Cleaning AND Sealing Exist Joints (CL7) (Item 438-7007): TxDOT Unit Price History
1,084 bids · 152 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure LF
TxDOT 438-7007 · CLEANING AND SEALING EXIST JOINTS (CL7) · Unit: LF
- Low bid
- $34.14/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $40.00/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $43.00/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -10.91%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 438-7007 (Cleaning AND Sealing Exist Joints (CL7)) is measured in LF. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 1,084 bids for it on 152 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 566 bids was $40.00 per LF, and the winning low bidders priced it at a weighted median of $34.14 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $43.00 per LF, so winning bids came in 20.6% below the estimate.
By calendar year, the median bid moved from $55.00 in 2025 (505 bids) to $47.25 in 2026 (530 bids), down 14.1%. The middle half of 2026 bids fell between $35.25 and $60.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 10.91%.
Quantity matters for this item. Lines of 20 to 264 LF had a weighted median of $56.00, while lines above 1,059 LF had $42.00, a 25% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 153 lines where both a winning and a second-place bid were published, the median winning unit price was $46.64 against $48.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 21 TxDOT districts with at least ten bids, San Antonio had the lowest weighted median ($15.00) and Bryan the highest ($70.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 12, 2026 in Potter County, where Infratex Construction LLC was the low bidder at $34.14 per LF for 4,636 LF against an estimate of $60.00.
3 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 432-7013 Riprap (MOW Strip)(4 IN) (weighted median $645.00 per CY); 432-7001 Riprap (Conc)(4 IN) (weighted median $515.00 per CY); 432-7043 Riprap (Stone Protection)(18 IN) (weighted median $189.00 per CY); 432-7002 Riprap (Conc)(5 IN) (weighted median $587.00 per CY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 49 | 7 | $67.28 | $62.00 | $65.00 | $50.00 | $80.00 |
| 2025 | 505 | 77 | $54.71 | $50.00 | $55.00 | $45.00 | $75.00 |
| 2026 | 530 | 70 | $41.59 | $40.00 | $47.25 | $35.25 | $60.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 20–264 | 373 | $64.39 | $56.00 | $45.00–$80.00 |
| Medium | 272–1,016 | 353 | $54.07 | $50.00 | $40.00–$65.00 |
| Large | 1,059–22,429 | 358 | $45.26 | $42.00 | $35.00–$57.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $46.64
- Median second-low unit price
- $48.00
- Median engineer’s estimate
- $50.00
- Median gap, second vs. low
- +0%
153 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6508-80-001 · let Nov 12, 2026 · Potter County, Amarillo District
Line quantity 4,636 LF · Engineer’s estimate $60.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Infratex Construction LLCLOW BID | $34.14/LF | $158,273.04 | — | -43.1% | $306,731 | $80,184 (26.14%) left on table |
| 2 | Rear Contractors LLC | $35.00/LF | $162,260.00 | +$3,987 | -41.7% | $386,915 | +$80,184 |
| 3 | Premier Contractors LLC | $45.00/LF | $208,620.00 | +$50,347 | -25% | $485,032 | +$178,301 |
| 4 | 12twelve Road and Bridge LLC | $50.00/LF | $231,800.00 | +$73,527 | -16.7% | $488,466 | +$181,735 |
| 5 | Scr Civil Construction, LLC | $34.00/LF | $157,624.00 | -$649.04 | -43.3% | $547,310 | +$240,579 |
| 6 | Ti-Zack Concrete, LLC | $50.60/LF | $234,581.60 | +$76,309 | -15.7% | $563,794 | +$257,063 |
| 7 | Road Doctors LLC | $50.00/LF | $231,800.00 | +$73,527 | -16.7% | $574,214 | +$267,483 |
| 8 | Icos Management, LLC | $47.25/LF | $219,051.00 | +$60,778 | -21.3% | $578,045 | +$271,314 |
| 9 | Boen Landscaping & Irrigation, LLC | $48.00/LF | $222,528.00 | +$64,255 | -20% | $600,851 | +$294,120 |
| 10 | Structural Integrity Group LLC | $53.00/LF | $245,708.00 | +$87,435 | -11.7% | $622,169 | +$315,438 |
| 11 | Pathfield Investments LLC | $45.00/LF | $208,620.00 | +$50,347 | -25% | $627,520 | +$320,789 |
| 12 | Winding Road Construction, Inc. | $54.00/LF | $250,344.00 | +$92,071 | -10% | $633,450 | +$326,719 |
| 13 | O. Trevino Construction, LLC | $30.00/LF | $139,080.00 | -$19,193 | -50% | $732,872 | +$426,141 |
| 14 | The Truesdell Corporation | $47.00/LF | $217,892.00 | +$59,619 | -21.7% | $844,844 | +$538,113 |
1. Infratex Construction LLC
LOW BID · WINNER- Unit price
- $34.14/LF
- Extension
- $158,273.04
- Proposal total
- $306,731
- Money left on the table
- $80,184 (26.14%)
- vs. engineer’s estimate
- -43.1%
- Unit price
- $35.00/LF
- Extension
- $162,260.00
- Proposal total
- $386,915
- vs. low bid
- +$80,184
- vs. engineer’s estimate
- -41.7%
- Unit price
- $45.00/LF
- Extension
- $208,620.00
- Proposal total
- $485,032
- vs. low bid
- +$178,301
- vs. engineer’s estimate
- -25%
- Unit price
- $50.00/LF
- Extension
- $231,800.00
- Proposal total
- $488,466
- vs. low bid
- +$181,735
- vs. engineer’s estimate
- -16.7%
- Unit price
- $34.00/LF
- Extension
- $157,624.00
- Proposal total
- $547,310
- vs. low bid
- +$240,579
- vs. engineer’s estimate
- -43.3%
- Unit price
- $50.60/LF
- Extension
- $234,581.60
- Proposal total
- $563,794
- vs. low bid
- +$257,063
- vs. engineer’s estimate
- -15.7%
- Unit price
- $50.00/LF
- Extension
- $231,800.00
- Proposal total
- $574,214
- vs. low bid
- +$267,483
- vs. engineer’s estimate
- -16.7%
- Unit price
- $47.25/LF
- Extension
- $219,051.00
- Proposal total
- $578,045
- vs. low bid
- +$271,314
- vs. engineer’s estimate
- -21.3%
- Unit price
- $48.00/LF
- Extension
- $222,528.00
- Proposal total
- $600,851
- vs. low bid
- +$294,120
- vs. engineer’s estimate
- -20%
- Unit price
- $53.00/LF
- Extension
- $245,708.00
- Proposal total
- $622,169
- vs. low bid
- +$315,438
- vs. engineer’s estimate
- -11.7%
- Unit price
- $45.00/LF
- Extension
- $208,620.00
- Proposal total
- $627,520
- vs. low bid
- +$320,789
- vs. engineer’s estimate
- -25%
- Unit price
- $54.00/LF
- Extension
- $250,344.00
- Proposal total
- $633,450
- vs. low bid
- +$326,719
- vs. engineer’s estimate
- -10%
- Unit price
- $30.00/LF
- Extension
- $139,080.00
- Proposal total
- $732,872
- vs. low bid
- +$426,141
- vs. engineer’s estimate
- -50%
- Unit price
- $47.00/LF
- Extension
- $217,892.00
- Proposal total
- $844,844
- vs. low bid
- +$538,113
- vs. engineer’s estimate
- -21.7%
Proposal 0157-04-058 · let Nov 4, 2026 · Haskell County, Abilene District
Line quantity 388 LF · Engineer’s estimate $70.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Paving CompanyLOW BID | $50.00/LF | $19,400.00 | — | -28.6% | $6,732,215 | $1,063,968 (15.8%) left on table |
| 2 | Rk Hall, LLC | $53.00/LF | $20,564.00 | +$1,164 | -24.3% | $7,796,183 | +$1,063,968 |
| 3 | Zack Burkett Co. | $55.70/LF | $21,611.60 | +$2,212 | -20.4% | $7,966,171 | +$1,233,956 |
| 4 | Foutsco Paving Company, LLC | $51.00/LF | $19,788.00 | +$388.00 | -27.1% | $8,000,580 | +$1,268,365 |
| 5 | Nobles Road Construction, Inc. | $53.50/LF | $20,758.00 | +$1,358 | -23.6% | $8,307,427 | +$1,575,212 |
| 6 | Ck Newberry, LLC | $60.00/LF | $23,280.00 | +$3,880 | -14.3% | $8,389,000 | +$1,656,785 |
| 7 | Reece Albert, Inc. | $62.25/LF | $24,153.00 | +$4,753 | -11.1% | $8,534,153 | +$1,801,938 |
| 8 | Texas Materials Group, Inc. | $37.00/LF | $14,356.00 | -$5,044 | -47.1% | $8,617,318 | +$1,885,103 |
| 9 | A. L. Helmcamp, Inc. | $57.00/LF | $22,116.00 | +$2,716 | -18.6% | $9,257,856 | +$2,525,641 |
- LOW BID · WINNER
- Unit price
- $50.00/LF
- Extension
- $19,400.00
- Proposal total
- $6,732,215
- Money left on the table
- $1,063,968 (15.8%)
- vs. engineer’s estimate
- -28.6%
2. Rk Hall, LLC
- Unit price
- $53.00/LF
- Extension
- $20,564.00
- Proposal total
- $7,796,183
- vs. low bid
- +$1,063,968
- vs. engineer’s estimate
- -24.3%
- Unit price
- $55.70/LF
- Extension
- $21,611.60
- Proposal total
- $7,966,171
- vs. low bid
- +$1,233,956
- vs. engineer’s estimate
- -20.4%
- Unit price
- $51.00/LF
- Extension
- $19,788.00
- Proposal total
- $8,000,580
- vs. low bid
- +$1,268,365
- vs. engineer’s estimate
- -27.1%
5. Nobles Road Construction, Inc.
- Unit price
- $53.50/LF
- Extension
- $20,758.00
- Proposal total
- $8,307,427
- vs. low bid
- +$1,575,212
- vs. engineer’s estimate
- -23.6%
- Unit price
- $60.00/LF
- Extension
- $23,280.00
- Proposal total
- $8,389,000
- vs. low bid
- +$1,656,785
- vs. engineer’s estimate
- -14.3%
- Unit price
- $62.25/LF
- Extension
- $24,153.00
- Proposal total
- $8,534,153
- vs. low bid
- +$1,801,938
- vs. engineer’s estimate
- -11.1%
- Unit price
- $37.00/LF
- Extension
- $14,356.00
- Proposal total
- $8,617,318
- vs. low bid
- +$1,885,103
- vs. engineer’s estimate
- -47.1%
- Unit price
- $57.00/LF
- Extension
- $22,116.00
- Proposal total
- $9,257,856
- vs. low bid
- +$2,525,641
- vs. engineer’s estimate
- -18.6%
Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District
Line quantity 322 LF · Engineer’s estimate $62.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LPLOW BID | $46.87/LF | $15,092.14 | — | -24.4% | $412,233,374 | $3,506,193 (0.85%) left on table |
| 2 | Pulice Construction, Inc. | $50.00/LF | $16,100.00 | +$1,008 | -19.4% | $415,739,567 | +$3,506,193 |
| 3 | Fluor Enterprises, Inc. | $85.58/LF | $27,556.76 | +$12,465 | +38% | $473,353,333 | +$61,119,959 |
| 4 | Harper Brothers Construction LLC | $170.18/LF | $54,797.96 | +$39,706 | +174.5% | $477,550,553 | +$65,317,180 |
| 5 | Webber, LLC | $94.19/LF | $30,329.18 | +$15,237 | +51.9% | $477,564,067 | +$65,330,694 |
| 6 | Balfour Beatty Infrastructure, Inc. | $63.70/LF | $20,511.40 | +$5,419 | +2.7% | $492,134,823 | +$79,901,450 |
1. Austin Bridge & Road Services, LP
LOW BID · WINNER- Unit price
- $46.87/LF
- Extension
- $15,092.14
- Proposal total
- $412,233,374
- Money left on the table
- $3,506,193 (0.85%)
- vs. engineer’s estimate
- -24.4%
2. Pulice Construction, Inc.
- Unit price
- $50.00/LF
- Extension
- $16,100.00
- Proposal total
- $415,739,567
- vs. low bid
- +$3,506,193
- vs. engineer’s estimate
- -19.4%
3. Fluor Enterprises, Inc.
- Unit price
- $85.58/LF
- Extension
- $27,556.76
- Proposal total
- $473,353,333
- vs. low bid
- +$61,119,959
- vs. engineer’s estimate
- +38%
4. Harper Brothers Construction LLC
- Unit price
- $170.18/LF
- Extension
- $54,797.96
- Proposal total
- $477,550,553
- vs. low bid
- +$65,317,180
- vs. engineer’s estimate
- +174.5%
5. Webber, LLC
- Unit price
- $94.19/LF
- Extension
- $30,329.18
- Proposal total
- $477,564,067
- vs. low bid
- +$65,330,694
- vs. engineer’s estimate
- +51.9%
6. Balfour Beatty Infrastructure, Inc.
- Unit price
- $63.70/LF
- Extension
- $20,511.40
- Proposal total
- $492,134,823
- vs. low bid
- +$79,901,450
- vs. engineer’s estimate
- +2.7%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-12 | 6508-80-001 | Potter | Amarillo | 4,636 | 14 | Infratex Construction LLC | $34.14 | $60.00 |
| 2026-11-04 | 0157-04-058 | Haskell | Abilene | 388 | 9 | Lone Star Paving Company | $50.00 | $70.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 322 | 6 | Austin Bridge & Road Services, LP | $46.87 | $62.00 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 98 | 6 | A. K. Gillis & Sons, LLC | $38.00 | $40.00 |
| 2026-10-07 | 6504-67-001 | Harris | Houston | 7,000 | 4 | Isi Contracting, Inc. | $9.00 | $28.47 |
| 2026-10-06 | 0204-01-075 | Williamson | Austin | 20 | 14 | Taylor Bridge LLC | $50.00 | $57.00 |
| 2026-10-06 | 6499-74-001 | Comanche | Brownwood | 216 | 11 | Taylor Bridge LLC | $30.00 | $45.00 |
| 2026-09-22 | 6492-74-001 | Taylor | Abilene | 328 | 12 | Blacksmith Ventures LLC | $25.00 | $45.00 |
| 2026-08-20 | 6493-78-001 | Fannin | Paris | 484 | 8 | Gibson & Associates, Inc. | $52.00 | $50.00 |
| 2026-08-11 | 6501-71-001 | Smith | Tyler | 1,352 | 11 | Infratex Construction LLC | $35.00 | $30.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 98 | $46.00 | $48.00 | $50.00 | -14.41% |
| Amarillo | 38 | $34.14 | $47.25 | $60.00 | — |
| Austin | 108 | $50.00 | $55.00 | $62.00 | -1.08% |
| Beaumont | 44 | $28.00 | $35.00 | $38.00 | -39.13% |
| Brownwood | 27 | $40.00 | $40.00 | $53.00 | — |
| Bryan | 13 | $48.00 | $70.00 | $55.00 | — |
| Childress | 13 | $30.00 | $42.00 | $58.00 | — |
| Dallas | 119 | $29.63 | $34.50 | $45.00 | -15.09% |
| El Paso | 17 | $50.00 | $55.00 | $70.00 | — |
| Fort Worth | 113 | $45.00 | $42.50 | $75.00 | -7.98% |
| Houston | 102 | $30.00 | $40.00 | $38.00 | -15% |
| Laredo | 14 | $50.00 | $60.00 | $30.00 | — |
| Lufkin | 39 | $40.00 | $40.00 | $35.00 | -11.11% |
| Odessa | 42 | $50.00 | $50.00 | $44.95 | — |
| Paris | 41 | $47.08 | $50.00 | $50.00 | — |
| Pharr | 6 | $50.00 | $95.00 | $50.00 | — |
| San Angelo | 43 | $29.00 | $45.00 | $43.00 | — |
| San Antonio | 25 | $15.00 | $15.00 | $45.00 | -51.27% |
| Tyler | 75 | $35.00 | $40.00 | $30.00 | -29.58% |
| Waco | 54 | $50.00 | $55.00 | $45.00 | -11.29% |
| Wichita Falls | 39 | $47.25 | $33.50 | $50.00 | -27.17% |
| Yoakum | 14 | $42.00 | $48.46 | $62.00 | — |
Related items
- 432-7013 · Riprap (MOW Strip)(4 IN) ($645.00/CY)
- 432-7001 · Riprap (Conc)(4 IN) ($515.00/CY)
- 432-7043 · Riprap (Stone Protection)(18 IN) ($189.00/CY)
- 432-7002 · Riprap (Conc)(5 IN) ($587.00/CY)
- 432-7041 · Riprap (Stone Protection)(12 IN) ($185.00/CY)
- 429-7007 · Conc STR Repair (Vertical & Overhead) ($150.00/SF)
- 420-7012 · CL C Conc (Abut) ($1,250.00/CY)
- 416-7006 · Drill Shaft (36 IN) ($270.00/LF)