Relmco, Inc.: TxDOT Bid Results and Margins

Name as published by TxDOT: RELMCO, INC. · Data as published by TxDOT, lettings Nov 6, 2024 to Nov 19, 2026, retrieved Nov 24, 2026.

Proposals bid
46
Low bids (rank 1)
15
Win rate
32.61%
Low-bid value
$104M
Money left on table
$13M
Avg. bid vs. estimate
-5.61%

From Nov 6, 2024 to Nov 19, 2026, Relmco, Inc. submitted 46 bids on TxDOT proposals and was the apparent low bidder on 15 of them (32.61%), with low bids totalling $103,980,475. In 15 low bids that faced at least one other bidder, the gap between this bidder and the next-lowest bid totalled $12,969,019 (12.47% of those bids); the median gap was 10.03%. On average its bids came in 5.61% below TxDOT's engineer's estimate. Its most frequent district was San Antonio (11 bids).

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

By year

YearBidsLow bidsWin rateLow-bid value
202422100.0%$13,698,017
202519631.6%$34,736,304
202625728.0%$55,546,154

Head-to-head rivals

BidderProposals togetherRanked ahead
Scr Civil Construction, LLC1514 of 15
Ragle Construction, Inc.1411 of 14
Mpb, Inc.133 of 13
Blacksmith Ventures LLC116 of 11
Bk Field Operations LLC103 of 10
Built Right Construction of Oklahoma, LLC109 of 10
Garret Shields Infrastructure95 of 9
Icos Management, LLC96 of 9

Districts and work types

DistrictBids
San Antonio11
Odessa8
San Angelo8
Corpus Christi5
Laredo5
Work type of low bidsLow bids
Bridge Replacement4
Bridge Maintenance3
Safety Improvement Projects2
Bridge Preventative Maintenance - Sealed1
Bridge Widening or Rehabilitation1
Culvert & Storm Drainage Work1

Closest second-place finishes

Let dateProposalCountyLow bidderLow bidThis bidvs. low bid
2026-11-030022-03-032TerrellThe Truesdell Corporation$2,888,888$2,978,677+3.1%
2026-01-071197-01-023HaysProfessional Traffic Control LLC$999,085$1,048,948+5%
2025-09-040022-06-054Val VerdeTaylor Bridge LLC$138,550$147,170+6.2%
2025-05-010924-35-021BrewsterDigg Commercial, LLC$894,200$966,053+8%
2026-06-020915-00-283BexarTaylor Bridge LLC$4,555,821$4,955,889+8.8%

Recent bids

Let dateProposalCountyWork typeRankBid totalvs. low bidvs. estimate
2026-11-196510-75-001EctorBridge Preventative Maintenance - Sealed1 of 9$669,750—-65.5%
2026-11-176509-99-001BexarMaterial Maintenance Project1 of 2$207,100—-19.2%
2026-11-040074-06-256NuecesBridge Maintenance1 of 4$849,655—-46.8%
2026-11-030022-03-032TerrellBridge Maintenance2 of 7$2,978,677+3.1%-8.3%
2026-10-070022-01-034TerrellBridge Replacement1 of 7$6,768,348—-7.1%
2026-10-066500-59-001La SalleBridge Preventative Maintenance3 of 8$1,545,379+24.1%+16.4%
2026-09-296508-59-001KimbleRoutine Maintenance Project - Sealed2 of 5$250,575+8.9%-41.5%
2026-09-106501-04-001KimbleBridge Preventative Maintenance8 of 10$785,109+74.5%+47.1%
2026-09-036501-05-001Tom GreenBridge Preventative Maintenance4 of 11$1,478,786+6.9%+11.2%
2026-08-060140-13-023CrockettSafety Rest Area2 of 6$16,617,786+20.9%-16.9%
2026-08-050037-02-060ZavalaBridge Replacement1 of 10$13,786,607—-23%
2026-07-020915-12-751BexarBridge Widening or Rehabilitation3 of 7$3,848,184+16.5%-16.4%

Report an error. Wrong company merged, a name change, or a figure that does not match TxDOT's file? Email bidtabulation@apps.adeptaoperations.com. We respond within five business days. See how corrections work.