Preparing ROW (Item 100-7002): TxDOT Unit Price History
3,913 bids · 591 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure STA
TxDOT 100-7002 · PREPARING ROW · Unit: STA
- Low bid
- $995.00/STA
- Quantity-weighted median of winning unit prices
- Weighted median
- $1,500.00/STA
- Quantity-weighted median of every bid
- Engineer’s estimate
- $1,500.00/STA
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -25.04%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 100-7002 (Preparing ROW) is measured in STA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 3,913 bids for it on 591 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 2,036 bids was $1,500.00 per STA, and the winning low bidders priced it at a weighted median of $995.00 per STA.
TxDOT's engineer's estimate for the same lines had a weighted median of $1,500.00 per STA, so winning bids came in 33.7% below the estimate.
By calendar year, the median bid moved from $3,047.40 in 2025 (1,884 bids) to $2,500.00 in 2026 (1,885 bids), down 18.0%. The middle half of 2026 bids fell between $1,000.00 and $6,500.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 25.04%.
Quantity matters for this item. Lines of 1 to 13 STA had a weighted median of $4,000.00, while lines above 86 STA had $1,350.00, a 66% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 586 lines where both a winning and a second-place bid were published, the median winning unit price was $1,782.23 against $2,047.50 from the second-lowest bidder, a median gap of 7.14% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 25 TxDOT districts with at least ten bids, Amarillo had the lowest weighted median ($19.13) and Wichita Falls the highest ($12,000.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $10,865.00 per STA for 138 STA against an estimate of $13,632.00.
12 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 104-7006 Remov Conc (Riprap) (weighted median $10.00 per SY); 104-7011 Remov Conc (Driveways) (weighted median $18.21 per SY); 104-7013 Remov Conc (Sidewalk, Ramp OR SUP) (weighted median $15.00 per SY); 104-7016 Remov Conc (Curb) (weighted median $4.57 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 144 | 22 | $9,491.15 | $1,945.00 | $5,250.00 | $2,000.00 | $11,557.78 |
| 2025 | 1,884 | 297 | $6,923.08 | $1,500.00 | $3,047.40 | $1,197.50 | $7,625.00 |
| 2026 | 1,885 | 274 | $9,300.17 | $1,600.00 | $2,500.00 | $1,000.00 | $6,500.00 |
Quantity bands
| Band | Quantity (STA) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–13 | 1,315 | $16,333.17 | $4,000.00 | $2,100.00–$10,000.00 |
| Medium | 13.1–84.98 | 1,302 | $12,599.92 | $2,500.00 | $1,100.00–$7,387.50 |
| Large | 86–1,567 | 1,296 | $7,234.37 | $1,350.00 | $577.38–$4,489.45 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $1,782.23
- Median second-low unit price
- $2,047.50
- Median engineer’s estimate
- $2,900.00
- Median gap, second vs. low
- +7.14%
586 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 138 STA · Engineer’s estimate $13,632/STA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $10,865.00/STA | $1,499,370.00 | — | -20.3% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $4,000.00/STA | $552,000.00 | -$947,370 | -70.7% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $8,190.00/STA | $1,130,220.00 | -$369,150 | -39.9% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $6,000.00/STA | $828,000.00 | -$671,370 | -56% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $10,865.00/STA
- Extension
- $1,499,370.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -20.3%
- Unit price
- $4,000.00/STA
- Extension
- $552,000.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- -70.7%
3. Tiseo Paving Company, LLC
- Unit price
- $8,190.00/STA
- Extension
- $1,130,220.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -39.9%
4. Harper Brothers Construction LLC
- Unit price
- $6,000.00/STA
- Extension
- $828,000.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -56%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 130.066 STA · Engineer’s estimate $48,650/STA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $36,031.36/STA | $4,686,454.87 | — | -25.9% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $14,906.00/STA | $1,938,763.80 | -$2,747,691 | -69.4% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $42,800.00/STA | $5,566,824.80 | +$880,370 | -12% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $56,900.00/STA | $7,400,755.40 | +$2,714,301 | +17% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $115,121.70/STA | $14,973,419.03 | +$10,286,964 | +136.6% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $115,326.07/STA | $15,000,000.62 | +$10,313,546 | +137.1% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $36,031.36/STA
- Extension
- $4,686,454.87
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -25.9%
2. Rpm Xconstruction, LLC
- Unit price
- $14,906.00/STA
- Extension
- $1,938,763.80
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -69.4%
- Unit price
- $42,800.00/STA
- Extension
- $5,566,824.80
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -12%
4. Webber, LLC
- Unit price
- $56,900.00/STA
- Extension
- $7,400,755.40
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +17%
5. Sema Construction, Inc.
- Unit price
- $115,121.70/STA
- Extension
- $14,973,419.03
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +136.6%
6. Zachry Construction Corporation
- Unit price
- $115,326.07/STA
- Extension
- $15,000,000.62
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +137.1%
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 150.5 STA · Engineer’s estimate $1,500/STA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $4,376.74/STA | $658,699.37 | — | +191.8% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $2,500.00/STA | $376,250.00 | -$282,449 | +66.7% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $595.72/STA | $89,655.86 | -$569,044 | -60.3% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $2,000.00/STA | $301,000.00 | -$357,699 | +33.3% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $25,225.00/STA | $3,796,362.50 | +$3,137,663 | +1,581.7% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $5,500.00/STA | $827,750.00 | +$169,051 | +266.7% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $2,000.00/STA | $301,000.00 | -$357,699 | +33.3% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $2,000.00/STA | $301,000.00 | -$357,699 | +33.3% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $26,578.07/STA | $3,999,999.54 | +$3,341,300 | +1,671.9% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $3,000.00/STA | $451,500.00 | -$207,199 | +100% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $24,750.00/STA | $3,724,875.00 | +$3,066,176 | +1,550% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $3,500.00/STA | $526,750.00 | -$131,949 | +133.3% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $4,376.74/STA
- Extension
- $658,699.37
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- +191.8%
- Unit price
- $2,500.00/STA
- Extension
- $376,250.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- +66.7%
- Unit price
- $595.72/STA
- Extension
- $89,655.86
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- -60.3%
- Unit price
- $2,000.00/STA
- Extension
- $301,000.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- +33.3%
- Unit price
- $25,225.00/STA
- Extension
- $3,796,362.50
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- +1,581.7%
- Unit price
- $5,500.00/STA
- Extension
- $827,750.00
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- +266.7%
- Unit price
- $2,000.00/STA
- Extension
- $301,000.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- +33.3%
- Unit price
- $2,000.00/STA
- Extension
- $301,000.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- +33.3%
9. Zachry Construction Corporation
- Unit price
- $26,578.07/STA
- Extension
- $3,999,999.54
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- +1,671.9%
10. Brizo Construction, LLC
- Unit price
- $3,000.00/STA
- Extension
- $451,500.00
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- +100%
- Unit price
- $24,750.00/STA
- Extension
- $3,724,875.00
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- +1,550%
- Unit price
- $3,500.00/STA
- Extension
- $526,750.00
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- +133.3%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 138 | 4 | Mario Sinacola & Sons Excavating, Inc. | $10,865.00 | $13,632.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 130.07 | 6 | Indus Road & Bridge, Inc. | $36,031.36 | $48,650.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 150.5 | 12 | Fluor Enterprises, Inc. | $4,376.74 | $1,500.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 275 | 7 | Big Creek Construction, Ltd. | $750.00 | $625.00 |
| 2026-11-04 | 0353-01-031 | Wise | Fort Worth | 13 | 7 | Xit Paving and Construction Inc. | $2,100.00 | $5,067.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 11 | 7 | Stx Civil | $1,994.88 | $2,500.00 |
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 10 | 2 | Texas Materials Group, Inc. | $4,235.00 | $2,000.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 281 | 9 | Highway 19 Construction LLC | $543.00 | $900.00 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 28 | 5 | J E Construction Services, LLC | $1,160.00 | $3,500.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 206.05 | 6 | Austin Bridge & Road Services, LP | $175,000.00 | $105,638.78 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 72 | $1,400.00 | $2,500.00 | $5,000.00 | -68.35% |
| Amarillo | 20 | $11.65 | $19.13 | $100.00 | — |
| Atlanta | 117 | $1,000.00 | $1,950.00 | $1,500.00 | -11.38% |
| Austin | 292 | $700.00 | $800.00 | $1,500.00 | -54% |
| Beaumont | 88 | $750.00 | $750.00 | $1,000.00 | -27.67% |
| Brownwood | 34 | $950.00 | $950.00 | $800.00 | — |
| Bryan | 224 | $1,144.00 | $1,260.00 | $1,500.00 | +10% |
| Childress | 37 | $2,750.00 | $2,900.00 | $4,000.00 | — |
| Corpus Christi | 131 | $166.79 | $272.15 | $260.00 | -84.45% |
| Dallas | 522 | $500.00 | $1,100.00 | $700.00 | -8.75% |
| El Paso | 21 | $986.97 | $5,000.00 | $7,500.00 | — |
| Fort Worth | 334 | $300.00 | $800.00 | $1,500.00 | 0% |
| Houston | 196 | $6,550.00 | $12,000.00 | $4,500.00 | -16.53% |
| Laredo | 89 | $1,451.88 | $2,000.00 | $3,500.00 | +76.11% |
| Lubbock | 18 | $4,000.00 | $12,000.00 | $9,000.00 | — |
| Lufkin | 129 | $1,600.00 | $2,700.00 | $3,000.00 | -23.08% |
| Odessa | 27 | $1,500.00 | $10,000.00 | $10,000.00 | +3.6% |
| Paris | 317 | $633.17 | $700.00 | $950.00 | 0% |
| Pharr | 154 | $2,000.00 | $2,500.00 | $2,500.00 | -37.46% |
| San Angelo | 34 | $10,500.00 | $5,000.00 | $6,000.00 | +45.38% |
| San Antonio | 218 | $800.00 | $2,000.00 | $4,500.00 | +4.23% |
| Tyler | 177 | $3,500.00 | $3,400.00 | $3,250.00 | +8.76% |
| Waco | 189 | $320.00 | $500.00 | $950.00 | -55% |
| Wichita Falls | 61 | $12,000.00 | $12,000.00 | $5,000.00 | +5% |
| Yoakum | 412 | $2,181.15 | $3,400.00 | $2,500.00 | -8.93% |
Related items
- 104-7006 · Remov Conc (Riprap) ($10.00/SY)
- 104-7011 · Remov Conc (Driveways) ($18.21/SY)
- 104-7013 · Remov Conc (Sidewalk, Ramp OR SUP) ($15.00/SY)
- 104-7016 · Remov Conc (Curb) ($4.57/LF)
- 110-7001 · Excav (Roadway) ($10.00/CY)
- 110-7002 · Excav (Channel) ($18.00/CY)
- 132-7003 · Embank (FNL)(OC)(TY B) ($15.00/CY)
- 132-7006 · Embank (FNL)(DC)(TY C) ($12.00/CY)
Is your price for item 100-7002 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.