D-GR HMA TY-B PG64-22 (Item 341-7001): TxDOT Unit Price History
727 bids · 123 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure TON
TxDOT 341-7001 · D-GR HMA TY-B PG64-22 · Unit: TON
- Low bid
- $84.17/TON
- Quantity-weighted median of winning unit prices
- Weighted median
- $85.40/TON
- Quantity-weighted median of every bid
- Engineer’s estimate
- $82.50/TON
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -3.73%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 341-7001 (D-GR HMA TY-B PG64-22) is measured in TON. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 727 bids for it on 123 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 387 bids was $85.40 per TON, and the winning low bidders priced it at a weighted median of $84.17 per TON.
TxDOT's engineer's estimate for the same lines had a weighted median of $82.50 per TON, so winning bids came in 2.0% above the estimate.
By calendar year, the median bid moved from $132.25 in 2025 (353 bids) to $126.80 in 2026 (367 bids), down 4.1%. The middle half of 2026 bids fell between $101.10 and $171.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 3.73%.
Quantity matters for this item. Lines of 9 to 1,622 TON had a weighted median of $163.00, while lines above 10,248 TON had $90.00, a 45% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 121 lines where both a winning and a second-place bid were published, the median winning unit price was $119.00 against $124.02 from the second-lowest bidder, a median gap of 3.91% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 13 TxDOT districts with at least ten bids, San Antonio had the lowest weighted median ($77.00) and Brownwood the highest ($362.50). The busiest district for this item was San Antonio.
The most recent letting with this item was on Nov 4, 2026 in Hays County, where Lone Star Sitework, LLC was the low bidder at $325.00 per TON for 135 TON against an estimate of $90.00.
2 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 341-7082 Tack Coat (weighted median $4.00 per GAL); 341-7050 D-GR HMA TY-D SAC-B PG70-22 (weighted median $125.00 per TON); 344-7077 Tack Coat (weighted median $4.50 per GAL); 344-7001 SP Mixes SP-B PG64-22 (weighted median $127.00 per TON).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 7 | 1 | $90.72 | $90.42 | $90.42 | $89.00 | $94.05 |
| 2025 | 353 | 64 | $111.62 | $102.00 | $132.25 | $103.20 | $181.00 |
| 2026 | 367 | 59 | $100.24 | $87.45 | $126.80 | $101.10 | $171.00 |
Quantity bands
| Band | Quantity (TON) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 9–1,622 | 255 | $174.34 | $163.00 | $141.61–$260.00 |
| Medium | 1,735–9,967 | 235 | $133.27 | $126.80 | $110.00–$150.00 |
| Large | 10,248–157,288 | 237 | $100.86 | $90.00 | $83.00–$121.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $119.00
- Median second-low unit price
- $124.02
- Median engineer’s estimate
- $115.00
- Median gap, second vs. low
- +3.91%
121 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 135 TON · Engineer’s estimate $90.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $325.00/TON | $43,875.00 | — | +261.1% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $194.75/TON | $26,291.25 | -$17,584 | +116.4% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $300.00/TON | $40,500.00 | -$3,375 | +233.3% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $383.00/TON | $51,705.00 | +$7,830 | +325.6% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $220.00/TON | $29,700.00 | -$14,175 | +144.4% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $178.00/TON | $24,030.00 | -$19,845 | +97.8% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $464.32/TON | $62,683.20 | +$18,808 | +415.9% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $350.00/TON | $47,250.00 | +$3,375 | +288.9% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $350.00/TON | $47,250.00 | +$3,375 | +288.9% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $325.00/TON
- Extension
- $43,875.00
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- +261.1%
2. Stx Civil
- Unit price
- $194.75/TON
- Extension
- $26,291.25
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- +116.4%
3. Rucoba & Maya Construction, LLC
- Unit price
- $300.00/TON
- Extension
- $40,500.00
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- +233.3%
4. Myers Concrete Construction, LP
- Unit price
- $383.00/TON
- Extension
- $51,705.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +325.6%
- Unit price
- $220.00/TON
- Extension
- $29,700.00
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- +144.4%
- Unit price
- $178.00/TON
- Extension
- $24,030.00
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- +97.8%
7. Ratliff Hardscape, Ltd.
- Unit price
- $464.32/TON
- Extension
- $62,683.20
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- +415.9%
- Unit price
- $350.00/TON
- Extension
- $47,250.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- +288.9%
- Unit price
- $350.00/TON
- Extension
- $47,250.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +288.9%
Proposal 1017-03-040 · let Nov 4, 2026 · Hunt County, Paris District
Line quantity 24,930 TON · Engineer’s estimate $110.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Highway 19 Construction LLCLOW BID | $131.00/TON | $3,265,830.00 | — | +19.1% | $6,803,596 | $438,151 (6.44%) left on table |
| 2 | Thk Construction LLC | $143.12/TON | $3,567,981.60 | +$302,152 | +30.1% | $7,241,746 | +$438,151 |
| 3 | East Texas Bridge, Inc. | $132.00/TON | $3,290,760.00 | +$24,930 | +20% | $7,366,754 | +$563,159 |
| 4 | D. L. Lennon Incorporated - Contractor | $132.60/TON | $3,305,718.00 | +$39,888 | +20.5% | $7,400,348 | +$596,752 |
| 5 | Rk Hall, LLC | $123.74/TON | $3,084,838.20 | -$180,992 | +12.5% | $7,514,717 | +$711,122 |
| 6 | Austin Bridge & Road Services, LP | $126.01/TON | $3,141,429.30 | -$124,401 | +14.6% | $7,794,981 | +$991,385 |
| 7 | Texas Materials Group, Inc. | $142.00/TON | $3,540,060.00 | +$274,230 | +29.1% | $7,795,159 | +$991,563 |
| 8 | Cdm Holdings | $135.00/TON | $3,365,550.00 | +$99,720 | +22.7% | $8,325,506 | +$1,521,910 |
| 9 | Ed Bell Construction Company | $132.00/TON | $3,290,760.00 | +$24,930 | +20% | $9,159,173 | +$2,355,578 |
1. Highway 19 Construction LLC
LOW BID · WINNER- Unit price
- $131.00/TON
- Extension
- $3,265,830.00
- Proposal total
- $6,803,596
- Money left on the table
- $438,151 (6.44%)
- vs. engineer’s estimate
- +19.1%
- Unit price
- $143.12/TON
- Extension
- $3,567,981.60
- Proposal total
- $7,241,746
- vs. low bid
- +$438,151
- vs. engineer’s estimate
- +30.1%
- Unit price
- $132.00/TON
- Extension
- $3,290,760.00
- Proposal total
- $7,366,754
- vs. low bid
- +$563,159
- vs. engineer’s estimate
- +20%
- Unit price
- $132.60/TON
- Extension
- $3,305,718.00
- Proposal total
- $7,400,348
- vs. low bid
- +$596,752
- vs. engineer’s estimate
- +20.5%
5. Rk Hall, LLC
- Unit price
- $123.74/TON
- Extension
- $3,084,838.20
- Proposal total
- $7,514,717
- vs. low bid
- +$711,122
- vs. engineer’s estimate
- +12.5%
- Unit price
- $126.01/TON
- Extension
- $3,141,429.30
- Proposal total
- $7,794,981
- vs. low bid
- +$991,385
- vs. engineer’s estimate
- +14.6%
- Unit price
- $142.00/TON
- Extension
- $3,540,060.00
- Proposal total
- $7,795,159
- vs. low bid
- +$991,563
- vs. engineer’s estimate
- +29.1%
8. Cdm Holdings
- Unit price
- $135.00/TON
- Extension
- $3,365,550.00
- Proposal total
- $8,325,506
- vs. low bid
- +$1,521,910
- vs. engineer’s estimate
- +22.7%
- Unit price
- $132.00/TON
- Extension
- $3,290,760.00
- Proposal total
- $9,159,173
- vs. low bid
- +$2,355,578
- vs. engineer’s estimate
- +20%
Proposal 0008-02-078 · let Nov 3, 2026 · Parker County, Fort Worth District
Line quantity 918 TON · Engineer’s estimate $170.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Jay Mills Contracting, IncorporatedLOW BID | $117.00/TON | $107,406.00 | — | -31.2% | $494,986 | $418 (0.08%) left on table |
| 2 | Texas Materials Group, Inc. | $125.00/TON | $114,750.00 | +$7,344 | -26.5% | $495,404 | +$418.25 |
| 3 | Jagoe-Public Company | $120.00/TON | $110,160.00 | +$2,754 | -29.4% | $598,414 | +$103,428 |
| 4 | Eurovia Atlantic Coast LLC | $128.00/TON | $117,504.00 | +$10,098 | -24.7% | $614,549 | +$119,563 |
| 5 | Overland Corporation | $165.00/TON | $151,470.00 | +$44,064 | -2.9% | $616,693 | +$121,707 |
| 6 | Foutsco Paving Company, LLC | $197.00/TON | $180,846.00 | +$73,440 | +15.9% | $621,064 | +$126,078 |
| 7 | A. L. Helmcamp, Inc. | $175.00/TON | $160,650.00 | +$53,244 | +2.9% | $662,993 | +$168,007 |
| 8 | Ed Bell Construction Company | $120.00/TON | $110,160.00 | +$2,754 | -29.4% | $679,542 | +$184,556 |
1. Jay Mills Contracting, Incorporated
LOW BID · WINNER- Unit price
- $117.00/TON
- Extension
- $107,406.00
- Proposal total
- $494,986
- Money left on the table
- $418 (0.08%)
- vs. engineer’s estimate
- -31.2%
- Unit price
- $125.00/TON
- Extension
- $114,750.00
- Proposal total
- $495,404
- vs. low bid
- +$418.25
- vs. engineer’s estimate
- -26.5%
- Unit price
- $120.00/TON
- Extension
- $110,160.00
- Proposal total
- $598,414
- vs. low bid
- +$103,428
- vs. engineer’s estimate
- -29.4%
- Unit price
- $128.00/TON
- Extension
- $117,504.00
- Proposal total
- $614,549
- vs. low bid
- +$119,563
- vs. engineer’s estimate
- -24.7%
5. Overland Corporation
- Unit price
- $165.00/TON
- Extension
- $151,470.00
- Proposal total
- $616,693
- vs. low bid
- +$121,707
- vs. engineer’s estimate
- -2.9%
- Unit price
- $197.00/TON
- Extension
- $180,846.00
- Proposal total
- $621,064
- vs. low bid
- +$126,078
- vs. engineer’s estimate
- +15.9%
- Unit price
- $175.00/TON
- Extension
- $160,650.00
- Proposal total
- $662,993
- vs. low bid
- +$168,007
- vs. engineer’s estimate
- +2.9%
- Unit price
- $120.00/TON
- Extension
- $110,160.00
- Proposal total
- $679,542
- vs. low bid
- +$184,556
- vs. engineer’s estimate
- -29.4%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0285-03-066 | Hays | Austin | 135 | 9 | Lone Star Sitework, LLC | $325.00 | $90.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 24,930 | 9 | Highway 19 Construction LLC | $131.00 | $110.00 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 918 | 8 | Jay Mills Contracting, Incorporated | $117.00 | $170.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 40,138 | 6 | Austin Bridge & Road Services, LP | $115.24 | $105.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 27,086 | 8 | Hunter Industries, Ltd. | $84.17 | $90.00 |
| 2026-10-06 | 2502-01-024 | Bell | Waco | 13,060 | 6 | Big Creek Construction, Ltd. | $90.00 | $88.00 |
| 2026-09-03 | 1479-01-028 | Bexar | San Antonio | 1,735 | 6 | Hunter Industries, Ltd. | $96.99 | $135.00 |
| 2026-09-02 | 0549-02-038 | Fannin | Paris | 1,736 | 4 | Highway 19 Construction LLC | $162.00 | $121.00 |
| 2026-09-02 | 0903-28-073 | Montague | Wichita Falls | 299 | 6 | Texas Steel Industrial Placing, LLC | $255.75 | $125.00 |
| 2026-09-02 | 0915-11-037 | Kendall | San Antonio | 339 | 8 | Delgado's Contractors, LLC | $175.00 | $86.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 25 | $140.00 | $132.00 | $250.00 | — |
| Amarillo | 12 | $150.00 | $192.00 | $140.00 | — |
| Austin | 143 | $115.24 | $117.00 | $95.00 | +20.81% |
| Beaumont | 4 | $130.00 | $355.00 | $195.00 | — |
| Brownwood | 14 | $300.00 | $362.50 | $250.00 | — |
| Corpus Christi | 26 | $192.00 | $226.86 | $130.00 | — |
| Dallas | 3 | $261.40 | $261.40 | $200.00 | — |
| El Paso | 11 | $105.00 | $105.00 | $125.00 | — |
| Fort Worth | 112 | $130.00 | $122.50 | $130.00 | -24.71% |
| Laredo | 18 | $110.25 | $115.00 | $125.00 | — |
| Paris | 35 | $131.00 | $132.00 | $110.00 | -9.59% |
| San Angelo | 6 | $135.00 | $172.00 | $150.00 | — |
| San Antonio | 146 | $76.92 | $77.00 | $77.00 | -8.33% |
| Waco | 26 | $90.00 | $96.00 | $88.00 | — |
| Wichita Falls | 58 | $102.00 | $111.00 | $78.80 | +1.79% |
| Yoakum | 88 | $87.75 | $121.00 | $105.00 | -26.66% |
Related items
- 341-7082 · Tack Coat ($4.00/GAL)
- 341-7050 · D-GR HMA TY-D SAC-B PG70-22 ($125.00/TON)
- 344-7077 · Tack Coat ($4.50/GAL)
- 344-7001 · SP Mixes SP-B PG64-22 ($127.00/TON)
- 400-7010 · CEM Stabil Bkfl ($133.66/CY)
- 401-7001 · Flowable Backfill ($231.39/CY)
- 402-7001 · Trench Excavation Protection ($4.65/LF)
- 403-7001 · Temporary SPL Shoring ($31.39/SF)
Is your price for item 341-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.