Conc Curb & Gutter (TY II) (Item 529-7009): TxDOT Unit Price History
1,349 bids · 232 bid lines · Nov 6, 2024 to Nov 10, 2026 · unit of measure LF
TxDOT 529-7009 · CONC CURB & GUTTER (TY II) · Unit: LF
- Low bid
- $28.20/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $30.00/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $40.00/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -18.18%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 10, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 529-7009 (Conc Curb & Gutter (TY II)) is measured in LF. Between Nov 6, 2024 and Nov 10, 2026, contractors entered 1,349 bids for it on 232 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 688 bids was $30.00 per LF, and the winning low bidders priced it at a weighted median of $28.20 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $40.00 per LF, so winning bids came in 29.5% below the estimate.
By calendar year, the median bid moved from $55.00 in 2025 (643 bids) to $45.00 in 2026 (665 bids), down 18.2%. The middle half of 2026 bids fell between $32.00 and $67.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 18.18%.
Quantity matters for this item. Lines of 10 to 220 LF had a weighted median of $62.00, while lines above 1,578 LF had $31.05, a 50% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 228 lines where both a winning and a second-place bid were published, the median winning unit price was $42.00 against $50.00 from the second-lowest bidder, a median gap of 4.04% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Waco had the lowest weighted median ($24.75) and Laredo the highest ($58.96). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 10, 2026 in Ector County, where Scr Civil Construction, LLC was the low bidder at $76.00 per LF for 620 LF against an estimate of $76.50.
Related items: 530-7010 Driveways (ACP) (weighted median $59.25 per SY); 530-7006 Driveways (Conc) (weighted median $106.00 per SY); 531-7001 Conc Sidewalks (4") (weighted median $65.00 per SY); 533-7001 Mill Rumble Strips (Asphalt) (Shldr) (weighted median $0.180 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 41 | 7 | $40.93 | $31.08 | $60.00 | $43.00 | $83.47 |
| 2025 | 643 | 116 | $41.77 | $36.08 | $55.00 | $39.38 | $75.00 |
| 2026 | 665 | 109 | $33.07 | $30.00 | $45.00 | $32.00 | $67.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 10–220 | 451 | $70.93 | $62.00 | $50.00–$95.70 |
| Medium | 223.5–1,562 | 450 | $55.09 | $50.00 | $36.00–$75.00 |
| Large | 1,578–50,357 | 448 | $34.38 | $31.05 | $28.91–$48.50 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $42.00
- Median second-low unit price
- $50.00
- Median engineer’s estimate
- $50.00
- Median gap, second vs. low
- +4.04%
228 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6496-11-001 · let Nov 10, 2026 · Ector County, Odessa District
Line quantity 620 LF · Engineer’s estimate $76.50/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Scr Civil Construction, LLCLOW BID | $76.00/LF | $47,120.00 | — | -0.7% | $274,692 | $13,868 (5.05%) left on table |
| 2 | Rb Contracting, LLC | $90.00/LF | $55,800.00 | +$8,680 | +17.6% | $288,560 | +$13,868 |
| 3 | Scott Tucker Construction Company, LLC | $74.00/LF | $45,880.00 | -$1,240 | -3.3% | $288,914 | +$14,222 |
1. Scr Civil Construction, LLC
LOW BID · WINNER- Unit price
- $76.00/LF
- Extension
- $47,120.00
- Proposal total
- $274,692
- Money left on the table
- $13,868 (5.05%)
- vs. engineer’s estimate
- -0.7%
- Unit price
- $90.00/LF
- Extension
- $55,800.00
- Proposal total
- $288,560
- vs. low bid
- +$13,868
- vs. engineer’s estimate
- +17.6%
- Unit price
- $74.00/LF
- Extension
- $45,880.00
- Proposal total
- $288,914
- vs. low bid
- +$14,222
- vs. engineer’s estimate
- -3.3%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 1,562 LF · Engineer’s estimate $32.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $18.00/LF | $28,116.00 | — | -43.8% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $35.30/LF | $55,138.60 | +$27,023 | +10.3% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $35.00/LF | $54,670.00 | +$26,554 | +9.4% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $31.56/LF | $49,296.72 | +$21,181 | -1.4% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $31.54/LF | $49,265.48 | +$21,149 | -1.4% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $34.57/LF | $53,998.34 | +$25,882 | +8% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $18.00/LF
- Extension
- $28,116.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -43.8%
2. Rpm Xconstruction, LLC
- Unit price
- $35.30/LF
- Extension
- $55,138.60
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +10.3%
- Unit price
- $35.00/LF
- Extension
- $54,670.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- +9.4%
4. Webber, LLC
- Unit price
- $31.56/LF
- Extension
- $49,296.72
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -1.4%
5. Sema Construction, Inc.
- Unit price
- $31.54/LF
- Extension
- $49,265.48
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -1.4%
6. Zachry Construction Corporation
- Unit price
- $34.57/LF
- Extension
- $53,998.34
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +8%
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 345 LF · Engineer’s estimate $35.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $37.00/LF | $12,765.00 | — | +5.7% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $35.48/LF | $12,240.60 | -$524.40 | +1.4% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $42.00/LF | $14,490.00 | +$1,725 | +20% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $41.00/LF | $14,145.00 | +$1,380 | +17.1% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $49.44/LF | $17,056.80 | +$4,292 | +41.3% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $26.50/LF | $9,142.50 | -$3,623 | -24.3% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $40.25/LF | $13,886.25 | +$1,121 | +15% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $40.00/LF | $13,800.00 | +$1,035 | +14.3% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $55.00/LF | $18,975.00 | +$6,210 | +57.1% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $37.00/LF
- Extension
- $12,765.00
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- +5.7%
2. Stx Civil
- Unit price
- $35.48/LF
- Extension
- $12,240.60
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- +1.4%
3. Rucoba & Maya Construction, LLC
- Unit price
- $42.00/LF
- Extension
- $14,490.00
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- +20%
4. Myers Concrete Construction, LP
- Unit price
- $41.00/LF
- Extension
- $14,145.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +17.1%
- Unit price
- $49.44/LF
- Extension
- $17,056.80
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- +41.3%
- Unit price
- $26.50/LF
- Extension
- $9,142.50
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- -24.3%
7. Ratliff Hardscape, Ltd.
- Unit price
- $40.25/LF
- Extension
- $13,886.25
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- +15%
- Unit price
- $40.00/LF
- Extension
- $13,800.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- +14.3%
- Unit price
- $55.00/LF
- Extension
- $18,975.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +57.1%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-10 | 6496-11-001 | Ector | Odessa | 620 | 3 | Scr Civil Construction, LLC | $76.00 | $76.50 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 1,562 | 6 | Indus Road & Bridge, Inc. | $18.00 | $32.00 |
| 2026-11-04 | 0285-03-066 | Hays | Austin | 345 | 9 | Lone Star Sitework, LLC | $37.00 | $35.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 294 | 7 | Stx Civil | $15.80 | $70.00 |
| 2026-11-04 | 0923-06-068 | Brown | Brownwood | 116.5 | 6 | Jay Mills Contracting, Incorporated | $55.00 | $55.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 26,831.7 | 6 | Austin Bridge & Road Services, LP | $25.18 | $34.00 |
| 2026-10-14 | 6507-39-001 | El Paso | El Paso | 300 | 6 | Synergy Project Contractors, Inc. | $39.73 | $35.00 |
| 2026-10-14 | 6504-79-001 | Kaufman | Dallas | 30 | 4 | Jackson Excavation, LLC | $30.00 | $30.00 |
| 2026-10-07 | 0921-02-527 | Hidalgo | Pharr | 572 | 1 | Digg Commercial, LLC | $50.00 | $30.00 |
| 2026-10-06 | 0095-03-100 | Kaufman | Dallas | 5,405 | 10 | Highway 19 Construction LLC | $35.00 | $20.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 27 | $31.00 | $27.30 | $40.00 | — |
| Amarillo | 48 | $29.30 | $35.00 | $44.00 | -15.58% |
| Atlanta | 50 | $40.00 | $50.03 | $45.00 | -19.98% |
| Austin | 111 | $25.18 | $30.00 | $34.00 | -2.12% |
| Beaumont | 8 | $16.00 | $18.50 | $86.00 | — |
| Brownwood | 19 | $50.04 | $50.04 | $40.00 | — |
| Bryan | 83 | $20.00 | $40.00 | $40.00 | -5.97% |
| Childress | 18 | $42.50 | $45.00 | $45.00 | — |
| Corpus Christi | 36 | $23.00 | $28.00 | $30.00 | +16.41% |
| Dallas | 200 | $35.00 | $36.67 | $32.00 | -26.67% |
| El Paso | 19 | $26.00 | $30.53 | $35.00 | — |
| Fort Worth | 129 | $35.00 | $31.55 | $40.00 | -21.67% |
| Houston | 25 | $30.00 | $30.00 | $50.00 | — |
| Laredo | 19 | $72.00 | $58.96 | $50.00 | — |
| Lubbock | 21 | $28.20 | $28.20 | $55.00 | — |
| Lufkin | 4 | $42.00 | $59.38 | $85.00 | — |
| Odessa | 60 | $39.78 | $40.00 | $40.00 | -20.01% |
| Paris | 67 | $30.00 | $35.00 | $45.50 | -3.64% |
| Pharr | 69 | $16.00 | $28.22 | $39.00 | -16.67% |
| San Angelo | 19 | $48.29 | $48.29 | $40.00 | — |
| San Antonio | 18 | $46.20 | $44.00 | $29.46 | — |
| Tyler | 88 | $28.60 | $28.60 | $23.00 | -25.75% |
| Waco | 76 | $27.00 | $24.75 | $34.00 | +18% |
| Wichita Falls | 25 | $40.00 | $40.00 | $50.00 | — |
| Yoakum | 110 | $35.00 | $40.00 | $65.00 | -18.35% |
Related items
- 530-7010 · Driveways (ACP) ($59.25/SY)
- 530-7006 · Driveways (Conc) ($106.00/SY)
- 531-7001 · Conc Sidewalks (4") ($65.00/SY)
- 533-7001 · Mill Rumble Strips (Asphalt) (Shldr) ($0.180/LF)
- 533-7002 · Mill Rumble Strips (Asph) (Centerline) ($0.200/LF)
- 540-7001 · MTL W-Beam GD FEN (TIM Post) ($25.75/LF)
- 540-7005 · MTL Beam GD FEN Trans (Thrie-Beam) ($2,208.14/EA)
- 540-7015 · Downstream Anchor Terminal Section ($1,485.00/EA)
Is your price for item 529-7009 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.