate $1,497/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LPLOW BID | $1,397.34/CY | $1,074,414.73 | — | -6.7% | $412,233,374 | $3,506,193 (0.85%) left on table |
| 2 | Pulice Construction, Inc. | $1,400.00/CY | $1,076,460.00 | +$2,045 | -6.5% | $415,739,567 | +$3,506,193 |
| 3 | Fluor Enterprises, Inc. | $1,404.31/CY | $1,079,773.96 | +$5,359 | -6.2% | $473,353,333 | +$61,119,959 |
| 4 | Harper Brothers Construction LLC | $2,115.00/CY | $1,626,223.50 | +$551,809 | +41.3% | $477,550,553 | +$65,317,180 |
| 5 | Webber, LLC | $2,616.47/CY | $2,011,803.78 | +$937,389 | +74.8% | $477,564,067 | +$65,330,694 |
| 6 | Balfour Beatty Infrastructure, Inc. | $1,578.87/CY | $1,213,993.14 | +$139,578 | +5.5% | $492,134,823 | +$79,901,450 |
1. Austin Bridge & Road Services, LP
LOW BID · WINNER- Unit price
- $1,397.34/CY
- Extension
- $1,074,414.73
- Proposal total
- $412,233,374
- Money left on the table
- $3,506,193 (0.85%)
- vs. engineer’s estimate
- -6.7%
2. Pulice Construction, Inc.
- Unit price
- $1,400.00/CY
- Extension
- $1,076,460.00
- Proposal total
- $415,739,567
- vs. low bid
- +$3,506,193
- vs. engineer’s estimate
- -6.5%
3. Fluor Enterprises, Inc.
- Unit price
- $1,404.31/CY
- Extension
- $1,079,773.96
- Proposal total
- $473,353,333
- vs. low bid
- +$61,119,959
- vs. engineer’s estimate
- -6.2%
4. Harper Brothers Construction LLC
- Unit price
- $2,115.00/CY
- Extension
- $1,626,223.50
- Proposal total
- $477,550,553
- vs. low bid
- +$65,317,180
- vs. engineer’s estimate
- +41.3%
5. Webber, LLC
- Unit price
- $2,616.47/CY
- Extension
- $2,011,803.78
- Proposal total
- $477,564,067
- vs. low bid
- +$65,330,694
- vs. engineer’s estimate
- +74.8%
6. Balfour Beatty Infrastructure, Inc.
- Unit price
- $1,578.87/CY
- Extension
- $1,213,993.14
- Proposal total
- $492,134,823
- vs. low bid
- +$79,901,450
- vs. engineer’s estimate
- +5.5%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 347.5 | 12 | Fluor Enterprises, Inc. | $1,047.00 | $1,000.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 83.4 | 7 | Stx Civil | $1,039.46 | $1,500.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 768.9 | 6 | Austin Bridge & Road Services, LP | $1,397.34 | $1,497.00 |
| 2026-11-03 | 0917-30-068 | Burleson | Bryan | 37.8 | 15 | C & W Southern LLC | $1,100.00 | $1,000.00 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 116 | 7 | Longview Bridge and Road, Ltd. | $1,465.00 | $1,300.00 |
| 2026-10-07 | 0922-20-030 | La Salle | Laredo | 17.6 | 6 | Presidio Contracting, LLC | $1,190.00 | $1,600.00 |
| 2026-10-06 | 0912-34-209 | Fort Bend | Houston | 57 | 9 | Garret Shields Infrastructure | $1,200.00 | $1,715.02 |
| 2026-09-03 | 0722-03-016 | Red River | Paris | 56.2 | 8 | Longview Bridge and Road, Ltd. | $900.00 | $1,400.00 |
| 2026-09-03 | 0844-04-011 | Collingsworth | Childress | 40.9 | 7 | Coppell Construction Co., Inc. | $1,350.00 | $1,600.00 |
| 2026-09-03 | 0901-19-198 | Grayson | Paris | 94.6 | 8 | Rb Contracting, LLC | $975.00 | $1,200.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 21 | $950.00 | $1,320.00 | $1,800.00 | — |
| Amarillo | 34 | $1,800.00 | $1,800.00 | $1,550.00 | -26.53% |
| Atlanta | 13 | $950.00 | $1,100.00 | $1,100.00 | — |
| Austin | 44 | $1,397.34 | $1,491.59 | $1,497.00 | — |
| Beaumont | 43 | $1,200.00 | $1,200.00 | $1,200.00 | -12.01% |
| Brownwood | 9 | $1,500.00 | $1,891.00 | $1,800.00 | — |
| Bryan | 92 | $1,047.00 | $1,187.00 | $1,000.00 | -28.82% |
| Childress | 31 | $1,350.00 | $1,900.00 | $1,510.00 | -13.64% |
| Corpus Christi | 92 | $1,500.00 | $1,500.00 | $1,500.00 | -11.76% |
| Fort Worth | 9 | $1,100.00 | $1,400.00 | $1,800.00 | — |
| Houston | 71 | $827.15 | $1,200.00 | $1,400.00 | — |
| Laredo | 50 | $1,330.00 | $1,345.00 | $1,300.00 | — |
| Lubbock | 13 | $1,800.00 | $1,600.00 | $400.00 | — |
| Lufkin | 69 | $1,465.00 | $1,210.00 | $1,300.00 | -10.36% |
| Odessa | 9 | $1,540.00 | $1,117.20 | $1,500.00 | — |
| Paris | 96 | $975.00 | $1,100.00 | $1,200.00 | -18.22% |
| Pharr | 45 | $1,000.00 | $1,094.40 | $1,350.00 | -1.9% |
| San Angelo | 26 | $1,800.00 | $1,500.00 | $1,500.00 | -16.67% |
| San Antonio | 72 | $1,050.00 | $1,151.99 | $1,200.00 | -1.86% |
| Tyler | 66 | $1,050.00 | $1,122.00 | $1,600.00 | -18.23% |
| Waco | 57 | $1,200.00 | $1,325.00 | $1,400.00 | -27.71% |
| Wichita Falls | 27 | $1,250.00 | $1,250.00 | $2,000.00 | — |
| Yoakum | 264 | $1,300.00 | $1,300.00 | $1,250.00 | -2.39% |
Related items
- 416-7006 · Drill Shaft (36 IN) ($270.00/LF)
- 416-7040 · Drill Shaft (Rdwy ILL Pole) (30 IN) ($255.00/LF)
- 429-7007 · Conc STR Repair (Vertical & Overhead) ($150.00/SF)
- 432-7013 · Riprap (MOW Strip)(4 IN) ($645.00/CY)
- 432-7001 · Riprap (Conc)(4 IN) ($515.00/CY)
- 432-7043 · Riprap (Stone Protection)(18 IN) ($189.00/CY)
- 432-7002 · Riprap (Conc)(5 IN) ($587.00/CY)
- 432-7041 · Riprap (Stone Protection)(12 IN) ($185.00/CY)
Is your price for item 420-7012 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.