Embank (FNL)(OC)(TY B) (Item 132-7003): TxDOT Unit Price History
1,207 bids · 178 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure CY
TxDOT 132-7003 · EMBANK (FNL)(OC)(TY B) · Unit: CY
- Low bid
- $9.75/CY
- Quantity-weighted median of winning unit prices
- Weighted median
- $15.00/CY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $25.00/CY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- 0%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 132-7003 (Embank (FNL)(OC)(TY B)) is measured in CY. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 1,207 bids for it on 178 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 548 bids was $15.00 per CY, and the winning low bidders priced it at a weighted median of $9.75 per CY.
TxDOT's engineer's estimate for the same lines had a weighted median of $25.00 per CY, so winning bids came in 61.0% below the estimate.
By calendar year, the median bid moved from $40.00 in 2025 (644 bids) to $40.00 in 2026 (524 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $21.70 and $80.00.
Comparing the last 12 months with the 12 months before, the median unit price did not change.
Quantity matters for this item. Lines of 1 to 222 CY had a weighted median of $55.00, while lines above 1,587 CY had $13.21, a 76% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 177 lines where both a winning and a second-place bid were published, the median winning unit price was $33.75 against $40.00 from the second-lowest bidder, a median gap of 4.62% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 13 TxDOT districts with at least ten bids, San Antonio had the lowest weighted median ($10.00) and Amarillo the highest ($100.00). The busiest district for this item was Austin.
The most recent letting with this item was on Nov 12, 2026 in Potter County, where Ti-Zack Concrete, LLC was the low bidder at $64.63 per CY for 81 CY against an estimate of $50.00.
Related items: 132-7006 Embank (FNL)(DC)(TY C) (weighted median $12.00 per CY); 132-7005 Embank (FNL)(OC)(TY C) (weighted median $15.00 per CY); 110-7001 Excav (Roadway) (weighted median $10.00 per CY); 110-7002 Excav (Channel) (weighted median $18.00 per CY).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 39 | 6 | $38.21 | $40.00 | $44.00 | $30.75 | $57.50 |
| 2025 | 644 | 96 | $20.06 | $13.21 | $40.00 | $25.00 | $65.00 |
| 2026 | 524 | 76 | $19.41 | $15.00 | $40.00 | $21.70 | $80.00 |
Quantity bands
| Band | Quantity (CY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–222 | 407 | $80.41 | $55.00 | $45.47–$150.00 |
| Medium | 236–1,568 | 402 | $39.94 | $31.47 | $25.00–$55.65 |
| Large | 1,587–213,815 | 398 | $19.05 | $13.21 | $15.24–$39.18 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $33.75
- Median second-low unit price
- $40.00
- Median engineer’s estimate
- $34.42
- Median gap, second vs. low
- +4.62%
177 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6504-61-001 · let Nov 12, 2026 · Potter County, Amarillo District
Line quantity 81 CY · Engineer’s estimate $50.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLCLOW BID | $64.63/CY | $5,234.63 | — | +29.3% | $734,629 | $59,414 (8.09%) left on table |
| 2 | Cross Plus Construction, LLC | $50.00/CY | $4,050.00 | -$1,185 | 0% | $794,043 | +$59,414 |
| 3 | Structural Integrity Group LLC | $82.00/CY | $6,642.00 | +$1,407 | +64% | $852,064 | +$117,434 |
| 4 | Pathfield Investments LLC | $120.00/CY | $9,720.00 | +$4,485 | +140% | $863,606 | +$128,977 |
| 5 | Scr Civil Construction, LLC | $100.00/CY | $8,100.00 | +$2,865 | +100% | $916,535 | +$181,906 |
| 6 | Icos Management, LLC | $63.00/CY | $5,103.00 | -$131.63 | +26% | $974,652 | +$240,023 |
| 7 | Road Doctors LLC | $250.00/CY | $20,250.00 | +$15,015 | +400% | $981,238 | +$246,609 |
- LOW BID · WINNER
- Unit price
- $64.63/CY
- Extension
- $5,234.63
- Proposal total
- $734,629
- Money left on the table
- $59,414 (8.09%)
- vs. engineer’s estimate
- +29.3%
- Unit price
- $50.00/CY
- Extension
- $4,050.00
- Proposal total
- $794,043
- vs. low bid
- +$59,414
- vs. engineer’s estimate
- 0%
- Unit price
- $82.00/CY
- Extension
- $6,642.00
- Proposal total
- $852,064
- vs. low bid
- +$117,434
- vs. engineer’s estimate
- +64%
- Unit price
- $120.00/CY
- Extension
- $9,720.00
- Proposal total
- $863,606
- vs. low bid
- +$128,977
- vs. engineer’s estimate
- +140%
- Unit price
- $100.00/CY
- Extension
- $8,100.00
- Proposal total
- $916,535
- vs. low bid
- +$181,906
- vs. engineer’s estimate
- +100%
- Unit price
- $63.00/CY
- Extension
- $5,103.00
- Proposal total
- $974,652
- vs. low bid
- +$240,023
- vs. engineer’s estimate
- +26%
- Unit price
- $250.00/CY
- Extension
- $20,250.00
- Proposal total
- $981,238
- vs. low bid
- +$246,609
- vs. engineer’s estimate
- +400%
Proposal 0008-02-078 · let Nov 3, 2026 · Parker County, Fort Worth District
Line quantity 275 CY · Engineer’s estimate $150.00/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Jay Mills Contracting, IncorporatedLOW BID | $26.00/CY | $7,150.00 | — | -82.7% | $494,986 | $418 (0.08%) left on table |
| 2 | Texas Materials Group, Inc. | $50.00/CY | $13,750.00 | +$6,600 | -66.7% | $495,404 | +$418.25 |
| 3 | Jagoe-Public Company | $85.00/CY | $23,375.00 | +$16,225 | -43.3% | $598,414 | +$103,428 |
| 4 | Eurovia Atlantic Coast LLC | $115.00/CY | $31,625.00 | +$24,475 | -23.3% | $614,549 | +$119,563 |
| 5 | Overland Corporation | $58.04/CY | $15,961.00 | +$8,811 | -61.3% | $616,693 | +$121,707 |
| 6 | Foutsco Paving Company, LLC | $60.00/CY | $16,500.00 | +$9,350 | -60% | $621,064 | +$126,078 |
| 7 | A. L. Helmcamp, Inc. | $30.00/CY | $8,250.00 | +$1,100 | -80% | $662,993 | +$168,007 |
| 8 | Ed Bell Construction Company | $100.00/CY | $27,500.00 | +$20,350 | -33.3% | $679,542 | +$184,556 |
1. Jay Mills Contracting, Incorporated
LOW BID · WINNER- Unit price
- $26.00/CY
- Extension
- $7,150.00
- Proposal total
- $494,986
- Money left on the table
- $418 (0.08%)
- vs. engineer’s estimate
- -82.7%
- Unit price
- $50.00/CY
- Extension
- $13,750.00
- Proposal total
- $495,404
- vs. low bid
- +$418.25
- vs. engineer’s estimate
- -66.7%
- Unit price
- $85.00/CY
- Extension
- $23,375.00
- Proposal total
- $598,414
- vs. low bid
- +$103,428
- vs. engineer’s estimate
- -43.3%
- Unit price
- $115.00/CY
- Extension
- $31,625.00
- Proposal total
- $614,549
- vs. low bid
- +$119,563
- vs. engineer’s estimate
- -23.3%
5. Overland Corporation
- Unit price
- $58.04/CY
- Extension
- $15,961.00
- Proposal total
- $616,693
- vs. low bid
- +$121,707
- vs. engineer’s estimate
- -61.3%
- Unit price
- $60.00/CY
- Extension
- $16,500.00
- Proposal total
- $621,064
- vs. low bid
- +$126,078
- vs. engineer’s estimate
- -60%
- Unit price
- $30.00/CY
- Extension
- $8,250.00
- Proposal total
- $662,993
- vs. low bid
- +$168,007
- vs. engineer’s estimate
- -80%
- Unit price
- $100.00/CY
- Extension
- $27,500.00
- Proposal total
- $679,542
- vs. low bid
- +$184,556
- vs. engineer’s estimate
- -33.3%
Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District
Line quantity 1,732 CY · Engineer’s estimate $3.88/CY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LPLOW BID | $45.00/CY | $77,940.00 | — | +1,059.8% | $412,233,374 | $3,506,193 (0.85%) left on table |
| 2 | Pulice Construction, Inc. | $22.00/CY | $38,104.00 | -$39,836 | +467% | $415,739,567 | +$3,506,193 |
| 3 | Fluor Enterprises, Inc. | $92.94/CY | $160,972.08 | +$83,032 | +2,295.4% | $473,353,333 | +$61,119,959 |
| 4 | Harper Brothers Construction LLC | $15.00/CY | $25,980.00 | -$51,960 | +286.6% | $477,550,553 | +$65,317,180 |
| 5 | Webber, LLC | $13.30/CY | $23,035.60 | -$54,904 | +242.8% | $477,564,067 | +$65,330,694 |
| 6 | Balfour Beatty Infrastructure, Inc. | $30.01/CY | $51,977.32 | -$25,963 | +673.5% | $492,134,823 | +$79,901,450 |
1. Austin Bridge & Road Services, LP
LOW BID · WINNER- Unit price
- $45.00/CY
- Extension
- $77,940.00
- Proposal total
- $412,233,374
- Money left on the table
- $3,506,193 (0.85%)
- vs. engineer’s estimate
- +1,059.8%
2. Pulice Construction, Inc.
- Unit price
- $22.00/CY
- Extension
- $38,104.00
- Proposal total
- $415,739,567
- vs. low bid
- +$3,506,193
- vs. engineer’s estimate
- +467%
3. Fluor Enterprises, Inc.
- Unit price
- $92.94/CY
- Extension
- $160,972.08
- Proposal total
- $473,353,333
- vs. low bid
- +$61,119,959
- vs. engineer’s estimate
- +2,295.4%
4. Harper Brothers Construction LLC
- Unit price
- $15.00/CY
- Extension
- $25,980.00
- Proposal total
- $477,550,553
- vs. low bid
- +$65,317,180
- vs. engineer’s estimate
- +286.6%
5. Webber, LLC
- Unit price
- $13.30/CY
- Extension
- $23,035.60
- Proposal total
- $477,564,067
- vs. low bid
- +$65,330,694
- vs. engineer’s estimate
- +242.8%
6. Balfour Beatty Infrastructure, Inc.
- Unit price
- $30.01/CY
- Extension
- $51,977.32
- Proposal total
- $492,134,823
- vs. low bid
- +$79,901,450
- vs. engineer’s estimate
- +673.5%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-12 | 6504-61-001 | Potter | Amarillo | 81 | 7 | Ti-Zack Concrete, LLC | $64.63 | $50.00 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 275 | 8 | Jay Mills Contracting, Incorporated | $26.00 | $150.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 1,732 | 6 | Austin Bridge & Road Services, LP | $45.00 | $3.88 |
| 2026-11-03 | 3330-01-011 | McLennan | Waco | 4 | 9 | The Levy Company, LLC | $311.21 | $20.00 |
| 2026-10-07 | 0067-17-039 | Randall | Amarillo | 150 | 5 | Gibson & Associates, Inc. | $128.70 | $60.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 68,259 | 8 | Hunter Industries, Ltd. | $8.60 | $30.00 |
| 2026-10-06 | 0249-02-026 | Archer | Wichita Falls | 686 | 5 | Overland Corporation | $115.00 | $55.00 |
| 2026-09-10 | 6501-04-001 | Kimble | San Angelo | 10 | 10 | 12twelve Road and Bridge LLC | $100.00 | $60.00 |
| 2026-09-03 | 0573-02-008 | Caldwell | Austin | 9,687 | 8 | Hunter Industries, Ltd. | $13.11 | $13.50 |
| 2026-09-03 | 0722-03-016 | Red River | Paris | 5,908 | 8 | Longview Bridge and Road, Ltd. | $10.00 | $27.15 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 34 | $44.00 | $27.50 | $35.00 | -50% |
| Amarillo | 29 | $128.70 | $100.00 | $60.00 | +82% |
| Atlanta | 11 | $15.00 | $73.00 | $110.00 | — |
| Austin | 252 | $13.11 | $17.00 | $15.00 | +10% |
| Beaumont | 3 | $85.00 | $82.00 | $48.00 | — |
| Bryan | 6 | $80.00 | $90.00 | $53.37 | — |
| Childress | 75 | $15.00 | $30.00 | $26.75 | -13.7% |
| Corpus Christi | 5 | $32.31 | $50.00 | $45.00 | — |
| Dallas | 3 | $130.70 | $120.00 | $77.00 | — |
| Fort Worth | 113 | $28.00 | $25.00 | $35.00 | +2.27% |
| Houston | 9 | $124.00 | $65.30 | $200.00 | — |
| Lubbock | 3 | $100.00 | $55.00 | $100.00 | — |
| Lufkin | 39 | $18.00 | $23.50 | $15.00 | — |
| Odessa | 34 | $25.00 | $25.00 | $15.00 | -5.88% |
| Paris | 137 | $10.00 | $22.00 | $27.15 | -11.76% |
| Pharr | 7 | $10.00 | $24.85 | $18.00 | — |
| San Angelo | 65 | $52.59 | $55.00 | $40.00 | +131.58% |
| San Antonio | 171 | $8.60 | $10.00 | $30.00 | 0% |
| Waco | 120 | $9.75 | $15.00 | $15.00 | -17.5% |
| Wichita Falls | 91 | $25.00 | $50.00 | $25.00 | +21.77% |
Related items
- 132-7006 · Embank (FNL)(DC)(TY C) ($12.00/CY)
- 132-7005 · Embank (FNL)(OC)(TY C) ($15.00/CY)
- 110-7001 · Excav (Roadway) ($10.00/CY)
- 110-7002 · Excav (Channel) ($18.00/CY)
- 104-7006 · Remov Conc (Riprap) ($10.00/SY)
- 104-7011 · Remov Conc (Driveways) ($18.21/SY)
- 160-7002 · Furn & Place Topsoil (4") ($1.35/SY)
- 104-7013 · Remov Conc (Sidewalk, Ramp OR SUP) ($15.00/SY)
Is your price for item 132-7003 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.