Proposals bid
204
Low bids (rank 1)
23
Win rate
11.27%
Low-bid value
$173.9M
Money left on table
$7.2M
Avg. bid vs. estimate
+8.73%

From Nov 6, 2024 to Nov 17, 2026, Ck Newberry, LLC submitted 204 bids on TxDOT proposals and was the apparent low bidder on 23 of them (11.27%), with low bids totalling $173,928,291. In 22 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $7,223,319 (4.16% of those bids); the median gap was 3.15%. On average its bids came in 8.73% above TxDOT's engineer's estimate. Its most frequent district was Corpus Christi (41 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
20241516.7%$192,590
20251041312.5%$102,840,902
202685910.6%$70,894,800

Head-to-head rivals

BidderProposals togetherRanked ahead
Hunter Industries, Ltd.6111 of 61
Clark Construction of Texas, Inc.5520 of 55
Anderson Columbia Co., Inc.4117 of 41
Texas Materials Group, Inc.4020 of 40
Ronald R. Wagner & Co., LP388 of 38
A. L. Helmcamp, Inc.3720 of 37
Stx Civil3212 of 32
J. Carroll Weaver, Inc.2914 of 29

Districts and work types

DistrictBids
Corpus Christi41
Abilene22
Pharr20
San Antonio18
Yoakum18
Work type of low bidsLow bids
Overlay6
Routine Maintenance Project - Sealed5
Rehabilitation of Existing Road3
Seal Coat3
Material Maintenance Project2
Bridge Replacement1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2025-08-080237-03-036WebbAnderson Columbia Co., Inc.$31,130,076$31,277,983+0.5%
2025-04-036480-88-001KarnesHunter Industries, Ltd.$1,289,866$1,297,809+0.6%
2025-09-056484-08-001KinneyRonald R. Wagner & Co., LP$5,349,596$5,390,718+0.8%
2025-02-060700-01-049BurnetHunter Industries, Ltd.$7,072,728$7,134,114+0.9%
2025-10-090074-02-083Live OakRonald R. Wagner & Co., LP$7,741,175$7,953,867+2.8%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-176509-21-001Jim WellsMaterial Maintenance Project1 of 4$427,000—-14.3%
2026-11-176509-22-001Live OakMaterial Maintenance Project1 of 3$370,000—0%
2026-11-176511-71-001KlebergMaterial Maintenance Project3 of 5$615,000+9.2%+19.4%
2026-11-040007-05-016EastlandSeal Coat4 of 4$11,265,688+20.7%+25.5%
2026-11-040027-03-077ColoradoSeal Coat3 of 4$19,218,375+9.2%+12.6%
2026-11-040052-04-054LambSeal Coat4 of 4$27,453,405+23.1%+6.8%
2026-11-040157-04-058HaskellOverlay6 of 9$8,389,000+24.6%+11.6%
2026-11-040923-06-068BrownTexas Park and Wildlife6 of 6$2,399,186+53.6%+37.9%
2026-11-041052-02-098NuecesSafety Improvement Projects3 of 5$4,616,801+20.4%-3.7%
2026-11-046504-98-001Tom GreenRoutine Maintenance Project - Sealed4 of 4$6,573,916+110.4%+266.4%
2026-11-030044-06-079MontagueSeal Coat5 of 6$14,559,655+19.6%+8.2%
2026-11-030054-05-027ColemanSeal Coat2 of 4$3,194,875+9.1%+30.5%