Mill Rumble Strips (Asphalt) (Shldr) (Item 533-7001): TxDOT Unit Price History
1,887 bids · 350 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 533-7001 · MILL RUMBLE STRIPS (ASPHALT) (SHLDR) · Unit: LF
- Low bid
- $0.180/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $0.180/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $0.200/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- 0%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 533-7001 (Mill Rumble Strips (Asphalt) (Shldr)) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,887 bids for it on 350 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 919 bids was $0.180 per LF, and the winning low bidders priced it at a weighted median of $0.180 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $0.200 per LF, so winning bids came in 10.0% below the estimate.
By calendar year, the median bid moved from $0.250 in 2025 (977 bids) to $0.250 in 2026 (840 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $0.180 and $0.600.
Comparing the last 12 months with the 12 months before, the median unit price did not change.
Quantity matters for this item. Lines of 50 to 26,280.64 LF had a weighted median of $0.500, while lines above 78,645 LF had $0.160, a 68% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 341 lines where both a winning and a second-place bid were published, the median winning unit price was $0.250 against $0.250 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Waco had the lowest weighted median ($0.110) and San Angelo the highest ($2.25). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Haskell County, where Lone Star Paving Company was the low bidder at $0.130 per LF for 122,905 LF against an estimate of $0.200.
31 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 533-7002 Mill Rumble Strips (Asph) (Centerline) (weighted median $0.200 per LF); 531-7001 Conc Sidewalks (4") (weighted median $65.00 per SY); 530-7010 Driveways (ACP) (weighted median $59.25 per SY); 530-7006 Driveways (Conc) (weighted median $106.00 per SY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 70 | 13 | $0.190 | $0.170 | $0.210 | $0.150 | $0.320 |
| 2025 | 977 | 182 | $0.230 | $0.180 | $0.250 | $0.160 | $0.500 |
| 2026 | 840 | 156 | $0.230 | $0.180 | $0.250 | $0.180 | $0.600 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 50–26,280.64 | 630 | $0.800 | $0.500 | $0.400–$1.84 |
| Medium | 26,477–78,258 | 630 | $0.260 | $0.220 | $0.160–$0.300 |
| Large | 78,645–1,183,325 | 627 | $0.190 | $0.160 | $0.130–$0.240 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $0.250
- Median second-low unit price
- $0.250
- Median engineer’s estimate
- $0.260
- Median gap, second vs. low
- +0%
341 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0157-04-058 · let Nov 4, 2026 · Haskell County, Abilene District
Line quantity 122,905 LF · Engineer’s estimate $0.200/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Paving CompanyLOW BID | $0.13/LF | $15,977.65 | — | -35% | $6,732,215 | $1,063,968 (15.8%) left on table |
| 2 | Rk Hall, LLC | $0.30/LF | $36,871.50 | +$20,894 | +50% | $7,796,183 | +$1,063,968 |
| 3 | Zack Burkett Co. | $0.19/LF | $23,351.95 | +$7,374 | -5% | $7,966,171 | +$1,233,956 |
| 4 | Foutsco Paving Company, LLC | $0.15/LF | $18,435.75 | +$2,458 | -25% | $8,000,580 | +$1,268,365 |
| 5 | Nobles Road Construction, Inc. | $0.18/LF | $22,122.90 | +$6,145 | -10% | $8,307,427 | +$1,575,212 |
| 6 | Ck Newberry, LLC | $0.20/LF | $24,581.00 | +$8,603 | 0% | $8,389,000 | +$1,656,785 |
| 7 | Reece Albert, Inc. | $0.21/LF | $25,810.05 | +$9,832 | +5% | $8,534,153 | +$1,801,938 |
| 8 | Texas Materials Group, Inc. | $0.20/LF | $24,581.00 | +$8,603 | 0% | $8,617,318 | +$1,885,103 |
| 9 | A. L. Helmcamp, Inc. | $0.28/LF | $34,413.40 | +$18,436 | +40% | $9,257,856 | +$2,525,641 |
- LOW BID · WINNER
- Unit price
- $0.13/LF
- Extension
- $15,977.65
- Proposal total
- $6,732,215
- Money left on the table
- $1,063,968 (15.8%)
- vs. engineer’s estimate
- -35%
2. Rk Hall, LLC
- Unit price
- $0.30/LF
- Extension
- $36,871.50
- Proposal total
- $7,796,183
- vs. low bid
- +$1,063,968
- vs. engineer’s estimate
- +50%
- Unit price
- $0.19/LF
- Extension
- $23,351.95
- Proposal total
- $7,966,171
- vs. low bid
- +$1,233,956
- vs. engineer’s estimate
- -5%
- Unit price
- $0.15/LF
- Extension
- $18,435.75
- Proposal total
- $8,000,580
- vs. low bid
- +$1,268,365
- vs. engineer’s estimate
- -25%
5. Nobles Road Construction, Inc.
- Unit price
- $0.18/LF
- Extension
- $22,122.90
- Proposal total
- $8,307,427
- vs. low bid
- +$1,575,212
- vs. engineer’s estimate
- -10%
- Unit price
- $0.20/LF
- Extension
- $24,581.00
- Proposal total
- $8,389,000
- vs. low bid
- +$1,656,785
- vs. engineer’s estimate
- 0%
- Unit price
- $0.21/LF
- Extension
- $25,810.05
- Proposal total
- $8,534,153
- vs. low bid
- +$1,801,938
- vs. engineer’s estimate
- +5%
- Unit price
- $0.20/LF
- Extension
- $24,581.00
- Proposal total
- $8,617,318
- vs. low bid
- +$1,885,103
- vs. engineer’s estimate
- 0%
- Unit price
- $0.28/LF
- Extension
- $34,413.40
- Proposal total
- $9,257,856
- vs. low bid
- +$2,525,641
- vs. engineer’s estimate
- +40%
Proposal 0353-01-031 · let Nov 4, 2026 · Wise County, Fort Worth District
Line quantity 1,300 LF · Engineer’s estimate $2.50/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Xit Paving and Construction Inc.LOW BID | $6.00/LF | $7,800.00 | — | +140% | $482,224 | $101,735 (21.1%) left on table |
| 2 | Ed Bell Construction Company | $0.01/LF | $13.00 | -$7,787 | -99.6% | $583,959 | +$101,735 |
| 3 | O. Trevino Construction, LLC | $3.25/LF | $4,225.00 | -$3,575 | +30% | $594,655 | +$112,431 |
| 4 | Jay Mills Contracting, Incorporated | $6.45/LF | $8,385.00 | +$585.00 | +158% | $607,976 | +$125,752 |
| 5 | Silver Creek Construction, Inc. | $3.00/LF | $3,900.00 | -$3,900 | +20% | $649,060 | +$166,836 |
| 6 | Jagoe-Public Company | $3.25/LF | $4,225.00 | -$3,575 | +30% | $701,946 | +$219,722 |
| 7 | Overland Corporation | $3.85/LF | $5,005.00 | -$2,795 | +54% | $771,411 | +$289,187 |
1. Xit Paving and Construction Inc.
LOW BID · WINNER- Unit price
- $6.00/LF
- Extension
- $7,800.00
- Proposal total
- $482,224
- Money left on the table
- $101,735 (21.1%)
- vs. engineer’s estimate
- +140%
- Unit price
- $0.01/LF
- Extension
- $13.00
- Proposal total
- $583,959
- vs. low bid
- +$101,735
- vs. engineer’s estimate
- -99.6%
- Unit price
- $3.25/LF
- Extension
- $4,225.00
- Proposal total
- $594,655
- vs. low bid
- +$112,431
- vs. engineer’s estimate
- +30%
4. Jay Mills Contracting, Incorporated
- Unit price
- $6.45/LF
- Extension
- $8,385.00
- Proposal total
- $607,976
- vs. low bid
- +$125,752
- vs. engineer’s estimate
- +158%
5. Silver Creek Construction, Inc.
- Unit price
- $3.00/LF
- Extension
- $3,900.00
- Proposal total
- $649,060
- vs. low bid
- +$166,836
- vs. engineer’s estimate
- +20%
- Unit price
- $3.25/LF
- Extension
- $4,225.00
- Proposal total
- $701,946
- vs. low bid
- +$219,722
- vs. engineer’s estimate
- +30%
7. Overland Corporation
- Unit price
- $3.85/LF
- Extension
- $5,005.00
- Proposal total
- $771,411
- vs. low bid
- +$289,187
- vs. engineer’s estimate
- +54%
Proposal 1052-02-098 · let Nov 4, 2026 · Nueces County, Corpus Christi District
Line quantity 11,096 LF · Engineer’s estimate $0.250/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | J E Construction Services, LLCLOW BID | $1.00/LF | $11,096.00 | — | +300% | $3,833,265 | $3,958 (0.1%) left on table |
| 2 | Anderson Columbia Co., Inc. | $0.65/LF | $7,212.40 | -$3,884 | +160% | $3,837,222 | +$3,958 |
| 3 | Ck Newberry, LLC | $0.40/LF | $4,438.40 | -$6,658 | +60% | $4,616,801 | +$783,537 |
| 4 | Stx Civil | $0.41/LF | $4,549.36 | -$6,547 | +64% | $4,817,402 | +$984,137 |
| 5 | Texas Materials Group, Inc. | $0.45/LF | $4,993.20 | -$6,103 | +80% | $4,943,316 | +$1,110,051 |
1. J E Construction Services, LLC
LOW BID · WINNER- Unit price
- $1.00/LF
- Extension
- $11,096.00
- Proposal total
- $3,833,265
- Money left on the table
- $3,958 (0.1%)
- vs. engineer’s estimate
- +300%
- Unit price
- $0.65/LF
- Extension
- $7,212.40
- Proposal total
- $3,837,222
- vs. low bid
- +$3,958
- vs. engineer’s estimate
- +160%
- Unit price
- $0.40/LF
- Extension
- $4,438.40
- Proposal total
- $4,616,801
- vs. low bid
- +$783,537
- vs. engineer’s estimate
- +60%
4. Stx Civil
- Unit price
- $0.41/LF
- Extension
- $4,549.36
- Proposal total
- $4,817,402
- vs. low bid
- +$984,137
- vs. engineer’s estimate
- +64%
- Unit price
- $0.45/LF
- Extension
- $4,993.20
- Proposal total
- $4,943,316
- vs. low bid
- +$1,110,051
- vs. engineer’s estimate
- +80%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0157-04-058 | Haskell | Abilene | 122,905 | 9 | Lone Star Paving Company | $0.130 | $0.200 |
| 2026-11-04 | 0353-01-031 | Wise | Fort Worth | 1,300 | 7 | Xit Paving and Construction Inc. | $6.00 | $2.50 |
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 21,200 | 2 | Texas Materials Group, Inc. | $0.460 | $0.300 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 11,096 | 5 | J E Construction Services, LLC | $1.00 | $0.250 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 1,800 | 8 | Jay Mills Contracting, Incorporated | $4.65 | $1.00 |
| 2026-11-03 | 0220-01-038 | Hidalgo | Pharr | 76,899 | 2 | Foremost Paving, Inc. | $0.180 | $0.150 |
| 2026-10-14 | 6502-76-001 | Ellis | Dallas | 4,400 | 2 | Stripe-A-Zone, LLC | $1.65 | $0.300 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 63,701 | 8 | Hunter Industries, Ltd. | $0.240 | $0.230 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 60,343 | 7 | Longview Bridge and Road, Ltd. | $0.170 | $0.300 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 64,642 | 6 | A. K. Gillis & Sons, LLC | $0.070 | $0.260 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 98 | $0.220 | $0.200 | $0.200 | 0% |
| Amarillo | 30 | $0.250 | $0.150 | $0.300 | — |
| Atlanta | 35 | $0.300 | $0.300 | $0.340 | — |
| Austin | 6 | $0.220 | $0.240 | $0.350 | — |
| Beaumont | 59 | $0.200 | $0.200 | $0.500 | -54.62% |
| Brownwood | 31 | $0.130 | $0.150 | $0.140 | -38.78% |
| Bryan | 113 | $0.270 | $0.250 | $0.230 | -32% |
| Childress | 54 | $0.230 | $0.160 | $0.190 | +33.33% |
| Corpus Christi | 96 | $0.120 | $0.170 | $0.150 | -11.11% |
| Dallas | 291 | $0.300 | $0.220 | $0.250 | +15.38% |
| El Paso | 2 | $1.00 | $0.750 | $0.500 | — |
| Fort Worth | 142 | $0.200 | $0.250 | $1.00 | +16.67% |
| Houston | 63 | $0.190 | $0.200 | $0.200 | +11.11% |
| Laredo | 49 | $0.210 | $0.140 | $0.170 | +12.5% |
| Lubbock | 57 | $0.450 | $0.800 | $0.280 | +506.06% |
| Lufkin | 64 | $0.200 | $0.250 | $0.300 | -68.75% |
| Odessa | 111 | $0.190 | $0.180 | $0.200 | +5.26% |
| Paris | 54 | $0.180 | $0.190 | $0.260 | -42.86% |
| Pharr | 63 | $0.130 | $0.180 | $0.360 | -28% |
| San Angelo | 17 | $2.25 | $2.25 | $5.00 | — |
| San Antonio | 91 | $0.190 | $0.170 | $0.170 | +17.5% |
| Tyler | 147 | $0.270 | $0.250 | $0.210 | +20% |
| Waco | 72 | $0.100 | $0.110 | $0.200 | -20% |
| Wichita Falls | 78 | $0.220 | $0.200 | $0.250 | 0% |
| Yoakum | 64 | $0.160 | $0.280 | $0.150 | -5.45% |
Related items
- 533-7002 · Mill Rumble Strips (Asph) (Centerline) ($0.200/LF)
- 531-7001 · Conc Sidewalks (4") ($65.00/SY)
- 530-7010 · Driveways (ACP) ($59.25/SY)
- 530-7006 · Driveways (Conc) ($106.00/SY)
- 529-7009 · Conc Curb & Gutter (TY II) ($30.00/LF)
- 540-7001 · MTL W-Beam GD FEN (TIM Post) ($25.75/LF)
- 540-7005 · MTL Beam GD FEN Trans (Thrie-Beam) ($2,208.14/EA)
- 540-7015 · Downstream Anchor Terminal Section ($1,485.00/EA)
Is your price for item 533-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.