Remov Conc (Sidewalk, Ramp OR SUP) (Item 104-7013): TxDOT Unit Price History
1,292 bids · 223 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure SY
TxDOT 104-7013 · REMOV CONC (SIDEWALK, RAMP OR SUP) · Unit: SY
- Low bid
- $10.00/SY
- Quantity-weighted median of winning unit prices
- Weighted median
- $15.00/SY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $18.00/SY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -16.67%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 104-7013 (Remov Conc (Sidewalk, Ramp OR SUP)) is measured in SY. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,292 bids for it on 223 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 723 bids was $15.00 per SY, and the winning low bidders priced it at a weighted median of $10.00 per SY.
TxDOT's engineer's estimate for the same lines had a weighted median of $18.00 per SY, so winning bids came in 44.4% below the estimate.
By calendar year, the median bid moved from $30.00 in 2025 (548 bids) to $25.50 in 2026 (693 bids), down 15.0%. The middle half of 2026 bids fell between $15.25 and $50.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 16.67%.
Quantity matters for this item. Lines of 6 to 93 SY had a weighted median of $44.30, while lines above 444 SY had $16.50, a 63% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 220 lines where both a winning and a second-place bid were published, the median winning unit price was $25.00 against $26.05 from the second-lowest bidder, a median gap of 12.25% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Atlanta had the lowest weighted median ($12.00) and Bryan the highest ($53.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $10.00 per SY for 304 SY against an estimate of $27.50.
Related items: 104-7006 Remov Conc (Riprap) (weighted median $10.00 per SY); 104-7011 Remov Conc (Driveways) (weighted median $18.21 per SY); 104-7016 Remov Conc (Curb) (weighted median $4.57 per LF); 100-7002 Preparing ROW (weighted median $1,500.00 per STA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 51 | 9 | $19.80 | $20.00 | $32.00 | $21.82 | $50.00 |
| 2025 | 548 | 100 | $23.28 | $20.00 | $30.00 | $20.00 | $50.00 |
| 2026 | 693 | 114 | $19.50 | $15.00 | $25.50 | $15.25 | $50.00 |
Quantity bands
| Band | Quantity (SY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 6–93 | 434 | $64.90 | $44.30 | $25.31–$84.75 |
| Medium | 95–442 | 428 | $34.30 | $25.00 | $19.57–$45.08 |
| Large | 444–27,346.9 | 430 | $18.95 | $16.50 | $13.45–$29.81 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $25.00
- Median second-low unit price
- $26.05
- Median engineer’s estimate
- $28.00
- Median gap, second vs. low
- +12.25%
220 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 304 SY · Engineer’s estimate $27.50/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $10.00/SY | $3,040.00 | — | -63.6% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $12.00/SY | $3,648.00 | +$608.00 | -56.4% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $17.50/SY | $5,320.00 | +$2,280 | -36.4% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $25.50/SY | $7,752.00 | +$4,712 | -7.3% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $10.00/SY
- Extension
- $3,040.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -63.6%
- Unit price
- $12.00/SY
- Extension
- $3,648.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- -56.4%
3. Tiseo Paving Company, LLC
- Unit price
- $17.50/SY
- Extension
- $5,320.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -36.4%
4. Harper Brothers Construction LLC
- Unit price
- $25.50/SY
- Extension
- $7,752.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -7.3%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 825 SY · Engineer’s estimate $12.00/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $10.00/SY | $8,250.00 | — | -16.7% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $14.50/SY | $11,962.50 | +$3,713 | +20.8% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $11.00/SY | $9,075.00 | +$825.00 | -8.3% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $16.48/SY | $13,596.00 | +$5,346 | +37.3% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $13.15/SY | $10,848.75 | +$2,599 | +9.6% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $9.01/SY | $7,433.25 | -$816.75 | -24.9% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $10.00/SY
- Extension
- $8,250.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -16.7%
2. Rpm Xconstruction, LLC
- Unit price
- $14.50/SY
- Extension
- $11,962.50
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +20.8%
- Unit price
- $11.00/SY
- Extension
- $9,075.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -8.3%
4. Webber, LLC
- Unit price
- $16.48/SY
- Extension
- $13,596.00
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +37.3%
5. Sema Construction, Inc.
- Unit price
- $13.15/SY
- Extension
- $10,848.75
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +9.6%
6. Zachry Construction Corporation
- Unit price
- $9.01/SY
- Extension
- $7,433.25
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -24.9%
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 26 SY · Engineer’s estimate $40.00/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $33.50/SY | $871.00 | — | -16.3% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $13.10/SY | $340.60 | -$530.40 | -67.3% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $45.00/SY | $1,170.00 | +$299.00 | +12.5% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $88.00/SY | $2,288.00 | +$1,417 | +120% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $60.81/SY | $1,581.06 | +$710.06 | +52% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $16.00/SY | $416.00 | -$455.00 | -60% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $41.40/SY | $1,076.40 | +$205.40 | +3.5% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $28.00/SY | $728.00 | -$143.00 | -30% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $75.00/SY | $1,950.00 | +$1,079 | +87.5% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $33.50/SY
- Extension
- $871.00
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- -16.3%
2. Stx Civil
- Unit price
- $13.10/SY
- Extension
- $340.60
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- -67.3%
3. Rucoba & Maya Construction, LLC
- Unit price
- $45.00/SY
- Extension
- $1,170.00
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- +12.5%
4. Myers Concrete Construction, LP
- Unit price
- $88.00/SY
- Extension
- $2,288.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +120%
- Unit price
- $60.81/SY
- Extension
- $1,581.06
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- +52%
- Unit price
- $16.00/SY
- Extension
- $416.00
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- -60%
7. Ratliff Hardscape, Ltd.
- Unit price
- $41.40/SY
- Extension
- $1,076.40
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- +3.5%
- Unit price
- $28.00/SY
- Extension
- $728.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- -30%
- Unit price
- $75.00/SY
- Extension
- $1,950.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +87.5%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 304 | 4 | Mario Sinacola & Sons Excavating, Inc. | $10.00 | $27.50 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 825 | 6 | Indus Road & Bridge, Inc. | $10.00 | $12.00 |
| 2026-11-04 | 0285-03-066 | Hays | Austin | 26 | 9 | Lone Star Sitework, LLC | $33.50 | $40.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 27,346.9 | 6 | Austin Bridge & Road Services, LP | $9.00 | $12.67 |
| 2026-11-03 | 0045-09-113 | Lamar | Paris | 13 | 5 | Drake Companies LLC | $95.00 | $50.00 |
| 2026-10-06 | 0009-11-248 | Dallas | Dallas | 311 | 7 | Ragle Construction, Inc. | $11.40 | $25.00 |
| 2026-10-06 | 0590-05-057 | Milam | Bryan | 24 | 10 | Yoko Excavating, LLC | $50.07 | $26.00 |
| 2026-10-06 | 2502-01-024 | Bell | Waco | 223 | 6 | Big Creek Construction, Ltd. | $18.00 | $22.00 |
| 2026-09-03 | 0051-09-127 | Galveston | Houston | 128 | 7 | Castillo Aranda LLC | $20.00 | $20.00 |
| 2026-09-03 | 0143-10-058 | Victoria | Yoakum | 1,711 | 7 | 3lw Civil LLC | $23.33 | $35.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 15 | $21.00 | $16.81 | $25.00 | — |
| Amarillo | 41 | $17.00 | $20.00 | $25.00 | 0% |
| Atlanta | 37 | $12.00 | $12.00 | $12.00 | -4.2% |
| Austin | 71 | $9.00 | $14.00 | $12.67 | -36.83% |
| Beaumont | 15 | $12.00 | $16.50 | $28.00 | — |
| Brownwood | 17 | $30.00 | $30.00 | $22.00 | — |
| Bryan | 54 | $15.00 | $53.00 | $8.00 | +68.52% |
| Childress | 6 | $20.00 | $20.00 | $28.00 | — |
| Corpus Christi | 34 | $9.63 | $15.84 | $9.50 | -0.5% |
| Dallas | 234 | $20.00 | $22.00 | $30.00 | -46.81% |
| El Paso | 26 | $20.66 | $24.75 | $15.57 | -5.68% |
| Fort Worth | 61 | $21.00 | $31.50 | $30.00 | -8.8% |
| Houston | 126 | $21.00 | $17.76 | $318.79 | -56.2% |
| Laredo | 19 | $12.49 | $12.49 | $30.00 | — |
| Lubbock | 16 | $28.11 | $28.11 | $50.00 | — |
| Odessa | 31 | $22.00 | $17.67 | $30.00 | — |
| Paris | 57 | $25.00 | $30.00 | $23.88 | +29.63% |
| Pharr | 83 | $10.00 | $15.00 | $20.00 | -15.21% |
| San Angelo | 14 | $25.00 | $25.00 | $20.00 | — |
| San Antonio | 136 | $9.00 | $12.00 | $18.00 | -18.33% |
| Tyler | 25 | $18.00 | $18.00 | $21.00 | -48.33% |
| Waco | 66 | $18.00 | $28.00 | $25.00 | +8.86% |
| Wichita Falls | 16 | $8.00 | $16.04 | $30.00 | — |
| Yoakum | 92 | $23.33 | $25.00 | $35.00 | +40% |
Related items
- 104-7006 · Remov Conc (Riprap) ($10.00/SY)
- 104-7011 · Remov Conc (Driveways) ($18.21/SY)
- 104-7016 · Remov Conc (Curb) ($4.57/LF)
- 100-7002 · Preparing ROW ($1,500.00/STA)
- 110-7001 · Excav (Roadway) ($10.00/CY)
- 110-7002 · Excav (Channel) ($18.00/CY)
- 132-7003 · Embank (FNL)(OC)(TY B) ($15.00/CY)
- 132-7006 · Embank (FNL)(DC)(TY C) ($12.00/CY)
Is your price for item 104-7013 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.