Mill Rumble Strips (Asph) (Centerline) (Item 533-7002): TxDOT Unit Price History
1,386 bids · 258 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 533-7002 · MILL RUMBLE STRIPS (ASPH) (CENTERLINE) · Unit: LF
- Low bid
- $0.200/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $0.200/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $0.220/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -3.85%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 533-7002 (Mill Rumble Strips (Asph) (Centerline)) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,386 bids for it on 258 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 635 bids was $0.200 per LF, and the winning low bidders priced it at a weighted median of $0.200 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $0.220 per LF, so winning bids came in 9.1% below the estimate.
By calendar year, the median bid moved from $0.270 in 2025 (769 bids) to $0.250 in 2026 (572 bids), down 7.4%. The middle half of 2026 bids fell between $0.200 and $0.500.
Comparing the last 12 months with the 12 months before, the median unit price fell 3.85%.
Quantity matters for this item. Lines of 50 to 14,779 LF had a weighted median of $0.400, while lines above 42,140 LF had $0.200, a 50% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 248 lines where both a winning and a second-place bid were published, the median winning unit price was $0.260 against $0.250 from the second-lowest bidder, a median gap of 2.49% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 22 TxDOT districts with at least ten bids, Laredo had the lowest weighted median ($0.160) and Bryan the highest ($0.580). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Jasper County, where Texas Materials Group, Inc. was the low bidder at $0.540 per LF for 10,600 LF against an estimate of $0.300.
40 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 533-7001 Mill Rumble Strips (Asphalt) (Shldr) (weighted median $0.180 per LF); 531-7001 Conc Sidewalks (4") (weighted median $65.00 per SY); 530-7010 Driveways (ACP) (weighted median $59.25 per SY); 530-7006 Driveways (Conc) (weighted median $106.00 per SY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 45 | 9 | $0.240 | $0.210 | $0.260 | $0.200 | $0.400 |
| 2025 | 769 | 141 | $0.260 | $0.220 | $0.270 | $0.180 | $0.500 |
| 2026 | 572 | 109 | $0.240 | $0.200 | $0.250 | $0.200 | $0.500 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 50–14,779 | 464 | $0.640 | $0.400 | $0.300–$1.14 |
| Medium | 14,864–41,186 | 462 | $0.310 | $0.250 | $0.190–$0.350 |
| Large | 42,140–1,143,359 | 460 | $0.220 | $0.200 | $0.150–$0.250 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $0.260
- Median second-low unit price
- $0.250
- Median engineer’s estimate
- $0.300
- Median gap, second vs. low
- +2.49%
248 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 1052-02-098 · let Nov 4, 2026 · Nueces County, Corpus Christi District
Line quantity 5,444 LF · Engineer’s estimate $0.250/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | J E Construction Services, LLCLOW BID | $1.00/LF | $5,444.00 | — | +300% | $3,833,265 | $3,958 (0.1%) left on table |
| 2 | Anderson Columbia Co., Inc. | $1.05/LF | $5,716.20 | +$272.20 | +320% | $3,837,222 | +$3,958 |
| 3 | Ck Newberry, LLC | $0.50/LF | $2,722.00 | -$2,722 | +100% | $4,616,801 | +$783,537 |
| 4 | Stx Civil | $0.41/LF | $2,232.04 | -$3,212 | +64% | $4,817,402 | +$984,137 |
| 5 | Texas Materials Group, Inc. | $0.55/LF | $2,994.20 | -$2,450 | +120% | $4,943,316 | +$1,110,051 |
1. J E Construction Services, LLC
LOW BID · WINNER- Unit price
- $1.00/LF
- Extension
- $5,444.00
- Proposal total
- $3,833,265
- Money left on the table
- $3,958 (0.1%)
- vs. engineer’s estimate
- +300%
- Unit price
- $1.05/LF
- Extension
- $5,716.20
- Proposal total
- $3,837,222
- vs. low bid
- +$3,958
- vs. engineer’s estimate
- +320%
- Unit price
- $0.50/LF
- Extension
- $2,722.00
- Proposal total
- $4,616,801
- vs. low bid
- +$783,537
- vs. engineer’s estimate
- +100%
4. Stx Civil
- Unit price
- $0.41/LF
- Extension
- $2,232.04
- Proposal total
- $4,817,402
- vs. low bid
- +$984,137
- vs. engineer’s estimate
- +64%
- Unit price
- $0.55/LF
- Extension
- $2,994.20
- Proposal total
- $4,943,316
- vs. low bid
- +$1,110,051
- vs. engineer’s estimate
- +120%
Proposal 0200-01-093 · let Oct 7, 2026 · Angelina County, Lufkin District
Line quantity 51,024 LF · Engineer’s estimate $0.350/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Longview Bridge and Road, Ltd.LOW BID | $0.18/LF | $9,184.32 | — | -48.6% | $31,796,270 | $1,482,945 (4.66%) left on table |
| 2 | Texas Materials Group, Inc. | $0.31/LF | $15,817.44 | +$6,633 | -11.4% | $33,279,215 | +$1,482,945 |
| 3 | A. L. Helmcamp, Inc. | $0.15/LF | $7,653.60 | -$1,531 | -57.1% | $37,472,944 | +$5,676,674 |
| 4 | R Construction Civil, LLC | $0.20/LF | $10,204.80 | +$1,020 | -42.9% | $39,358,349 | +$7,562,079 |
| 5 | Posillico Civil, Inc. | $0.22/LF | $11,225.28 | +$2,041 | -37.1% | $40,757,181 | +$8,960,911 |
| 6 | Ragle Construction, Inc. | $0.30/LF | $15,307.20 | +$6,123 | -14.3% | $46,841,741 | +$15,045,471 |
| 7 | Durwood Greene Construction Co. | $0.25/LF | $12,756.00 | +$3,572 | -28.6% | $48,973,611 | +$17,177,341 |
1. Longview Bridge and Road, Ltd.
LOW BID · WINNER- Unit price
- $0.18/LF
- Extension
- $9,184.32
- Proposal total
- $31,796,270
- Money left on the table
- $1,482,945 (4.66%)
- vs. engineer’s estimate
- -48.6%
- Unit price
- $0.31/LF
- Extension
- $15,817.44
- Proposal total
- $33,279,215
- vs. low bid
- +$1,482,945
- vs. engineer’s estimate
- -11.4%
- Unit price
- $0.15/LF
- Extension
- $7,653.60
- Proposal total
- $37,472,944
- vs. low bid
- +$5,676,674
- vs. engineer’s estimate
- -57.1%
- Unit price
- $0.20/LF
- Extension
- $10,204.80
- Proposal total
- $39,358,349
- vs. low bid
- +$7,562,079
- vs. engineer’s estimate
- -42.9%
- Unit price
- $0.22/LF
- Extension
- $11,225.28
- Proposal total
- $40,757,181
- vs. low bid
- +$8,960,911
- vs. engineer’s estimate
- -37.1%
- Unit price
- $0.30/LF
- Extension
- $15,307.20
- Proposal total
- $46,841,741
- vs. low bid
- +$15,045,471
- vs. engineer’s estimate
- -14.3%
- Unit price
- $0.25/LF
- Extension
- $12,756.00
- Proposal total
- $48,973,611
- vs. low bid
- +$17,177,341
- vs. engineer’s estimate
- -28.6%
Proposal 0510-06-024 · let Oct 7, 2026 · Fannin County, Paris District
Line quantity 32,321 LF · Engineer’s estimate $0.240/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | A. K. Gillis & Sons, LLCLOW BID | $0.08/LF | $2,618.00 | — | -66.2% | $9,766,246 | $198,541 (2.03%) left on table |
| 2 | D. L. Lennon Incorporated - Contractor | $0.58/LF | $18,778.50 | +$16,161 | +142.1% | $9,964,787 | +$198,541 |
| 3 | Overland Corporation | $0.10/LF | $3,232.10 | +$614.10 | -58.3% | $11,920,777 | +$2,154,531 |
| 4 | Jagoe-Public Company | $0.26/LF | $8,403.46 | +$5,785 | +8.3% | $13,165,820 | +$3,399,574 |
| 5 | Austin Bridge & Road Services, LP | $0.09/LF | $2,908.89 | +$290.89 | -62.5% | $13,580,257 | +$3,814,011 |
| 6 | Thk Construction LLC | $0.27/LF | $8,726.67 | +$6,109 | +12.5% | $18,167,614 | +$8,401,368 |
- LOW BID · WINNER
- Unit price
- $0.08/LF
- Extension
- $2,618.00
- Proposal total
- $9,766,246
- Money left on the table
- $198,541 (2.03%)
- vs. engineer’s estimate
- -66.2%
- Unit price
- $0.58/LF
- Extension
- $18,778.50
- Proposal total
- $9,964,787
- vs. low bid
- +$198,541
- vs. engineer’s estimate
- +142.1%
3. Overland Corporation
- Unit price
- $0.10/LF
- Extension
- $3,232.10
- Proposal total
- $11,920,777
- vs. low bid
- +$2,154,531
- vs. engineer’s estimate
- -58.3%
- Unit price
- $0.26/LF
- Extension
- $8,403.46
- Proposal total
- $13,165,820
- vs. low bid
- +$3,399,574
- vs. engineer’s estimate
- +8.3%
- Unit price
- $0.09/LF
- Extension
- $2,908.89
- Proposal total
- $13,580,257
- vs. low bid
- +$3,814,011
- vs. engineer’s estimate
- -62.5%
- Unit price
- $0.27/LF
- Extension
- $8,726.67
- Proposal total
- $18,167,614
- vs. low bid
- +$8,401,368
- vs. engineer’s estimate
- +12.5%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 10,600 | 2 | Texas Materials Group, Inc. | $0.540 | $0.300 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 5,444 | 5 | J E Construction Services, LLC | $1.00 | $0.250 |
| 2026-11-03 | 0220-01-038 | Hidalgo | Pharr | 29,413 | 2 | Foremost Paving, Inc. | $0.270 | $0.200 |
| 2026-10-14 | 6502-76-001 | Ellis | Dallas | 4,400 | 2 | Stripe-A-Zone, LLC | $1.65 | $0.300 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 51,024 | 7 | Longview Bridge and Road, Ltd. | $0.180 | $0.350 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 32,321 | 6 | A. K. Gillis & Sons, LLC | $0.081 | $0.240 |
| 2026-10-06 | 0249-02-026 | Archer | Wichita Falls | 22,704 | 5 | Overland Corporation | $0.170 | $0.250 |
| 2026-10-06 | 0387-01-016 | Collin | Dallas | 8,744 | 8 | A. K. Gillis & Sons, LLC | $0.220 | $0.300 |
| 2026-10-06 | 0410-02-047 | Grayson | Paris | 60,966 | 7 | Highway 19 Construction LLC | $0.220 | $0.280 |
| 2026-10-06 | 1122-01-034 | Karnes | Corpus Christi | 62,180 | 7 | Ck Newberry, LLC | $0.200 | $0.230 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 59 | $0.280 | $0.200 | $0.200 | +17.5% |
| Amarillo | 19 | $0.270 | $0.200 | $0.280 | — |
| Austin | 41 | $0.380 | $0.190 | $0.500 | +10% |
| Beaumont | 56 | $0.240 | $0.240 | $0.500 | -59.72% |
| Brownwood | 35 | $0.160 | $0.170 | $0.140 | +7.5% |
| Bryan | 68 | $0.350 | $0.580 | $0.230 | +13.64% |
| Childress | 46 | $0.260 | $0.170 | $0.250 | +25% |
| Corpus Christi | 84 | $0.180 | $0.180 | $0.150 | -33.33% |
| Dallas | 209 | $0.300 | $0.200 | $0.300 | -5.66% |
| El Paso | 4 | $0.150 | $0.250 | $0.250 | — |
| Fort Worth | 91 | $0.160 | $0.220 | $0.670 | -26.67% |
| Houston | 75 | $0.250 | $0.250 | $0.200 | +44.23% |
| Laredo | 45 | $0.120 | $0.160 | $0.220 | +24.44% |
| Lubbock | 19 | $0.200 | $0.160 | $0.180 | — |
| Lufkin | 55 | $0.180 | $0.250 | $0.350 | -43% |
| Odessa | 56 | $0.240 | $0.240 | $0.200 | +25% |
| Paris | 53 | $0.220 | $0.230 | $0.270 | -43.53% |
| Pharr | 25 | $0.270 | $0.250 | $0.200 | — |
| San Antonio | 35 | $0.160 | $0.160 | $0.150 | +53.33% |
| Tyler | 116 | $0.290 | $0.300 | $0.280 | +20% |
| Waco | 63 | $0.200 | $0.210 | $0.300 | -23.33% |
| Wichita Falls | 80 | $0.220 | $0.210 | $0.250 | -9.09% |
| Yoakum | 52 | $0.200 | $0.350 | $0.500 | +20% |
Related items
- 533-7001 · Mill Rumble Strips (Asphalt) (Shldr) ($0.180/LF)
- 531-7001 · Conc Sidewalks (4") ($65.00/SY)
- 530-7010 · Driveways (ACP) ($59.25/SY)
- 530-7006 · Driveways (Conc) ($106.00/SY)
- 529-7009 · Conc Curb & Gutter (TY II) ($30.00/LF)
- 540-7001 · MTL W-Beam GD FEN (TIM Post) ($25.75/LF)
- 540-7005 · MTL Beam GD FEN Trans (Thrie-Beam) ($2,208.14/EA)
- 540-7015 · Downstream Anchor Terminal Section ($1,485.00/EA)