Instl DEL Assm (D-SW)SZ 1(BRF)GF2(BI) (Item 658-7019): TxDOT Unit Price History
2,045 bids · 320 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure EA
TxDOT 658-7019 · INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) · Unit: EA
- Low bid
- $35.00/EA
- Quantity-weighted median of winning unit prices
- Weighted median
- $25.00/EA
- Quantity-weighted median of every bid
- Engineer’s estimate
- $35.00/EA
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -2.78%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 658-7019 (Instl DEL Assm (D-SW)SZ 1(BRF)GF2(BI)) is measured in EA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 2,045 bids for it on 320 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 959 bids was $25.00 per EA, and the winning low bidders priced it at a weighted median of $35.00 per EA.
Winning unit prices sat close to TxDOT's own engineer's estimate ($35.00 per EA), within two percent.
By calendar year, the median bid moved from $35.00 in 2025 (1,102 bids) to $34.95 in 2026 (872 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $27.00 and $45.63.
Comparing the last 12 months with the 12 months before, the median unit price fell 2.78%.
Quantity matters for this item. Lines of 2 to 12 EA had a weighted median of $35.00, while lines above 28 EA had $27.00, a 23% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 293 lines where both a winning and a second-place bid were published, the median winning unit price was $35.00 against $35.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 25 TxDOT districts with at least ten bids, Houston had the lowest weighted median ($5.00) and El Paso the highest ($75.00). The busiest district for this item was Yoakum.
The most recent letting with this item was on Nov 4, 2026 in Hunt County, where Highway 19 Construction LLC was the low bidder at $25.00 per EA for 15 EA against an estimate of $32.00.
59 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 658-7013 Instl DEL Assm (D-SW)SZ 1(BRF)CTB (BI) (weighted median $30.00 per EA); 662-7112 WK ZN PAV MRK SHT Term (TAB)TY W (weighted median $1.08 per EA); 662-7114 WK ZN PAV MRK SHT Term (TAB)TY Y-2 (weighted median $1.00 per EA); 662-7038 WK ZN PAV MRK NON-Remov (Y)6"(SLD) (weighted median $0.220 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 71 | 10 | $46.25 | $45.00 | $42.95 | $32.75 | $50.21 |
| 2025 | 1,102 | 179 | $38.20 | $35.00 | $35.00 | $29.72 | $49.99 |
| 2026 | 872 | 132 | $26.77 | $24.00 | $34.95 | $27.00 | $45.63 |
Quantity bands
| Band | Quantity (EA) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 2–12 | 695 | $41.96 | $35.00 | $27.67–$50.00 |
| Medium | 13–27 | 671 | $42.78 | $35.00 | $29.10–$50.00 |
| Large | 28–4,000 | 679 | $30.19 | $27.00 | $27.50–$46.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $35.00
- Median second-low unit price
- $35.00
- Median engineer’s estimate
- $40.00
- Median gap, second vs. low
- +0%
293 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 1017-03-040 · let Nov 4, 2026 · Hunt County, Paris District
Line quantity 15 EA · Engineer’s estimate $32.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Highway 19 Construction LLCLOW BID | $25.00/EA | $375.00 | — | -21.9% | $6,803,596 | $438,151 (6.44%) left on table |
| 2 | Thk Construction LLC | $26.25/EA | $393.75 | +$18.75 | -18% | $7,241,746 | +$438,151 |
| 3 | East Texas Bridge, Inc. | $30.00/EA | $450.00 | +$75.00 | -6.3% | $7,366,754 | +$563,159 |
| 4 | D. L. Lennon Incorporated - Contractor | $25.00/EA | $375.00 | $0.000 | -21.9% | $7,400,348 | +$596,752 |
| 5 | Rk Hall, LLC | $32.55/EA | $488.25 | +$113.25 | +1.7% | $7,514,717 | +$711,122 |
| 6 | Austin Bridge & Road Services, LP | $25.00/EA | $375.00 | $0.000 | -21.9% | $7,794,981 | +$991,385 |
| 7 | Texas Materials Group, Inc. | $22.00/EA | $330.00 | -$45.00 | -31.3% | $7,795,159 | +$991,563 |
| 8 | Cdm Holdings | $28.00/EA | $420.00 | +$45.00 | -12.5% | $8,325,506 | +$1,521,910 |
| 9 | Ed Bell Construction Company | $30.00/EA | $450.00 | +$75.00 | -6.3% | $9,159,173 | +$2,355,578 |
1. Highway 19 Construction LLC
LOW BID · WINNER- Unit price
- $25.00/EA
- Extension
- $375.00
- Proposal total
- $6,803,596
- Money left on the table
- $438,151 (6.44%)
- vs. engineer’s estimate
- -21.9%
- Unit price
- $26.25/EA
- Extension
- $393.75
- Proposal total
- $7,241,746
- vs. low bid
- +$438,151
- vs. engineer’s estimate
- -18%
- Unit price
- $30.00/EA
- Extension
- $450.00
- Proposal total
- $7,366,754
- vs. low bid
- +$563,159
- vs. engineer’s estimate
- -6.3%
- Unit price
- $25.00/EA
- Extension
- $375.00
- Proposal total
- $7,400,348
- vs. low bid
- +$596,752
- vs. engineer’s estimate
- -21.9%
5. Rk Hall, LLC
- Unit price
- $32.55/EA
- Extension
- $488.25
- Proposal total
- $7,514,717
- vs. low bid
- +$711,122
- vs. engineer’s estimate
- +1.7%
- Unit price
- $25.00/EA
- Extension
- $375.00
- Proposal total
- $7,794,981
- vs. low bid
- +$991,385
- vs. engineer’s estimate
- -21.9%
- Unit price
- $22.00/EA
- Extension
- $330.00
- Proposal total
- $7,795,159
- vs. low bid
- +$991,563
- vs. engineer’s estimate
- -31.3%
8. Cdm Holdings
- Unit price
- $28.00/EA
- Extension
- $420.00
- Proposal total
- $8,325,506
- vs. low bid
- +$1,521,910
- vs. engineer’s estimate
- -12.5%
- Unit price
- $30.00/EA
- Extension
- $450.00
- Proposal total
- $9,159,173
- vs. low bid
- +$2,355,578
- vs. engineer’s estimate
- -6.3%
Proposal 0022-03-032 · let Nov 3, 2026 · Terrell County, Odessa District
Line quantity 26 EA · Engineer’s estimate $54.10/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | The Truesdell CorporationLOW BID | $40.00/EA | $1,040.00 | — | -26.1% | $2,888,888 | $89,789 (3.11%) left on table |
| 2 | Relmco, Inc. | $35.00/EA | $910.00 | -$130.00 | -35.3% | $2,978,677 | +$89,789 |
| 3 | Pathfield Investments LLC | $95.00/EA | $2,470.00 | +$1,430 | +75.6% | $3,052,152 | +$163,264 |
| 4 | Structural Integrity Group LLC | $35.00/EA | $910.00 | -$130.00 | -35.3% | $3,205,119 | +$316,231 |
| 5 | Massana Construction Inc. | $45.00/EA | $1,170.00 | +$130.00 | -16.8% | $3,332,351 | +$443,463 |
| 6 | Scr Civil Construction, LLC | $42.00/EA | $1,092.00 | +$52.00 | -22.4% | $3,557,553 | +$668,665 |
| 7 | Ragle Construction, Inc. | $35.00/EA | $910.00 | -$130.00 | -35.3% | $3,982,565 | +$1,093,677 |
- LOW BID · WINNER
- Unit price
- $40.00/EA
- Extension
- $1,040.00
- Proposal total
- $2,888,888
- Money left on the table
- $89,789 (3.11%)
- vs. engineer’s estimate
- -26.1%
2. Relmco, Inc.
- Unit price
- $35.00/EA
- Extension
- $910.00
- Proposal total
- $2,978,677
- vs. low bid
- +$89,789
- vs. engineer’s estimate
- -35.3%
- Unit price
- $95.00/EA
- Extension
- $2,470.00
- Proposal total
- $3,052,152
- vs. low bid
- +$163,264
- vs. engineer’s estimate
- +75.6%
- Unit price
- $35.00/EA
- Extension
- $910.00
- Proposal total
- $3,205,119
- vs. low bid
- +$316,231
- vs. engineer’s estimate
- -35.3%
- Unit price
- $45.00/EA
- Extension
- $1,170.00
- Proposal total
- $3,332,351
- vs. low bid
- +$443,463
- vs. engineer’s estimate
- -16.8%
- Unit price
- $42.00/EA
- Extension
- $1,092.00
- Proposal total
- $3,557,553
- vs. low bid
- +$668,665
- vs. engineer’s estimate
- -22.4%
- Unit price
- $35.00/EA
- Extension
- $910.00
- Proposal total
- $3,982,565
- vs. low bid
- +$1,093,677
- vs. engineer’s estimate
- -35.3%
Proposal 6507-80-001 · let Oct 28, 2026 · Angelina County, Lufkin District
Line quantity 20 EA · Engineer’s estimate $20.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Blacksmith Ventures LLCLOW BID | $50.00/EA | $1,000.00 | — | +150% | $681,151 | $163,607 (24.02%) left on table |
| 2 | Garret Shields Infrastructure | $40.00/EA | $800.00 | -$200.00 | +100% | $844,758 | +$163,607 |
| 3 | Ace Contractors, Inc. | $40.00/EA | $800.00 | -$200.00 | +100% | $893,898 | +$212,747 |
| 4 | Shalom Services Corporation | $50.00/EA | $1,000.00 | $0.000 | +150% | $959,894 | +$278,743 |
| 5 | Icos Management, LLC | $42.00/EA | $840.00 | -$160.00 | +110% | $962,069 | +$280,917 |
| 6 | Road Doctors LLC | $75.00/EA | $1,500.00 | +$500.00 | +275% | $966,295 | +$285,144 |
| 7 | Rear Contractors LLC | $50.00/EA | $1,000.00 | $0.000 | +150% | $1,158,023 | +$476,872 |
| 8 | Structural Integrity Group LLC | $50.00/EA | $1,000.00 | $0.000 | +150% | $1,509,149 | +$827,998 |
- LOW BID · WINNER
- Unit price
- $50.00/EA
- Extension
- $1,000.00
- Proposal total
- $681,151
- Money left on the table
- $163,607 (24.02%)
- vs. engineer’s estimate
- +150%
2. Garret Shields Infrastructure
- Unit price
- $40.00/EA
- Extension
- $800.00
- Proposal total
- $844,758
- vs. low bid
- +$163,607
- vs. engineer’s estimate
- +100%
- Unit price
- $40.00/EA
- Extension
- $800.00
- Proposal total
- $893,898
- vs. low bid
- +$212,747
- vs. engineer’s estimate
- +100%
- Unit price
- $50.00/EA
- Extension
- $1,000.00
- Proposal total
- $959,894
- vs. low bid
- +$278,743
- vs. engineer’s estimate
- +150%
- Unit price
- $42.00/EA
- Extension
- $840.00
- Proposal total
- $962,069
- vs. low bid
- +$280,917
- vs. engineer’s estimate
- +110%
- Unit price
- $75.00/EA
- Extension
- $1,500.00
- Proposal total
- $966,295
- vs. low bid
- +$285,144
- vs. engineer’s estimate
- +275%
- Unit price
- $50.00/EA
- Extension
- $1,000.00
- Proposal total
- $1,158,023
- vs. low bid
- +$476,872
- vs. engineer’s estimate
- +150%
- Unit price
- $50.00/EA
- Extension
- $1,000.00
- Proposal total
- $1,509,149
- vs. low bid
- +$827,998
- vs. engineer’s estimate
- +150%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 15 | 9 | Highway 19 Construction LLC | $25.00 | $32.00 |
| 2026-11-03 | 0022-03-032 | Terrell | Odessa | 26 | 7 | The Truesdell Corporation | $40.00 | $54.10 |
| 2026-10-28 | 6507-80-001 | Angelina | Lufkin | 20 | 8 | Blacksmith Ventures LLC | $50.00 | $20.00 |
| 2026-10-07 | 0022-01-034 | Terrell | Odessa | 16 | 7 | Relmco, Inc. | $38.50 | $40.00 |
| 2026-10-07 | 0922-20-030 | La Salle | Laredo | 20 | 6 | Presidio Contracting, LLC | $30.00 | $100.00 |
| 2026-10-07 | 6503-84-001 | McLennan | Waco | 35 | 4 | T&l Cleaning Services LLC | $10.00 | $32.50 |
| 2026-10-06 | 0912-34-209 | Fort Bend | Houston | 41 | 9 | Garret Shields Infrastructure | $40.00 | $38.13 |
| 2026-10-06 | 1122-01-034 | Karnes | Corpus Christi | 8 | 7 | Ck Newberry, LLC | $40.00 | $25.00 |
| 2026-10-06 | 1414-03-043 | Brazoria | Houston | 24 | 2 | Durwood Greene Construction Co. | $56.00 | $21.00 |
| 2026-10-06 | 6504-87-001 | Bell | Waco | 25 | 3 | Ross Sa Enterprise LLC | $25.00 | $32.50 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 119 | $50.00 | $45.00 | $55.00 | 0% |
| Amarillo | 19 | $96.30 | $45.00 | $40.00 | — |
| Atlanta | 88 | $45.00 | $45.00 | $30.00 | -6.4% |
| Austin | 54 | $50.00 | $26.00 | $17.00 | -35.21% |
| Beaumont | 61 | $26.00 | $30.00 | $40.00 | -13.04% |
| Brownwood | 66 | $35.00 | $36.00 | $47.00 | +2.86% |
| Bryan | 92 | $30.00 | $30.00 | $40.00 | 0% |
| Childress | 62 | $44.00 | $31.00 | $65.00 | -20.38% |
| Corpus Christi | 77 | $50.00 | $50.00 | $4.00 | 0% |
| Dallas | 175 | $20.00 | $29.00 | $320.00 | -19.24% |
| El Paso | 26 | $100.00 | $75.00 | $75.00 | — |
| Fort Worth | 114 | $40.00 | $30.00 | $38.00 | -12.86% |
| Houston | 107 | $33.00 | $5.00 | $21.00 | +9.38% |
| Laredo | 25 | $50.00 | $50.00 | $40.00 | +19.1% |
| Lubbock | 17 | $5.00 | $12.00 | $5.00 | — |
| Lufkin | 115 | $26.25 | $30.00 | $25.00 | -14.29% |
| Odessa | 32 | $40.00 | $45.00 | $54.10 | -9.55% |
| Paris | 115 | $31.00 | $30.00 | $45.00 | -11.29% |
| Pharr | 31 | $35.00 | $35.00 | $35.00 | +2.82% |
| San Angelo | 38 | $20.00 | $20.00 | $30.00 | -35.15% |
| San Antonio | 52 | $25.00 | $29.64 | $40.00 | -12.38% |
| Tyler | 65 | $31.00 | $29.00 | $36.00 | 0% |
| Waco | 118 | $49.50 | $45.00 | $40.00 | -2.6% |
| Wichita Falls | 69 | $28.00 | $27.50 | $20.00 | -6.45% |
| Yoakum | 308 | $28.00 | $30.00 | $35.00 | -1.23% |
Related items
- 658-7013 · Instl DEL Assm (D-SW)SZ 1(BRF)CTB (BI) ($30.00/EA)
- 662-7112 · WK ZN PAV MRK SHT Term (TAB)TY W ($1.08/EA)
- 662-7114 · WK ZN PAV MRK SHT Term (TAB)TY Y-2 ($1.00/EA)
- 662-7038 · WK ZN PAV MRK NON-Remov (Y)6"(SLD) ($0.220/LF)
- 662-7008 · WK ZN PAV MRK NON-Remov (W)6"(SLD) ($0.250/LF)
- 662-7100 · WK ZN PAV MRK Remov (Y)6"(SLD) ($0.800/LF)
- 662-7068 · WK ZN PAV MRK Remov (W)6"(SLD) ($0.760/LF)
- 666-7024 · Refl PAV MRK TY I (W)8"(SLD)(100MIL) ($0.850/LF)
Is your price for item 658-7019 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.