Excav (Channel) (Item 110-7002): TxDOT Unit Price History

1,465 bids · 207 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure CY

TxDOT 110-7002 · EXCAV (CHANNEL) · Unit: CY

Low bid
$8.60/CY
Quantity-weighted median of winning unit prices
Weighted median
$18.00/CY
Quantity-weighted median of every bid
Engineer’s estimate
$17.00/CY
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-20.14%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$50.00$100.00$150.00$200.001101001K10K100KQuantity (CY), log scaleUnit price ($/CY)
Winning (low) bid Other bid Fitted price curve (ln price = 5.06 − 0.271·ln qty, R² 0.37)320 plotted bids, 5 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 110-7002 (Excav (Channel)) is measured in CY. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 1,465 bids for it on 207 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 752 bids was $18.00 per CY, and the winning low bidders priced it at a weighted median of $8.60 per CY.

TxDOT's engineer's estimate for the same lines had a weighted median of $17.00 per CY, so winning bids came in 49.4% below the estimate.

By calendar year, the median bid moved from $35.00 in 2025 (721 bids) to $27.90 in 2026 (693 bids), down 20.3%. The middle half of 2026 bids fell between $18.00 and $50.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 20.14%.

Quantity matters for this item. Lines of 2 to 243 CY had a weighted median of $50.00, while lines above 1,005 CY had $18.00, a 64% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 202 lines where both a winning and a second-place bid were published, the median winning unit price was $25.00 against $30.00 from the second-lowest bidder, a median gap of 18.33% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 21 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($12.00) and Wichita Falls the highest ($70.00). The busiest district for this item was Yoakum.

The most recent letting with this item was on Nov 12, 2026 in Denton County, where Road Doctors LLC was the low bidder at $60.00 per CY for 89 CY against an estimate of $40.00.

15 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 110-7001 Excav (Roadway) (weighted median $10.00 per CY); 104-7006 Remov Conc (Riprap) (weighted median $10.00 per SY); 104-7011 Remov Conc (Driveways) (weighted median $18.21 per SY); 104-7013 Remov Conc (Sidewalk, Ramp OR SUP) (weighted median $15.00 per SY).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
2024517$26.84$25.00$29.00$20.00$50.50
2025721107$26.70$21.00$35.00$24.00$60.00
202669393$20.28$17.70$27.90$18.00$50.00

Quantity bands

BandQuantity (CY)BidsWeighted avgWeighted median25th–75th pct
Small2–243494$69.97$50.00$35.00–$100.00
Medium250–987487$33.48$27.35$20.00–$41.50
Large1,005–67,198.9484$20.02$18.00$15.22–$30.00

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$25.00
Median second-low unit price
$30.00
Median engineer’s estimate
$30.00
Median gap, second vs. low
+18.33%

202 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 6497-55-001 · let Nov 12, 2026 · Denton County, Dallas District

Line quantity 89 CY · Engineer’s estimate $40.00/CY

  • 1. Road Doctors LLC

    LOW BID · WINNER
    Unit price
    $60.00/CY
    Extension
    $5,340.00
    Proposal total
    $493,320
    Money left on the table
    $25,748 (5.22%)
    vs. engineer’s estimate
    +50%
  • Unit price
    $105.00/CY
    Extension
    $9,345.00
    Proposal total
    $519,068
    vs. low bid
    +$25,748
    vs. engineer’s estimate
    +162.5%
  • Unit price
    $25.00/CY
    Extension
    $2,225.00
    Proposal total
    $567,220
    vs. low bid
    +$73,900
    vs. engineer’s estimate
    -37.5%
  • Unit price
    $100.00/CY
    Extension
    $8,900.00
    Proposal total
    $598,798
    vs. low bid
    +$105,478
    vs. engineer’s estimate
    +150%
  • Unit price
    $120.00/CY
    Extension
    $10,680.00
    Proposal total
    $654,688
    vs. low bid
    +$161,368
    vs. engineer’s estimate
    +200%
  • 6. Jr West Texas Concrete LLC

    Unit price
    $49.00/CY
    Extension
    $4,361.00
    Proposal total
    $746,209
    vs. low bid
    +$252,889
    vs. engineer’s estimate
    +22.5%

Proposal 0922-33-234 · let Nov 4, 2026 · Webb County, Laredo District

Line quantity 1,540 CY · Engineer’s estimate $20.00/CY

  • 1. Stx Civil

    LOW BID · WINNER
    Unit price
    $18.96/CY
    Extension
    $29,198.40
    Proposal total
    $2,866,785
    Money left on the table
    $83,215 (2.9%)
    vs. engineer’s estimate
    -5.2%
  • Unit price
    $25.00/CY
    Extension
    $38,500.00
    Proposal total
    $2,950,000
    vs. low bid
    +$83,215
    vs. engineer’s estimate
    +25%
  • 3. Acee Construction LLC.

    Unit price
    $20.00/CY
    Extension
    $30,800.00
    Proposal total
    $3,033,273
    vs. low bid
    +$166,488
    vs. engineer’s estimate
    0%
  • Unit price
    $25.67/CY
    Extension
    $39,531.80
    Proposal total
    $3,261,472
    vs. low bid
    +$394,687
    vs. engineer’s estimate
    +28.4%
  • Unit price
    $25.00/CY
    Extension
    $38,500.00
    Proposal total
    $3,270,969
    vs. low bid
    +$404,184
    vs. engineer’s estimate
    +25%
  • Unit price
    $15.00/CY
    Extension
    $23,100.00
    Proposal total
    $3,466,015
    vs. low bid
    +$599,230
    vs. engineer’s estimate
    -25%
  • Unit price
    $10.00/CY
    Extension
    $15,400.00
    Proposal total
    $5,083,300
    vs. low bid
    +$2,216,516
    vs. engineer’s estimate
    -50%

Proposal 0923-06-068 · let Nov 4, 2026 · Brown County, Brownwood District

Line quantity 60 CY · Engineer’s estimate $40.00/CY

  • 1. Jay Mills Contracting, Incorporated

    LOW BID · WINNER
    Unit price
    $60.00/CY
    Extension
    $3,600.00
    Proposal total
    $1,561,729
    Money left on the table
    $122,095 (7.82%)
    vs. engineer’s estimate
    +50%
  • Unit price
    $105.00/CY
    Extension
    $6,300.00
    Proposal total
    $1,683,823
    vs. low bid
    +$122,095
    vs. engineer’s estimate
    +162.5%
  • 3. Prater Dirt Work LLC

    Unit price
    $50.00/CY
    Extension
    $3,000.00
    Proposal total
    $1,759,351
    vs. low bid
    +$197,622
    vs. engineer’s estimate
    +25%
  • Unit price
    $65.00/CY
    Extension
    $3,900.00
    Proposal total
    $1,774,687
    vs. low bid
    +$212,959
    vs. engineer’s estimate
    +62.5%
  • Unit price
    $63.00/CY
    Extension
    $3,780.00
    Proposal total
    $2,220,638
    vs. low bid
    +$658,910
    vs. engineer’s estimate
    +57.5%
  • Unit price
    $200.00/CY
    Extension
    $12,000.00
    Proposal total
    $2,399,186
    vs. low bid
    +$837,457
    vs. engineer’s estimate
    +400%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-126497-55-001DentonDallas896Road Doctors LLC$60.00$40.00
2026-11-040922-33-234WebbLaredo1,5407Stx Civil$18.96$20.00
2026-11-040923-06-068BrownBrownwood606Jay Mills Contracting, Incorporated$60.00$40.00
2026-11-041017-03-040HuntParis469Highway 19 Construction LLC$25.00$23.00
2026-11-030917-30-068BurlesonBryan9115C & W Southern LLC$20.00$30.00
2026-10-156506-36-001McLennanWaco1,2352Krimatt Services LLC$25.00$10.63
2026-10-070510-06-024FanninParis986A. K. Gillis & Sons, LLC$75.00$25.00
2026-10-070922-20-030La SalleLaredo396Presidio Contracting, LLC$76.00$50.00
2026-10-076493-26-001WiseFort Worth7,308.217Shalom Services Corporation$8.00$26.00
2026-10-076503-72-001LampasasBrownwood2439Taylor Bridge LLC$25.00$85.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene28$32.00$25.00$27.00—
Amarillo16$25.00$20.00$14.00—
Atlanta39$12.00$40.00$50.00-11.67%
Austin10$18.88$40.00$23.00—
Beaumont25$12.00$23.00$25.00—
Brownwood52$25.00$65.00$85.00+102.97%
Bryan56$18.00$20.00$29.00-19.4%
Childress51$15.00$22.25$30.00-16.3%
Corpus Christi36$8.00$24.21$23.00-5.04%
Dallas67$8.00$23.00$18.00+12.9%
El Paso8$30.00$37.68$20.00—
Fort Worth57$8.00$25.00$26.00-33.33%
Houston97$8.60$20.00$15.00-50%
Laredo18$18.96$25.00$20.00—
Lubbock5$16.60$26.00$15.00—
Lufkin6$12.00$25.39$70.00—
Paris185$10.00$20.00$20.00-50%
Pharr40$5.00$12.00$17.00-69.08%
San Angelo24$8.53$22.00$0.360—
San Antonio131$25.00$22.60$50.00-30%
Tyler54$17.30$35.00$20.00+118.75%
Waco120$12.00$25.00$25.000%
Wichita Falls75$50.00$70.00$12.00+97.67%
Yoakum265$18.00$18.81$20.00-20%

Related items

Is your price for item 110-7002 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.