Skip to content
BidTabulation.comDOT bid tabulations & unit-price intelligence
Menu

Jackson Excavation, LLC: TxDOT Bid Results and Margins

Name as published by TxDOT: JACKSON EXCAVATION, LLC · Data as published by TxDOT, lettings Mar 20, 2025 to Nov 19, 2026, retrieved Nov 24, 2026.

Proposals bid
57
Low bids (rank 1)
11
Win rate
19.3%
Low-bid value
$3.4M
Money left on table
$970K
Avg. bid vs. estimate
+17.66%

From Mar 20, 2025 to Nov 19, 2026, Jackson Excavation, LLC submitted 57 bids on TxDOT proposals and was the apparent low bidder on 11 of them (19.3%), with low bids totalling $3,366,765. In 11 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $969,802 (28.81% of those bids); the median gap was 17.34%. On average its bids came in 17.66% above TxDOT's engineer's estimate. Its most frequent district was Dallas (19 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202513646.2%$2,015,955
202644511.4%$1,350,810

Head-to-head rivals

BidderProposals togetherRanked ahead
Garret Shields Infrastructure2211 of 22
Icos Management, LLC1610 of 16
Structural Integrity Group LLC138 of 13
Western Certified Arborists126 of 12
Cross Plus Construction, LLC117 of 11
Road Doctors LLC116 of 11
Gv Landscape and Construction LLC105 of 10
Looks Great Services of Ms, Inc.106 of 10

Districts and work types

DistrictBids
Dallas19
Houston11
Beaumont4
Bryan4
Fort Worth3
Work type of low bidsLow bids
Routine Maintenance Project - Sealed5
Routine Maintenance Project3
Bridge Maintenance1
Bridge Preventative Maintenance1
Bridge Preventative Maintenance - Sealed1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2026-04-226489-07-001SabineAce Contractors, Inc.$292,558$299,600+2.4%
2026-08-050095-04-079KaufmanShalom Services Corporation$799,617$833,943+4.3%
2026-04-080901-00-069LamarThe Truesdell Corporation$734,734$778,173+5.9%
2026-08-116501-71-001SmithInfratex Construction LLC$167,226$179,600+7.4%
2026-06-036499-57-001BowieThk Construction LLC$904,025$1,001,820+10.8%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-196512-46-001KimbleRoutine Maintenance Project - Sealed5 of 8$203,300+27.5%+0.5%
2026-11-176508-25-001JeffersonRoutine Maintenance Project3 of 7$490,500+36.1%+14.1%
2026-11-176508-77-001LibertyRoutine Maintenance Project5 of 9$286,250+49.3%+5.5%
2026-11-176508-79-001JasperRoutine Maintenance Project5 of 8$468,450+46.8%+12.1%
2026-10-146485-46-001DentonBridge Preventative Maintenance6 of 6$140,440+69.1%+79.3%
2026-10-146501-52-001EllisRoutine Maintenance Project - Sealed4 of 8$168,208+4.5%-2.8%
2026-10-146503-16-001DentonRoutine Maintenance Project - Sealed3 of 3$272,500+63.7%+42.5%
2026-10-146504-79-001KaufmanRoutine Maintenance Project - Sealed1 of 4$203,140—-25%
2026-10-086509-34-001ColoradoRoutine Maintenance Project6 of 6$2,593,020+764.7%+695.4%
2026-10-076493-26-001WiseBridge Preventative Maintenance - Sealed2 of 7$1,358,957+30.6%-3.8%
2026-09-166505-59-001TarrantRoutine Maintenance Project - Sealed2 of 6$391,998+15.7%-16.2%
2026-09-166506-58-001TarrantRoutine Maintenance Project - Sealed4 of 5$237,400+40.7%+54.9%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.

Compare your own unit prices with TxDOT history: benchmark a bid tab.