CEM Stabil Bkfl (Item 400-7010): TxDOT Unit Price History
2,973 bids · 451 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure CY
TxDOT 400-7010 · CEM STABIL BKFL · Unit: CY
- Low bid
- $100.00/CY
- Quantity-weighted median of winning unit prices
- Weighted median
- $133.66/CY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $150.00/CY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -18.92%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 400-7010 (CEM Stabil Bkfl) is measured in CY. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 2,973 bids for it on 451 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,585 bids was $133.66 per CY, and the winning low bidders priced it at a weighted median of $100.00 per CY.
TxDOT's engineer's estimate for the same lines had a weighted median of $150.00 per CY, so winning bids came in 33.3% below the estimate.
By calendar year, the median bid moved from $242.00 in 2025 (1,446 bids) to $205.63 in 2026 (1,442 bids), down 15.0%. The middle half of 2026 bids fell between $148.77 and $275.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 18.92%.
Quantity matters for this item. Lines of 1 to 100 CY had a weighted median of $250.00, while lines above 305 CY had $130.19, a 48% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 444 lines where both a winning and a second-place bid were published, the median winning unit price was $216.51 against $216.30 from the second-lowest bidder, a median gap of 4.27% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 25 TxDOT districts with at least ten bids, Houston had the lowest weighted median ($62.38) and Brownwood the highest ($343.00). The busiest district for this item was Yoakum.
The most recent letting with this item was on Nov 12, 2026 in Denton County, where Road Doctors LLC was the low bidder at $250.00 per CY for 93 CY against an estimate of $400.00.
12 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 401-7001 Flowable Backfill (weighted median $231.39 per CY); 402-7001 Trench Excavation Protection (weighted median $4.65 per LF); 403-7001 Temporary SPL Shoring (weighted median $31.39 per SF); 416-7006 Drill Shaft (36 IN) (weighted median $270.00 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 85 | 13 | $160.66 | $108.40 | $245.00 | $162.32 | $300.00 |
| 2025 | 1,446 | 227 | $184.62 | $153.60 | $242.00 | $175.00 | $308.02 |
| 2026 | 1,442 | 212 | $142.04 | $132.00 | $205.63 | $148.77 | $275.00 |
Quantity bands
| Band | Quantity (CY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–100 | 996 | $261.28 | $250.00 | $185.00–$350.00 |
| Medium | 102–304.3 | 988 | $245.31 | $236.50 | $182.33–$300.00 |
| Large | 305–17,647 | 989 | $149.05 | $130.19 | $125.00–$246.77 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $216.51
- Median second-low unit price
- $216.30
- Median engineer’s estimate
- $218.50
- Median gap, second vs. low
- +4.27%
444 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6497-55-001 · let Nov 12, 2026 · Denton County, Dallas District
Line quantity 93 CY · Engineer’s estimate $400.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Road Doctors LLCLOW BID | $250.00/CY | $23,250.00 | — | -37.5% | $493,320 | $25,748 (5.22%) left on table |
| 2 | Icos Management, LLC | $315.00/CY | $29,295.00 | +$6,045 | -21.3% | $519,068 | +$25,748 |
| 3 | Texas Road Construction, LLC | $250.00/CY | $23,250.00 | $0.000 | -37.5% | $567,220 | +$73,900 |
| 4 | Rear Contractors LLC | $400.00/CY | $37,200.00 | +$13,950 | 0% | $598,798 | +$105,478 |
| 5 | Premier Contractors LLC | $550.00/CY | $51,150.00 | +$27,900 | +37.5% | $654,688 | +$161,368 |
| 6 | Jr West Texas Concrete LLC | $349.00/CY | $32,457.00 | +$9,207 | -12.8% | $746,209 | +$252,889 |
- LOW BID · WINNER
- Unit price
- $250.00/CY
- Extension
- $23,250.00
- Proposal total
- $493,320
- Money left on the table
- $25,748 (5.22%)
- vs. engineer’s estimate
- -37.5%
- Unit price
- $315.00/CY
- Extension
- $29,295.00
- Proposal total
- $519,068
- vs. low bid
- +$25,748
- vs. engineer’s estimate
- -21.3%
- Unit price
- $250.00/CY
- Extension
- $23,250.00
- Proposal total
- $567,220
- vs. low bid
- +$73,900
- vs. engineer’s estimate
- -37.5%
- Unit price
- $400.00/CY
- Extension
- $37,200.00
- Proposal total
- $598,798
- vs. low bid
- +$105,478
- vs. engineer’s estimate
- 0%
- Unit price
- $550.00/CY
- Extension
- $51,150.00
- Proposal total
- $654,688
- vs. low bid
- +$161,368
- vs. engineer’s estimate
- +37.5%
6. Jr West Texas Concrete LLC
- Unit price
- $349.00/CY
- Extension
- $32,457.00
- Proposal total
- $746,209
- vs. low bid
- +$252,889
- vs. engineer’s estimate
- -12.8%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 1,194 CY · Engineer’s estimate $275.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $245.00/CY | $292,530.00 | — | -10.9% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $216.00/CY | $257,904.00 | -$34,626 | -21.5% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $200.00/CY | $238,800.00 | -$53,730 | -27.3% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $133.34/CY | $159,207.96 | -$133,322 | -51.5% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $210.81/CY | $251,707.14 | -$40,823 | -23.3% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $176.98/CY | $211,314.12 | -$81,216 | -35.6% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $245.00/CY
- Extension
- $292,530.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -10.9%
2. Rpm Xconstruction, LLC
- Unit price
- $216.00/CY
- Extension
- $257,904.00
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -21.5%
- Unit price
- $200.00/CY
- Extension
- $238,800.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -27.3%
4. Webber, LLC
- Unit price
- $133.34/CY
- Extension
- $159,207.96
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -51.5%
5. Sema Construction, Inc.
- Unit price
- $210.81/CY
- Extension
- $251,707.14
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -23.3%
6. Zachry Construction Corporation
- Unit price
- $176.98/CY
- Extension
- $211,314.12
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -35.6%
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 1,247 CY · Engineer’s estimate $175.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $110.00/CY | $137,170.00 | — | -37.1% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $155.00/CY | $193,285.00 | +$56,115 | -11.4% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $181.00/CY | $225,707.00 | +$88,537 | +3.4% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $110.00/CY | $137,170.00 | $0.000 | -37.1% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $99.35/CY | $123,889.45 | -$13,281 | -43.2% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $152.00/CY | $189,544.00 | +$52,374 | -13.1% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $130.00/CY | $162,110.00 | +$24,940 | -25.7% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $135.00/CY | $168,345.00 | +$31,175 | -22.9% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $171.04/CY | $213,286.88 | +$76,117 | -2.3% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $135.58/CY | $169,068.26 | +$31,898 | -22.5% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $97.75/CY | $121,894.25 | -$15,276 | -44.1% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $141.00/CY | $175,827.00 | +$38,657 | -19.4% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $110.00/CY
- Extension
- $137,170.00
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- -37.1%
- Unit price
- $155.00/CY
- Extension
- $193,285.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- -11.4%
- Unit price
- $181.00/CY
- Extension
- $225,707.00
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- +3.4%
- Unit price
- $110.00/CY
- Extension
- $137,170.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- -37.1%
- Unit price
- $99.35/CY
- Extension
- $123,889.45
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- -43.2%
- Unit price
- $152.00/CY
- Extension
- $189,544.00
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- -13.1%
- Unit price
- $130.00/CY
- Extension
- $162,110.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- -25.7%
- Unit price
- $135.00/CY
- Extension
- $168,345.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- -22.9%
9. Zachry Construction Corporation
- Unit price
- $171.04/CY
- Extension
- $213,286.88
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- -2.3%
10. Brizo Construction, LLC
- Unit price
- $135.58/CY
- Extension
- $169,068.26
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- -22.5%
- Unit price
- $97.75/CY
- Extension
- $121,894.25
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- -44.1%
- Unit price
- $141.00/CY
- Extension
- $175,827.00
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- -19.4%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-12 | 6497-55-001 | Denton | Dallas | 93 | 6 | Road Doctors LLC | $250.00 | $400.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 1,194 | 6 | Indus Road & Bridge, Inc. | $245.00 | $275.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 1,247 | 12 | Fluor Enterprises, Inc. | $110.00 | $175.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 103 | 7 | Big Creek Construction, Ltd. | $250.00 | $116.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 282 | 7 | Stx Civil | $175.85 | $150.00 |
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 56 | 2 | Texas Materials Group, Inc. | $311.30 | $135.00 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 57 | 5 | J E Construction Services, LLC | $60.00 | $75.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 5,941.4 | 6 | Austin Bridge & Road Services, LP | $238.67 | $306.00 |
| 2026-11-03 | 0917-30-068 | Burleson | Bryan | 88.2 | 15 | C & W Southern LLC | $225.00 | $275.00 |
| 2026-10-07 | 0014-23-041 | Hill | Waco | 100 | 5 | Northeastern Pavers, LLC | $100.00 | $170.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 81 | $100.00 | $183.00 | $130.00 | -3.8% |
| Amarillo | 46 | $180.00 | $216.25 | $175.00 | -10.11% |
| Atlanta | 43 | $180.00 | $225.00 | $275.00 | -18.83% |
| Austin | 128 | $238.67 | $220.87 | $306.00 | +0.4% |
| Beaumont | 82 | $80.00 | $155.00 | $200.00 | -34.8% |
| Brownwood | 28 | $400.00 | $343.00 | $288.00 | — |
| Bryan | 204 | $150.00 | $152.00 | $190.00 | -9.09% |
| Childress | 15 | $301.00 | $301.00 | $250.00 | — |
| Corpus Christi | 159 | $52.00 | $89.08 | $60.00 | -0.88% |
| Dallas | 285 | $180.00 | $202.27 | $200.00 | -17.58% |
| El Paso | 21 | $167.00 | $183.50 | $185.00 | — |
| Fort Worth | 153 | $200.00 | $200.00 | $190.00 | -15.82% |
| Houston | 275 | $63.90 | $62.38 | $75.00 | -16.67% |
| Laredo | 65 | $100.00 | $130.19 | $150.00 | -27.43% |
| Lubbock | 58 | $300.00 | $300.00 | $175.00 | -12.5% |
| Lufkin | 160 | $120.00 | $250.00 | $225.00 | -8.67% |
| Odessa | 68 | $299.02 | $233.89 | $225.00 | +1.63% |
| Paris | 107 | $115.00 | $215.00 | $208.00 | -16.67% |
| Pharr | 155 | $59.00 | $80.10 | $70.00 | -20% |
| San Angelo | 32 | $200.00 | $222.50 | $200.00 | -25.83% |
| San Antonio | 119 | $117.90 | $157.83 | $110.00 | -24.44% |
| Tyler | 89 | $128.00 | $185.00 | $250.00 | -18.05% |
| Waco | 122 | $155.00 | $168.00 | $180.00 | -2.08% |
| Wichita Falls | 77 | $200.00 | $280.00 | $215.00 | -10.17% |
| Yoakum | 401 | $75.00 | $112.36 | $161.00 | -7.73% |
Related items
- 401-7001 · Flowable Backfill ($231.39/CY)
- 402-7001 · Trench Excavation Protection ($4.65/LF)
- 403-7001 · Temporary SPL Shoring ($31.39/SF)
- 416-7006 · Drill Shaft (36 IN) ($270.00/LF)
- 416-7040 · Drill Shaft (Rdwy ILL Pole) (30 IN) ($255.00/LF)
- 420-7012 · CL C Conc (Abut) ($1,250.00/CY)
- 429-7007 · Conc STR Repair (Vertical & Overhead) ($150.00/SF)
- 432-7013 · Riprap (MOW Strip)(4 IN) ($645.00/CY)
Is your price for item 400-7010 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.