Riprap (Stone Protection)(12 IN) (Item 432-7041): TxDOT Unit Price History
1,160 bids · 171 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure CY
TxDOT 432-7041 · RIPRAP (STONE PROTECTION)(12 IN) · Unit: CY
- Low bid
- $150.00/CY
- Quantity-weighted median of winning unit prices
- Weighted median
- $185.00/CY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $160.00/CY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -5.51%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 432-7041 (Riprap (Stone Protection)(12 IN)) is measured in CY. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 1,160 bids for it on 171 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 553 bids was $185.00 per CY, and the winning low bidders priced it at a weighted median of $150.00 per CY.
TxDOT's engineer's estimate for the same lines had a weighted median of $160.00 per CY, so winning bids came in 6.3% below the estimate.
By calendar year, the median bid moved from $229.88 in 2025 (574 bids) to $215.00 in 2026 (545 bids), down 6.5%. The middle half of 2026 bids fell between $176.82 and $275.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 5.51%.
Quantity matters for this item. Lines of 1 to 97 CY had a weighted median of $250.00, while lines above 398 CY had $185.00, a 26% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 165 lines where both a winning and a second-place bid were published, the median winning unit price was $200.00 against $220.00 from the second-lowest bidder, a median gap of 10% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 20 TxDOT districts with at least ten bids, Dallas had the lowest weighted median ($169.83) and Beaumont the highest ($300.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 12, 2026 in Denton County, where Road Doctors LLC was the low bidder at $250.00 per CY for 22 CY against an estimate of $190.00.
19 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 432-7013 Riprap (MOW Strip)(4 IN) (weighted median $645.00 per CY); 432-7001 Riprap (Conc)(4 IN) (weighted median $515.00 per CY); 432-7043 Riprap (Stone Protection)(18 IN) (weighted median $189.00 per CY); 432-7002 Riprap (Conc)(5 IN) (weighted median $587.00 per CY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 41 | 7 | $238.67 | $225.00 | $240.00 | $179.91 | $300.00 |
| 2025 | 574 | 84 | $221.36 | $200.00 | $229.88 | $185.00 | $300.00 |
| 2026 | 545 | 80 | $191.62 | $185.00 | $215.00 | $176.82 | $275.00 |
Quantity bands
| Band | Quantity (CY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–97 | 389 | $295.38 | $250.00 | $200.00–$370.00 |
| Medium | 98–390 | 385 | $236.77 | $220.00 | $177.34–$265.00 |
| Large | 398–12,465.6 | 386 | $195.62 | $185.00 | $165.38–$250.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $200.00
- Median second-low unit price
- $220.00
- Median engineer’s estimate
- $225.00
- Median gap, second vs. low
- +10%
165 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6497-55-001 · let Nov 12, 2026 · Denton County, Dallas District
Line quantity 22 CY · Engineer’s estimate $190.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Road Doctors LLCLOW BID | $250.00/CY | $5,500.00 | — | +31.6% | $493,320 | $25,748 (5.22%) left on table |
| 2 | Icos Management, LLC | $189.00/CY | $4,158.00 | -$1,342 | -0.5% | $519,068 | +$25,748 |
| 3 | Texas Road Construction, LLC | $275.00/CY | $6,050.00 | +$550.00 | +44.7% | $567,220 | +$73,900 |
| 4 | Rear Contractors LLC | $250.00/CY | $5,500.00 | $0.000 | +31.6% | $598,798 | +$105,478 |
| 5 | Premier Contractors LLC | $300.00/CY | $6,600.00 | +$1,100 | +57.9% | $654,688 | +$161,368 |
| 6 | Jr West Texas Concrete LLC | $418.00/CY | $9,196.00 | +$3,696 | +120% | $746,209 | +$252,889 |
- LOW BID · WINNER
- Unit price
- $250.00/CY
- Extension
- $5,500.00
- Proposal total
- $493,320
- Money left on the table
- $25,748 (5.22%)
- vs. engineer’s estimate
- +31.6%
- Unit price
- $189.00/CY
- Extension
- $4,158.00
- Proposal total
- $519,068
- vs. low bid
- +$25,748
- vs. engineer’s estimate
- -0.5%
- Unit price
- $275.00/CY
- Extension
- $6,050.00
- Proposal total
- $567,220
- vs. low bid
- +$73,900
- vs. engineer’s estimate
- +44.7%
- Unit price
- $250.00/CY
- Extension
- $5,500.00
- Proposal total
- $598,798
- vs. low bid
- +$105,478
- vs. engineer’s estimate
- +31.6%
- Unit price
- $300.00/CY
- Extension
- $6,600.00
- Proposal total
- $654,688
- vs. low bid
- +$161,368
- vs. engineer’s estimate
- +57.9%
6. Jr West Texas Concrete LLC
- Unit price
- $418.00/CY
- Extension
- $9,196.00
- Proposal total
- $746,209
- vs. low bid
- +$252,889
- vs. engineer’s estimate
- +120%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 12,465.6 CY · Engineer’s estimate $125.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $100.00/CY | $1,246,560.00 | — | -20% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $185.00/CY | $2,306,136.00 | +$1,059,576 | +48% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $150.00/CY | $1,869,840.00 | +$623,280 | +20% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $192.25/CY | $2,396,511.60 | +$1,149,952 | +53.8% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $176.82/CY | $2,204,167.39 | +$957,607 | +41.5% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $101.49/CY | $1,265,133.74 | +$18,574 | -18.8% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $100.00/CY
- Extension
- $1,246,560.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -20%
2. Rpm Xconstruction, LLC
- Unit price
- $185.00/CY
- Extension
- $2,306,136.00
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +48%
- Unit price
- $150.00/CY
- Extension
- $1,869,840.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- +20%
4. Webber, LLC
- Unit price
- $192.25/CY
- Extension
- $2,396,511.60
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +53.8%
5. Sema Construction, Inc.
- Unit price
- $176.82/CY
- Extension
- $2,204,167.39
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +41.5%
6. Zachry Construction Corporation
- Unit price
- $101.49/CY
- Extension
- $1,265,133.74
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -18.8%
Proposal 0922-33-234 · let Nov 4, 2026 · Webb County, Laredo District
Line quantity 1,052 CY · Engineer’s estimate $170.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Stx CivilLOW BID | $142.96/CY | $150,393.92 | — | -15.9% | $2,866,785 | $83,215 (2.9%) left on table |
| 2 | Delgado's Contractors, LLC | $200.00/CY | $210,400.00 | +$60,006 | +17.6% | $2,950,000 | +$83,215 |
| 3 | Acee Construction LLC. | $245.00/CY | $257,740.00 | +$107,346 | +44.1% | $3,033,273 | +$166,488 |
| 4 | James Construction Group, LLC | $275.95/CY | $290,299.40 | +$139,905 | +62.3% | $3,261,472 | +$394,687 |
| 5 | E-Z Bel Construction, LLC | $205.00/CY | $215,660.00 | +$65,266 | +20.6% | $3,270,969 | +$404,184 |
| 6 | Lucania Contractors LLC | $180.00/CY | $189,360.00 | +$38,966 | +5.9% | $3,466,015 | +$599,230 |
| 7 | Foremost Paving, Inc. | $250.00/CY | $263,000.00 | +$112,606 | +47.1% | $5,083,300 | +$2,216,516 |
1. Stx Civil
LOW BID · WINNER- Unit price
- $142.96/CY
- Extension
- $150,393.92
- Proposal total
- $2,866,785
- Money left on the table
- $83,215 (2.9%)
- vs. engineer’s estimate
- -15.9%
- Unit price
- $200.00/CY
- Extension
- $210,400.00
- Proposal total
- $2,950,000
- vs. low bid
- +$83,215
- vs. engineer’s estimate
- +17.6%
3. Acee Construction LLC.
- Unit price
- $245.00/CY
- Extension
- $257,740.00
- Proposal total
- $3,033,273
- vs. low bid
- +$166,488
- vs. engineer’s estimate
- +44.1%
- Unit price
- $275.95/CY
- Extension
- $290,299.40
- Proposal total
- $3,261,472
- vs. low bid
- +$394,687
- vs. engineer’s estimate
- +62.3%
- Unit price
- $205.00/CY
- Extension
- $215,660.00
- Proposal total
- $3,270,969
- vs. low bid
- +$404,184
- vs. engineer’s estimate
- +20.6%
- Unit price
- $180.00/CY
- Extension
- $189,360.00
- Proposal total
- $3,466,015
- vs. low bid
- +$599,230
- vs. engineer’s estimate
- +5.9%
- Unit price
- $250.00/CY
- Extension
- $263,000.00
- Proposal total
- $5,083,300
- vs. low bid
- +$2,216,516
- vs. engineer’s estimate
- +47.1%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-12 | 6497-55-001 | Denton | Dallas | 22 | 6 | Road Doctors LLC | $250.00 | $190.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 12,465.6 | 6 | Indus Road & Bridge, Inc. | $100.00 | $125.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 1,052 | 7 | Stx Civil | $142.96 | $170.00 |
| 2026-10-07 | 0922-20-030 | La Salle | Laredo | 48 | 6 | Presidio Contracting, LLC | $250.00 | $350.00 |
| 2026-10-06 | 0095-03-100 | Kaufman | Dallas | 4,540 | 10 | Highway 19 Construction LLC | $150.00 | $150.00 |
| 2026-10-06 | 0387-01-016 | Collin | Dallas | 601 | 8 | A. K. Gillis & Sons, LLC | $273.20 | $300.00 |
| 2026-10-06 | 0410-02-047 | Grayson | Paris | 177 | 7 | Highway 19 Construction LLC | $150.00 | $255.00 |
| 2026-10-06 | 1122-01-034 | Karnes | Corpus Christi | 17.03 | 7 | Ck Newberry, LLC | $400.00 | $175.00 |
| 2026-09-09 | 6494-80-001 | Navarro | Dallas | 10 | 5 | Garret Shields Infrastructure | $200.00 | $250.00 |
| 2026-09-09 | 6498-35-001 | Collin | Dallas | 318 | 3 | Texas Road Construction, LLC | $175.00 | $154.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 67 | $150.00 | $200.00 | $250.00 | +2.22% |
| Amarillo | 12 | $221.95 | $300.00 | $330.00 | — |
| Atlanta | 41 | $160.00 | $197.00 | $180.00 | +10.41% |
| Austin | 39 | $175.49 | $200.00 | $200.00 | -28.99% |
| Beaumont | 35 | $200.00 | $300.00 | $180.00 | +8.11% |
| Brownwood | 36 | $145.00 | $275.00 | $400.00 | — |
| Bryan | 46 | $160.00 | $220.00 | $315.27 | — |
| Corpus Christi | 47 | $132.27 | $200.00 | $320.00 | -13.79% |
| Dallas | 241 | $120.00 | $169.83 | $125.00 | -9.76% |
| El Paso | 9 | $250.00 | $280.00 | $600.00 | — |
| Fort Worth | 29 | $160.00 | $200.00 | $235.00 | — |
| Houston | 24 | $230.59 | $225.00 | $250.00 | -18.64% |
| Laredo | 30 | $142.96 | $205.00 | $170.00 | — |
| Lubbock | 5 | $200.00 | $258.11 | $160.00 | — |
| Odessa | 1 | — | $710.00 | — | — |
| Paris | 85 | $186.00 | $200.00 | $213.00 | -11.16% |
| Pharr | 48 | $210.00 | $222.20 | $200.00 | -18.29% |
| San Angelo | 29 | $660.00 | $250.00 | $240.00 | +20% |
| San Antonio | 57 | $319.30 | $200.00 | $260.00 | — |
| Tyler | 25 | $87.20 | $208.36 | $210.00 | -0.47% |
| Waco | 60 | $150.00 | $180.00 | $180.00 | -3.75% |
| Wichita Falls | 80 | $160.00 | $212.00 | $221.45 | +22.67% |
| Yoakum | 114 | $250.00 | $218.00 | $226.00 | +5.86% |
Related items
- 432-7013 · Riprap (MOW Strip)(4 IN) ($645.00/CY)
- 432-7001 · Riprap (Conc)(4 IN) ($515.00/CY)
- 432-7043 · Riprap (Stone Protection)(18 IN) ($189.00/CY)
- 432-7002 · Riprap (Conc)(5 IN) ($587.00/CY)
- 429-7007 · Conc STR Repair (Vertical & Overhead) ($150.00/SF)
- 438-7007 · Cleaning AND Sealing Exist Joints (CL7) ($40.00/LF)
- 420-7012 · CL C Conc (Abut) ($1,250.00/CY)
- 416-7006 · Drill Shaft (36 IN) ($270.00/LF)
Is your price for item 432-7041 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.