Trench Excavation Protection (Item 402-7001): TxDOT Unit Price History
1,681 bids · 274 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 402-7001 · TRENCH EXCAVATION PROTECTION · Unit: LF
- Low bid
- $3.26/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $4.65/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $10.00/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- 0%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 402-7001 (Trench Excavation Protection) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,681 bids for it on 274 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 895 bids was $4.65 per LF, and the winning low bidders priced it at a weighted median of $3.26 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $10.00 per LF, so winning bids came in 67.4% below the estimate.
By calendar year, the median bid moved from $10.00 in 2025 (788 bids) to $10.00 in 2026 (823 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $3.58 and $20.00.
Comparing the last 12 months with the 12 months before, the median unit price did not change.
Quantity matters for this item. Lines of 6 to 150 LF had a weighted median of $15.00, while lines above 1,092 LF had $3.75, a 75% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 271 lines where both a winning and a second-place bid were published, the median winning unit price was $10.00 against $10.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 24 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($2.00) and Brownwood the highest ($66.13). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $1.00 per LF for 19,740 LF against an estimate of $7.50.
9 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 401-7001 Flowable Backfill (weighted median $231.39 per CY); 403-7001 Temporary SPL Shoring (weighted median $31.39 per SF); 400-7010 CEM Stabil Bkfl (weighted median $133.66 per CY); 416-7006 Drill Shaft (36 IN) (weighted median $270.00 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 70 | 11 | $8.62 | $5.00 | $10.57 | $5.69 | $30.00 |
| 2025 | 788 | 134 | $6.25 | $3.27 | $10.00 | $5.00 | $22.88 |
| 2026 | 823 | 129 | $7.08 | $4.65 | $10.00 | $3.58 | $20.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 6–150 | 562 | $40.87 | $15.00 | $10.00–$50.00 |
| Medium | 161–1,050 | 572 | $15.98 | $10.00 | $5.00–$20.00 |
| Large | 1,092–69,959.41 | 547 | $6.18 | $3.75 | $2.34–$10.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $10.00
- Median second-low unit price
- $10.00
- Median engineer’s estimate
- $13.00
- Median gap, second vs. low
- +0%
271 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 19,740 LF · Engineer’s estimate $7.50/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $1.00/LF | $19,740.00 | — | -86.7% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $3.15/LF | $62,181.00 | +$42,441 | -58% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $1.10/LF | $21,714.00 | +$1,974 | -85.3% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $1.00/LF | $19,740.00 | $0.000 | -86.7% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $1.00/LF
- Extension
- $19,740.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -86.7%
- Unit price
- $3.15/LF
- Extension
- $62,181.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- -58%
3. Tiseo Paving Company, LLC
- Unit price
- $1.10/LF
- Extension
- $21,714.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -85.3%
4. Harper Brothers Construction LLC
- Unit price
- $1.00/LF
- Extension
- $19,740.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -86.7%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 41,827 LF · Engineer’s estimate $10.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $7.00/LF | $292,789.00 | — | -30% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $2.45/LF | $102,476.15 | -$190,313 | -75.5% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $1.00/LF | $41,827.00 | -$250,962 | -90% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $5.92/LF | $247,615.84 | -$45,173 | -40.8% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $2.33/LF | $97,456.91 | -$195,332 | -76.7% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $2.42/LF | $101,221.34 | -$191,568 | -75.8% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $7.00/LF
- Extension
- $292,789.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -30%
2. Rpm Xconstruction, LLC
- Unit price
- $2.45/LF
- Extension
- $102,476.15
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -75.5%
- Unit price
- $1.00/LF
- Extension
- $41,827.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -90%
4. Webber, LLC
- Unit price
- $5.92/LF
- Extension
- $247,615.84
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -40.8%
5. Sema Construction, Inc.
- Unit price
- $2.33/LF
- Extension
- $97,456.91
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -76.7%
6. Zachry Construction Corporation
- Unit price
- $2.42/LF
- Extension
- $101,221.34
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -75.8%
Proposal 0262-01-034 · let Nov 4, 2026 · Milam County, Bryan District
Line quantity 175 LF · Engineer’s estimate $10.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Big Creek Construction, Ltd.LOW BID | $15.00/LF | $2,625.00 | — | +50% | $9,787,627 | $395,153 (4.04%) left on table |
| 2 | Larry Young Paving, Inc. | $1.00/LF | $175.00 | -$2,450 | -90% | $10,182,780 | +$395,153 |
| 3 | Knife River Corporation - South | $35.00/LF | $6,125.00 | +$3,500 | +250% | $10,424,591 | +$636,964 |
| 4 | Texas Materials Group, Inc. | $10.00/LF | $1,750.00 | -$875.00 | 0% | $12,020,138 | +$2,232,511 |
| 5 | A. L. Helmcamp, Inc. | $9.50/LF | $1,662.50 | -$962.50 | -5% | $12,374,454 | +$2,586,827 |
| 6 | Patin Construction LLC | $5.00/LF | $875.00 | -$1,750 | -50% | $15,629,317 | +$5,841,690 |
| 7 | Joe Bland Construction LLC | $5.00/LF | $875.00 | -$1,750 | -50% | $18,492,861 | +$8,705,235 |
1. Big Creek Construction, Ltd.
LOW BID · WINNER- Unit price
- $15.00/LF
- Extension
- $2,625.00
- Proposal total
- $9,787,627
- Money left on the table
- $395,153 (4.04%)
- vs. engineer’s estimate
- +50%
- Unit price
- $1.00/LF
- Extension
- $175.00
- Proposal total
- $10,182,780
- vs. low bid
- +$395,153
- vs. engineer’s estimate
- -90%
- Unit price
- $35.00/LF
- Extension
- $6,125.00
- Proposal total
- $10,424,591
- vs. low bid
- +$636,964
- vs. engineer’s estimate
- +250%
- Unit price
- $10.00/LF
- Extension
- $1,750.00
- Proposal total
- $12,020,138
- vs. low bid
- +$2,232,511
- vs. engineer’s estimate
- 0%
- Unit price
- $9.50/LF
- Extension
- $1,662.50
- Proposal total
- $12,374,454
- vs. low bid
- +$2,586,827
- vs. engineer’s estimate
- -5%
6. Patin Construction LLC
- Unit price
- $5.00/LF
- Extension
- $875.00
- Proposal total
- $15,629,317
- vs. low bid
- +$5,841,690
- vs. engineer’s estimate
- -50%
7. Joe Bland Construction LLC
- Unit price
- $5.00/LF
- Extension
- $875.00
- Proposal total
- $18,492,861
- vs. low bid
- +$8,705,235
- vs. engineer’s estimate
- -50%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 19,740 | 4 | Mario Sinacola & Sons Excavating, Inc. | $1.00 | $7.50 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 41,827 | 6 | Indus Road & Bridge, Inc. | $7.00 | $10.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 175 | 7 | Big Creek Construction, Ltd. | $15.00 | $10.00 |
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 80 | 2 | Texas Materials Group, Inc. | $6.60 | $25.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 174 | 9 | Highway 19 Construction LLC | $5.00 | $15.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 69,959.41 | 6 | Austin Bridge & Road Services, LP | $10.00 | $10.00 |
| 2026-10-13 | 6505-28-001 | Anderson | Tyler | 162 | 7 | Icos Management, LLC | $10.00 | $25.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 1,575 | 8 | Hunter Industries, Ltd. | $28.03 | $6.50 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 1,821 | 7 | Longview Bridge and Road, Ltd. | $10.00 | $12.00 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 824 | 6 | A. K. Gillis & Sons, LLC | $15.00 | $10.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 17 | $15.00 | $6.00 | $3.00 | — |
| Amarillo | 38 | $25.00 | $5.60 | $20.00 | -13.83% |
| Atlanta | 27 | $10.00 | $10.00 | $10.00 | — |
| Austin | 178 | $10.00 | $11.55 | $10.00 | -25.93% |
| Beaumont | 17 | $10.00 | $12.00 | $7.00 | — |
| Brownwood | 24 | $120.00 | $66.13 | $98.00 | — |
| Bryan | 82 | $15.00 | $10.00 | $10.00 | +25.96% |
| Childress | 16 | $49.50 | $45.00 | $60.00 | — |
| Corpus Christi | 45 | $2.00 | $4.95 | $1.00 | +100% |
| Dallas | 284 | $6.00 | $3.00 | $10.00 | +4.21% |
| El Paso | 18 | $3.00 | $3.75 | $7.00 | — |
| Fort Worth | 109 | $4.40 | $4.99 | $10.00 | -40% |
| Houston | 95 | $1.05 | $3.79 | $5.00 | -37.5% |
| Laredo | 47 | $2.42 | $6.27 | $8.00 | -41.58% |
| Lubbock | 13 | $3.00 | $3.00 | $11.00 | — |
| Lufkin | 40 | $10.00 | $8.50 | $12.00 | -34.37% |
| Odessa | 14 | $38.50 | $2.20 | $15.00 | — |
| Paris | 71 | $3.26 | $11.60 | $7.40 | +29.31% |
| Pharr | 129 | $1.00 | $2.00 | $10.00 | -43.92% |
| San Antonio | 124 | $3.68 | $5.00 | $9.75 | -48.17% |
| Tyler | 80 | $9.00 | $5.00 | $9.00 | 0% |
| Waco | 64 | $10.00 | $5.00 | $6.00 | -5.35% |
| Wichita Falls | 44 | $10.00 | $10.00 | $15.00 | -33.33% |
| Yoakum | 105 | $2.00 | $10.92 | $13.00 | -9.58% |
Related items
- 401-7001 · Flowable Backfill ($231.39/CY)
- 403-7001 · Temporary SPL Shoring ($31.39/SF)
- 400-7010 · CEM Stabil Bkfl ($133.66/CY)
- 416-7006 · Drill Shaft (36 IN) ($270.00/LF)
- 416-7040 · Drill Shaft (Rdwy ILL Pole) (30 IN) ($255.00/LF)
- 420-7012 · CL C Conc (Abut) ($1,250.00/CY)
- 429-7007 · Conc STR Repair (Vertical & Overhead) ($150.00/SF)
- 432-7013 · Riprap (MOW Strip)(4 IN) ($645.00/CY)
Is your price for item 402-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.