D-GR HMA TY-B PG64-22 (Item 341-7001): TxDOT Unit Price History

727 bids · 123 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure TON

TxDOT 341-7001 · D-GR HMA TY-B PG64-22 · Unit: TON

Low bid
$84.17/TON
Quantity-weighted median of winning unit prices
Weighted median
$85.40/TON
Quantity-weighted median of every bid
Engineer’s estimate
$82.50/TON
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-3.73%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$100.00$200.00$300.001101001K10K100K1MQuantity (TON), log scaleUnit price ($/TON)
Winning (low) bid Other bid Fitted price curve (ln price = 6.06 − 0.142·ln qty, R² 0.45)320 plotted bids, 6 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 341-7001 (D-GR HMA TY-B PG64-22) is measured in TON. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 727 bids for it on 123 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 387 bids was $85.40 per TON, and the winning low bidders priced it at a weighted median of $84.17 per TON.

TxDOT's engineer's estimate for the same lines had a weighted median of $82.50 per TON, so winning bids came in 2.0% above the estimate.

By calendar year, the median bid moved from $132.25 in 2025 (353 bids) to $126.80 in 2026 (367 bids), down 4.1%. The middle half of 2026 bids fell between $101.10 and $171.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 3.73%.

Quantity matters for this item. Lines of 9 to 1,622 TON had a weighted median of $163.00, while lines above 10,248 TON had $90.00, a 45% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 121 lines where both a winning and a second-place bid were published, the median winning unit price was $119.00 against $124.02 from the second-lowest bidder, a median gap of 3.91% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 13 TxDOT districts with at least ten bids, San Antonio had the lowest weighted median ($77.00) and Brownwood the highest ($362.50). The busiest district for this item was San Antonio.

The most recent letting with this item was on Nov 4, 2026 in Hays County, where Lone Star Sitework, LLC was the low bidder at $325.00 per TON for 135 TON against an estimate of $90.00.

2 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 341-7082 Tack Coat (weighted median $4.00 per GAL); 341-7050 D-GR HMA TY-D SAC-B PG70-22 (weighted median $125.00 per TON); 344-7077 Tack Coat (weighted median $4.50 per GAL); 344-7001 SP Mixes SP-B PG64-22 (weighted median $127.00 per TON).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
202471$90.72$90.42$90.42$89.00$94.05
202535364$111.62$102.00$132.25$103.20$181.00
202636759$100.24$87.45$126.80$101.10$171.00

Quantity bands

BandQuantity (TON)BidsWeighted avgWeighted median25th–75th pct
Small9–1,622255$174.34$163.00$141.61–$260.00
Medium1,735–9,967235$133.27$126.80$110.00–$150.00
Large10,248–157,288237$100.86$90.00$83.00–$121.00

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$119.00
Median second-low unit price
$124.02
Median engineer’s estimate
$115.00
Median gap, second vs. low
+3.91%

121 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District

Line quantity 135 TON · Engineer’s estimate $90.00/TON

  • 1. Lone Star Sitework, LLC

    LOW BID · WINNER
    Unit price
    $325.00/TON
    Extension
    $43,875.00
    Proposal total
    $950,337
    Money left on the table
    $133,497 (14.05%)
    vs. engineer’s estimate
    +261.1%
  • 2. Stx Civil

    Unit price
    $194.75/TON
    Extension
    $26,291.25
    Proposal total
    $1,083,834
    vs. low bid
    +$133,497
    vs. engineer’s estimate
    +116.4%
  • 3. Rucoba & Maya Construction, LLC

    Unit price
    $300.00/TON
    Extension
    $40,500.00
    Proposal total
    $1,103,755
    vs. low bid
    +$153,418
    vs. engineer’s estimate
    +233.3%
  • 4. Myers Concrete Construction, LP

    Unit price
    $383.00/TON
    Extension
    $51,705.00
    Proposal total
    $1,122,792
    vs. low bid
    +$172,455
    vs. engineer’s estimate
    +325.6%
  • Unit price
    $220.00/TON
    Extension
    $29,700.00
    Proposal total
    $1,135,337
    vs. low bid
    +$185,000
    vs. engineer’s estimate
    +144.4%
  • Unit price
    $178.00/TON
    Extension
    $24,030.00
    Proposal total
    $1,199,801
    vs. low bid
    +$249,464
    vs. engineer’s estimate
    +97.8%
  • 7. Ratliff Hardscape, Ltd.

    Unit price
    $464.32/TON
    Extension
    $62,683.20
    Proposal total
    $1,228,710
    vs. low bid
    +$278,373
    vs. engineer’s estimate
    +415.9%
  • Unit price
    $350.00/TON
    Extension
    $47,250.00
    Proposal total
    $1,272,000
    vs. low bid
    +$321,663
    vs. engineer’s estimate
    +288.9%
  • Unit price
    $350.00/TON
    Extension
    $47,250.00
    Proposal total
    $1,700,314
    vs. low bid
    +$749,977
    vs. engineer’s estimate
    +288.9%

Proposal 1017-03-040 · let Nov 4, 2026 · Hunt County, Paris District

Line quantity 24,930 TON · Engineer’s estimate $110.00/TON

  • 1. Highway 19 Construction LLC

    LOW BID · WINNER
    Unit price
    $131.00/TON
    Extension
    $3,265,830.00
    Proposal total
    $6,803,596
    Money left on the table
    $438,151 (6.44%)
    vs. engineer’s estimate
    +19.1%
  • Unit price
    $143.12/TON
    Extension
    $3,567,981.60
    Proposal total
    $7,241,746
    vs. low bid
    +$438,151
    vs. engineer’s estimate
    +30.1%
  • Unit price
    $132.00/TON
    Extension
    $3,290,760.00
    Proposal total
    $7,366,754
    vs. low bid
    +$563,159
    vs. engineer’s estimate
    +20%
  • Unit price
    $132.60/TON
    Extension
    $3,305,718.00
    Proposal total
    $7,400,348
    vs. low bid
    +$596,752
    vs. engineer’s estimate
    +20.5%
  • Unit price
    $123.74/TON
    Extension
    $3,084,838.20
    Proposal total
    $7,514,717
    vs. low bid
    +$711,122
    vs. engineer’s estimate
    +12.5%
  • Unit price
    $126.01/TON
    Extension
    $3,141,429.30
    Proposal total
    $7,794,981
    vs. low bid
    +$991,385
    vs. engineer’s estimate
    +14.6%
  • Unit price
    $142.00/TON
    Extension
    $3,540,060.00
    Proposal total
    $7,795,159
    vs. low bid
    +$991,563
    vs. engineer’s estimate
    +29.1%
  • Unit price
    $135.00/TON
    Extension
    $3,365,550.00
    Proposal total
    $8,325,506
    vs. low bid
    +$1,521,910
    vs. engineer’s estimate
    +22.7%
  • Unit price
    $132.00/TON
    Extension
    $3,290,760.00
    Proposal total
    $9,159,173
    vs. low bid
    +$2,355,578
    vs. engineer’s estimate
    +20%

Proposal 0008-02-078 · let Nov 3, 2026 · Parker County, Fort Worth District

Line quantity 918 TON · Engineer’s estimate $170.00/TON

  • 1. Jay Mills Contracting, Incorporated

    LOW BID · WINNER
    Unit price
    $117.00/TON
    Extension
    $107,406.00
    Proposal total
    $494,986
    Money left on the table
    $418 (0.08%)
    vs. engineer’s estimate
    -31.2%
  • Unit price
    $125.00/TON
    Extension
    $114,750.00
    Proposal total
    $495,404
    vs. low bid
    +$418.25
    vs. engineer’s estimate
    -26.5%
  • Unit price
    $120.00/TON
    Extension
    $110,160.00
    Proposal total
    $598,414
    vs. low bid
    +$103,428
    vs. engineer’s estimate
    -29.4%
  • Unit price
    $128.00/TON
    Extension
    $117,504.00
    Proposal total
    $614,549
    vs. low bid
    +$119,563
    vs. engineer’s estimate
    -24.7%
  • 5. Overland Corporation

    Unit price
    $165.00/TON
    Extension
    $151,470.00
    Proposal total
    $616,693
    vs. low bid
    +$121,707
    vs. engineer’s estimate
    -2.9%
  • Unit price
    $197.00/TON
    Extension
    $180,846.00
    Proposal total
    $621,064
    vs. low bid
    +$126,078
    vs. engineer’s estimate
    +15.9%
  • Unit price
    $175.00/TON
    Extension
    $160,650.00
    Proposal total
    $662,993
    vs. low bid
    +$168,007
    vs. engineer’s estimate
    +2.9%
  • Unit price
    $120.00/TON
    Extension
    $110,160.00
    Proposal total
    $679,542
    vs. low bid
    +$184,556
    vs. engineer’s estimate
    -29.4%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040285-03-066HaysAustin1359Lone Star Sitework, LLC$325.00$90.00
2026-11-041017-03-040HuntParis24,9309Highway 19 Construction LLC$131.00$110.00
2026-11-030008-02-078ParkerFort Worth9188Jay Mills Contracting, Incorporated$117.00$170.00
2026-11-030015-13-432TravisAustin40,1386Austin Bridge & Road Services, LP$115.24$105.00
2026-10-070143-03-049WilsonSan Antonio27,0868Hunter Industries, Ltd.$84.17$90.00
2026-10-062502-01-024BellWaco13,0606Big Creek Construction, Ltd.$90.00$88.00
2026-09-031479-01-028BexarSan Antonio1,7356Hunter Industries, Ltd.$96.99$135.00
2026-09-020549-02-038FanninParis1,7364Highway 19 Construction LLC$162.00$121.00
2026-09-020903-28-073MontagueWichita Falls2996Texas Steel Industrial Placing, LLC$255.75$125.00
2026-09-020915-11-037KendallSan Antonio3398Delgado's Contractors, LLC$175.00$86.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene25$140.00$132.00$250.00—
Amarillo12$150.00$192.00$140.00—
Austin143$115.24$117.00$95.00+20.81%
Beaumont4$130.00$355.00$195.00—
Brownwood14$300.00$362.50$250.00—
Corpus Christi26$192.00$226.86$130.00—
Dallas3$261.40$261.40$200.00—
El Paso11$105.00$105.00$125.00—
Fort Worth112$130.00$122.50$130.00-24.71%
Laredo18$110.25$115.00$125.00—
Paris35$131.00$132.00$110.00-9.59%
San Angelo6$135.00$172.00$150.00—
San Antonio146$76.92$77.00$77.00-8.33%
Waco26$90.00$96.00$88.00—
Wichita Falls58$102.00$111.00$78.80+1.79%
Yoakum88$87.75$121.00$105.00-26.66%

Related items

Is your price for item 341-7001 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.