O. Trevino Construction, LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: O. TREVINO CONSTRUCTION, LLC · Data as published by TxDOT, lettings Nov 13, 2024 to Nov 12, 2026, retrieved Nov 24, 2026.

Proposals bid
109
Low bids (rank 1)
20
Win rate
18.35%
Low-bid value
$52.2M
Money left on table
$4.7M
Avg. bid vs. estimate
+17.03%

From Nov 13, 2024 to Nov 12, 2026, O. Trevino Construction, LLC submitted 109 bids on TxDOT proposals and was the apparent low bidder on 20 of them (18.35%), with low bids totalling $52,230,064. In 19 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $4,716,067 (9.15% of those bids); the median gap was 8.32%. On average its bids came in 17.03% above TxDOT's engineer's estimate. Its most frequent district was Dallas (36 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
2024200.0%$0
202553815.1%$24,368,925
2026541222.2%$27,861,139

Head-to-head rivals

BidderProposals togetherRanked ahead
Garret Shields Infrastructure4114 of 41
Grey Sky Construction LLC2822 of 28
Structural Integrity Group LLC225 of 22
Winding Road Construction, Inc.208 of 20
Roy Jorgensen Associates, Inc.199 of 19
Ti-Zack Concrete, LLC197 of 19
Icos Management, LLC185 of 18
Stx Civil174 of 17

Districts and work types

DistrictBids
Dallas36
Fort Worth11
Paris8
Tyler6
Beaumont5
Work type of low bidsLow bids
Rehabilitation of Existing Road7
Routine Maintenance Project - Sealed4
Safety Improvement Projects4
Restoration2
Overlay1
Routine Maintenance Project1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2026-04-071245-02-052PotterL A Fuller & Sons Construction, Ltd.$7,487,324$7,598,853+1.5%
2025-12-026489-09-001KaufmanRoy Jorgensen Associates, Inc.$1,708,740$1,738,075+1.7%
2025-09-040581-01-171DallasFoutsco Paving Company, LLC$6,104,473$6,246,498+2.3%
2025-05-020718-02-076TarrantGrey Sky Construction LLC$6,426,835$6,622,014+3%
2026-06-026501-09-001WheelerWinding Road Construction, Inc.$847,645$880,255+3.9%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-126508-80-001PotterBridge Preventative Maintenance - Sealed13 of 14$732,872+138.9%+19.5%
2026-11-126509-36-001CollinRoutine Maintenance Project - Sealed4 of 6$765,100+24.3%-17.3%
2026-11-040353-01-031WiseIntersection & Operational Imprv3 of 7$594,655+23.3%-4.1%
2026-11-046504-98-001Tom GreenRoutine Maintenance Project - Sealed2 of 4$4,241,563+35.8%+136.4%
2026-11-046508-43-001DonleyBridge Preventative Maintenance - Sealed9 of 16$994,725+41.7%-12%
2026-11-036508-47-001ChildressBridge Preventative Maintenance - Sealed7 of 15$1,136,685+43.4%-0.6%
2026-10-146504-79-001KaufmanRoutine Maintenance Project - Sealed3 of 4$373,900+84.1%+38.1%
2026-10-060168-03-040ParmerSafety Improvement Projects6 of 6$2,605,040+53.5%+17.5%
2026-10-066497-96-001VictoriaRoutine Maintenance Project - Sealed5 of 5$2,170,000+42.6%+60%
2026-09-096503-05-001CollinRoutine Maintenance Project - Sealed2 of 7$705,640+4.1%-22.2%
2026-09-032266-02-169TarrantRehabilitation of Existing Road2 of 6$4,914,580+7.3%-5.5%
2026-09-020172-09-047TarrantRehabilitation of Existing Road1 of 7$2,623,267—-25.4%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.