WK ZN PAV MRK NON-Remov (Y)6"(SLD) (Item 662-7038): TxDOT Unit Price History
1,876 bids · 334 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 662-7038 · WK ZN PAV MRK NON-REMOV (Y)6"(SLD) · Unit: LF
- Low bid
- $0.210/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $0.220/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $0.300/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -7.89%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 662-7038 (WK ZN PAV MRK NON-Remov (Y)6"(SLD)) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,876 bids for it on 334 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 990 bids was $0.220 per LF, and the winning low bidders priced it at a weighted median of $0.210 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $0.300 per LF, so winning bids came in 30.0% below the estimate.
By calendar year, the median bid moved from $0.380 in 2025 (913 bids) to $0.350 in 2026 (921 bids), down 7.9%. The middle half of 2026 bids fell between $0.250 and $0.520.
Comparing the last 12 months with the 12 months before, the median unit price fell 7.89%.
Quantity matters for this item. Lines of 25 to 18,304 LF had a weighted median of $0.500, while lines above 58,214 LF had $0.230, a 54% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 329 lines where both a winning and a second-place bid were published, the median winning unit price was $0.350 against $0.350 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Waco had the lowest weighted median ($0.140) and Pharr the highest ($0.500). The busiest district for this item was Austin.
The most recent letting with this item was on Nov 4, 2026 in Hays County, where Bobcat Services, Inc. was the low bidder at $0.370 per LF for 68,847 LF against an estimate of $0.250.
13 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 662-7112 WK ZN PAV MRK SHT Term (TAB)TY W (weighted median $1.08 per EA); 662-7114 WK ZN PAV MRK SHT Term (TAB)TY Y-2 (weighted median $1.00 per EA); 662-7008 WK ZN PAV MRK NON-Remov (W)6"(SLD) (weighted median $0.250 per LF); 662-7100 WK ZN PAV MRK Remov (Y)6"(SLD) (weighted median $0.800 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 42 | 8 | $0.350 | $0.330 | $0.400 | $0.330 | $0.560 |
| 2025 | 913 | 168 | $0.330 | $0.260 | $0.380 | $0.250 | $0.620 |
| 2026 | 921 | 158 | $0.280 | $0.220 | $0.350 | $0.250 | $0.520 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 25–18,304 | 627 | $0.650 | $0.500 | $0.410–$1.05 |
| Medium | 18,360–57,174 | 625 | $0.420 | $0.340 | $0.250–$0.500 |
| Large | 58,214–1,216,676 | 624 | $0.270 | $0.230 | $0.200–$0.350 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $0.350
- Median second-low unit price
- $0.350
- Median engineer’s estimate
- $0.410
- Median gap, second vs. low
- +0%
329 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0016-03-125 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 68,847 LF · Engineer’s estimate $0.250/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Bobcat Services, Inc.LOW BID | $0.37/LF | $25,473.39 | — | +48% | $2,797,454 | $386,828 (13.83%) left on table |
| 2 | Hunter Industries, Ltd. | $0.35/LF | $24,096.45 | -$1,377 | +40% | $3,184,282 | +$386,828 |
| 3 | Dean Word Company, Ltd. | $0.35/LF | $24,096.45 | -$1,377 | +40% | $3,495,937 | +$698,482 |
| 4 | Texas Materials Group, Inc. | $0.40/LF | $27,538.80 | +$2,065 | +60% | $3,586,449 | +$788,995 |
| 5 | Lone Star Paving Company | $0.35/LF | $24,096.45 | -$1,377 | +40% | $3,801,261 | +$1,003,807 |
| 6 | Clark Construction of Texas, Inc. | $0.35/LF | $24,096.45 | -$1,377 | +40% | $3,825,058 | +$1,027,604 |
1. Bobcat Services, Inc.
LOW BID · WINNER- Unit price
- $0.37/LF
- Extension
- $25,473.39
- Proposal total
- $2,797,454
- Money left on the table
- $386,828 (13.83%)
- vs. engineer’s estimate
- +48%
- Unit price
- $0.35/LF
- Extension
- $24,096.45
- Proposal total
- $3,184,282
- vs. low bid
- +$386,828
- vs. engineer’s estimate
- +40%
- Unit price
- $0.35/LF
- Extension
- $24,096.45
- Proposal total
- $3,495,937
- vs. low bid
- +$698,482
- vs. engineer’s estimate
- +40%
- Unit price
- $0.40/LF
- Extension
- $27,538.80
- Proposal total
- $3,586,449
- vs. low bid
- +$788,995
- vs. engineer’s estimate
- +60%
- Unit price
- $0.35/LF
- Extension
- $24,096.45
- Proposal total
- $3,801,261
- vs. low bid
- +$1,003,807
- vs. engineer’s estimate
- +40%
- Unit price
- $0.35/LF
- Extension
- $24,096.45
- Proposal total
- $3,825,058
- vs. low bid
- +$1,027,604
- vs. engineer’s estimate
- +40%
Proposal 0157-04-058 · let Nov 4, 2026 · Haskell County, Abilene District
Line quantity 59,705 LF · Engineer’s estimate $0.400/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Paving CompanyLOW BID | $0.16/LF | $9,552.80 | — | -60% | $6,732,215 | $1,063,968 (15.8%) left on table |
| 2 | Rk Hall, LLC | $0.17/LF | $10,149.85 | +$597.05 | -57.5% | $7,796,183 | +$1,063,968 |
| 3 | Zack Burkett Co. | $0.33/LF | $19,702.65 | +$10,150 | -17.5% | $7,966,171 | +$1,233,956 |
| 4 | Foutsco Paving Company, LLC | $0.16/LF | $9,552.80 | $0.000 | -60% | $8,000,580 | +$1,268,365 |
| 5 | Nobles Road Construction, Inc. | $0.17/LF | $10,149.85 | +$597.05 | -57.5% | $8,307,427 | +$1,575,212 |
| 6 | Ck Newberry, LLC | $0.25/LF | $14,926.25 | +$5,373 | -37.5% | $8,389,000 | +$1,656,785 |
| 7 | Reece Albert, Inc. | $0.37/LF | $22,090.85 | +$12,538 | -7.5% | $8,534,153 | +$1,801,938 |
| 8 | Texas Materials Group, Inc. | $0.30/LF | $17,911.50 | +$8,359 | -25% | $8,617,318 | +$1,885,103 |
| 9 | A. L. Helmcamp, Inc. | $0.22/LF | $13,135.10 | +$3,582 | -45% | $9,257,856 | +$2,525,641 |
- LOW BID · WINNER
- Unit price
- $0.16/LF
- Extension
- $9,552.80
- Proposal total
- $6,732,215
- Money left on the table
- $1,063,968 (15.8%)
- vs. engineer’s estimate
- -60%
2. Rk Hall, LLC
- Unit price
- $0.17/LF
- Extension
- $10,149.85
- Proposal total
- $7,796,183
- vs. low bid
- +$1,063,968
- vs. engineer’s estimate
- -57.5%
- Unit price
- $0.33/LF
- Extension
- $19,702.65
- Proposal total
- $7,966,171
- vs. low bid
- +$1,233,956
- vs. engineer’s estimate
- -17.5%
- Unit price
- $0.16/LF
- Extension
- $9,552.80
- Proposal total
- $8,000,580
- vs. low bid
- +$1,268,365
- vs. engineer’s estimate
- -60%
5. Nobles Road Construction, Inc.
- Unit price
- $0.17/LF
- Extension
- $10,149.85
- Proposal total
- $8,307,427
- vs. low bid
- +$1,575,212
- vs. engineer’s estimate
- -57.5%
- Unit price
- $0.25/LF
- Extension
- $14,926.25
- Proposal total
- $8,389,000
- vs. low bid
- +$1,656,785
- vs. engineer’s estimate
- -37.5%
- Unit price
- $0.37/LF
- Extension
- $22,090.85
- Proposal total
- $8,534,153
- vs. low bid
- +$1,801,938
- vs. engineer’s estimate
- -7.5%
- Unit price
- $0.30/LF
- Extension
- $17,911.50
- Proposal total
- $8,617,318
- vs. low bid
- +$1,885,103
- vs. engineer’s estimate
- -25%
- Unit price
- $0.22/LF
- Extension
- $13,135.10
- Proposal total
- $9,257,856
- vs. low bid
- +$2,525,641
- vs. engineer’s estimate
- -45%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 16,467 LF · Engineer’s estimate $0.550/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $0.40/LF | $6,586.80 | — | -27.3% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $0.35/LF | $5,763.45 | -$823.35 | -36.4% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $0.47/LF | $7,739.49 | +$1,153 | -14.5% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $0.35/LF | $5,763.45 | -$823.35 | -36.4% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $0.35/LF | $5,763.45 | -$823.35 | -36.4% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $0.36/LF | $5,928.12 | -$658.68 | -34.5% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $0.40/LF
- Extension
- $6,586.80
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -27.3%
2. Rpm Xconstruction, LLC
- Unit price
- $0.35/LF
- Extension
- $5,763.45
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -36.4%
- Unit price
- $0.47/LF
- Extension
- $7,739.49
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -14.5%
4. Webber, LLC
- Unit price
- $0.35/LF
- Extension
- $5,763.45
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -36.4%
5. Sema Construction, Inc.
- Unit price
- $0.35/LF
- Extension
- $5,763.45
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -36.4%
6. Zachry Construction Corporation
- Unit price
- $0.36/LF
- Extension
- $5,928.12
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -34.5%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0016-03-125 | Hays | Austin | 68,847 | 6 | Bobcat Services, Inc. | $0.370 | $0.250 |
| 2026-11-04 | 0157-04-058 | Haskell | Abilene | 59,705 | 9 | Lone Star Paving Company | $0.160 | $0.400 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 16,467 | 6 | Indus Road & Bridge, Inc. | $0.400 | $0.550 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 61,406 | 7 | Big Creek Construction, Ltd. | $0.230 | $0.400 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 24,917 | 9 | Highway 19 Construction LLC | $0.240 | $0.310 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 976 | 8 | Jay Mills Contracting, Incorporated | $1.15 | $1.00 |
| 2026-11-03 | 0045-09-113 | Lamar | Paris | 31,164 | 5 | Drake Companies LLC | $0.400 | $0.280 |
| 2026-10-07 | 0014-23-041 | Hill | Waco | 4,756 | 5 | Northeastern Pavers, LLC | $2.50 | $0.250 |
| 2026-10-07 | 0022-01-034 | Terrell | Odessa | 7,200 | 7 | Relmco, Inc. | $1.10 | $0.320 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 61,090 | 7 | Longview Bridge and Road, Ltd. | $0.220 | $0.370 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 29 | $0.160 | $0.220 | $0.400 | — |
| Amarillo | 48 | $0.270 | $0.390 | $0.350 | +29.31% |
| Atlanta | 28 | $0.220 | $0.250 | $0.280 | 0% |
| Austin | 212 | $0.190 | $0.210 | $0.270 | -16.67% |
| Beaumont | 58 | $0.530 | $0.300 | $0.500 | -20.37% |
| Brownwood | 17 | $0.190 | $0.170 | $0.300 | — |
| Bryan | 95 | $0.230 | $0.280 | $0.320 | -30% |
| Childress | 17 | $0.180 | $0.170 | $0.310 | — |
| Corpus Christi | 76 | $0.200 | $0.200 | $0.200 | -54.78% |
| Dallas | 197 | $0.400 | $0.380 | $0.300 | +40% |
| Fort Worth | 117 | $0.260 | $0.250 | $1.00 | +42.86% |
| Houston | 89 | $0.300 | $0.350 | $0.400 | -27.08% |
| Laredo | 11 | $0.430 | $0.420 | $0.250 | — |
| Lubbock | 56 | $0.250 | $0.300 | $0.300 | +30% |
| Lufkin | 75 | $0.330 | $0.300 | $0.400 | -57.73% |
| Odessa | 116 | $0.180 | $0.180 | $0.240 | -18.33% |
| Paris | 120 | $0.270 | $0.300 | $0.300 | -32% |
| Pharr | 65 | $0.500 | $0.500 | $0.500 | +12.15% |
| San Angelo | 8 | $1.40 | $1.25 | $0.400 | — |
| San Antonio | 106 | $0.210 | $0.210 | $0.270 | -17.81% |
| Tyler | 143 | $0.450 | $0.370 | $0.450 | -2.44% |
| Waco | 65 | $0.110 | $0.140 | $0.200 | -47.37% |
| Wichita Falls | 11 | $0.380 | $0.360 | $0.320 | — |
| Yoakum | 117 | $0.210 | $0.300 | $0.380 | +30% |
Related items
- 662-7112 · WK ZN PAV MRK SHT Term (TAB)TY W ($1.08/EA)
- 662-7114 · WK ZN PAV MRK SHT Term (TAB)TY Y-2 ($1.00/EA)
- 662-7008 · WK ZN PAV MRK NON-Remov (W)6"(SLD) ($0.250/LF)
- 662-7100 · WK ZN PAV MRK Remov (Y)6"(SLD) ($0.800/LF)
- 662-7068 · WK ZN PAV MRK Remov (W)6"(SLD) ($0.760/LF)
- 666-7024 · Refl PAV MRK TY I (W)8"(SLD)(100MIL) ($0.850/LF)
- 666-7423 · Refl PAV MRK TY I (Y)6"(SLD)(100MIL) ($0.450/LF)
- 666-7036 · Refl PAV MRK TY I (W)24"(SLD)(100MIL) ($7.00/LF)
Is your price for item 662-7038 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.