Elim EXT PM & Mrks (4") (Item 677-7001): TxDOT Unit Price History

2,358 bids · 434 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF

TxDOT 677-7001 · ELIM EXT PM & MRKS (4") · Unit: LF

Low bid
$0.140/LF
Quantity-weighted median of winning unit prices
Weighted median
$0.150/LF
Quantity-weighted median of every bid
Engineer’s estimate
$0.300/LF
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-15.29%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$2.00$4.00$6.00$8.00$10.001101001K10K100K1M10MQuantity (LF), log scaleUnit price ($/LF)
Winning (low) bid Other bid Fitted price curve (ln price = 1.97 − 0.252·ln qty, R² 0.42)320 plotted bids, 5 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 677-7001 (Elim EXT PM & Mrks (4")) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 2,358 bids for it on 434 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,116 bids was $0.150 per LF, and the winning low bidders priced it at a weighted median of $0.140 per LF.

TxDOT's engineer's estimate for the same lines had a weighted median of $0.300 per LF, so winning bids came in 53.3% below the estimate.

By calendar year, the median bid moved from $0.870 in 2025 (1,224 bids) to $0.720 in 2026 (1,029 bids), down 17.2%. The middle half of 2026 bids fell between $0.500 and $1.20.

Comparing the last 12 months with the 12 months before, the median unit price fell 15.29%.

Quantity matters for this item. Lines of 2 to 2,800 LF had a weighted median of $1.10, while lines above 20,868 LF had $0.180, a 84% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 423 lines where both a winning and a second-place bid were published, the median winning unit price was $0.720 against $0.750 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 25 TxDOT districts with at least ten bids, Abilene had the lowest weighted median ($0.090) and San Angelo the highest ($3.00). The busiest district for this item was Dallas.

The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $0.510 per LF for 31,210 LF against an estimate of $0.560.

23 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 677-7008 Elim EXT PM & Mrks (24") (weighted median $2.80 per LF); 677-7002 Elim EXT PM & Mrks (6") (weighted median $0.290 per LF); 677-7004 Elim EXT PM & Mrks (8") (weighted median $0.550 per LF); 677-7009 Elim EXT PM & Mrks (Arrow) (weighted median $50.00 per EA).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
202410524$0.340$0.220$0.750$0.390$2.00
20251,224232$0.420$0.250$0.870$0.500$1.50
20261,029178$0.300$0.150$0.720$0.500$1.20

Quantity bands

BandQuantity (LF)BidsWeighted avgWeighted median25th–75th pct
Small2–2,800791$1.86$1.10$1.00–$3.00
Medium2,807–20,696786$0.920$0.650$0.500–$1.10
Large20,868–4,844,521781$0.320$0.180$0.300–$0.670

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$0.720
Median second-low unit price
$0.750
Median engineer’s estimate
$0.750
Median gap, second vs. low
+0%

423 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District

Line quantity 31,210 LF · Engineer’s estimate $0.560/LF

  • Unit price
    $0.51/LF
    Extension
    $15,917.10
    Proposal total
    $35,766,135
    Money left on the table
    $890,797 (2.49%)
    vs. engineer’s estimate
    -8.9%
  • Unit price
    $0.77/LF
    Extension
    $24,031.70
    Proposal total
    $36,656,931
    vs. low bid
    +$890,797
    vs. engineer’s estimate
    +37.5%
  • 3. Tiseo Paving Company, LLC

    Unit price
    $0.75/LF
    Extension
    $23,407.50
    Proposal total
    $38,169,956
    vs. low bid
    +$2,403,821
    vs. engineer’s estimate
    +33.9%
  • 4. Harper Brothers Construction LLC

    Unit price
    $0.55/LF
    Extension
    $17,165.50
    Proposal total
    $40,441,503
    vs. low bid
    +$4,675,368
    vs. engineer’s estimate
    -1.8%

Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District

Line quantity 66,967 LF · Engineer’s estimate $0.500/LF

  • 1. Indus Road & Bridge, Inc.

    LOW BID · WINNER
    Unit price
    $0.60/LF
    Extension
    $40,180.20
    Proposal total
    $138,145,038
    Money left on the table
    $5,131,824 (3.71%)
    vs. engineer’s estimate
    +20%
  • 2. Rpm Xconstruction, LLC

    Unit price
    $0.55/LF
    Extension
    $36,831.85
    Proposal total
    $143,276,861
    vs. low bid
    +$5,131,824
    vs. engineer’s estimate
    +10%
  • Unit price
    $0.68/LF
    Extension
    $45,537.56
    Proposal total
    $152,579,077
    vs. low bid
    +$14,434,039
    vs. engineer’s estimate
    +36%
  • Unit price
    $0.50/LF
    Extension
    $33,483.50
    Proposal total
    $153,499,152
    vs. low bid
    +$15,354,114
    vs. engineer’s estimate
    0%
  • 5. Sema Construction, Inc.

    Unit price
    $0.50/LF
    Extension
    $33,483.50
    Proposal total
    $154,136,028
    vs. low bid
    +$15,990,990
    vs. engineer’s estimate
    0%
  • 6. Zachry Construction Corporation

    Unit price
    $0.52/LF
    Extension
    $34,822.84
    Proposal total
    $154,873,429
    vs. low bid
    +$16,728,392
    vs. engineer’s estimate
    +4%

Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District

Line quantity 24,562 LF · Engineer’s estimate $0.600/LF

  • 1. Fluor Enterprises, Inc.

    LOW BID · WINNER
    Unit price
    $0.55/LF
    Extension
    $13,509.10
    Proposal total
    $30,209,876
    Money left on the table
    $2,977,718 (9.86%)
    vs. engineer’s estimate
    -8.3%
  • Unit price
    $1.20/LF
    Extension
    $29,474.40
    Proposal total
    $33,187,594
    vs. low bid
    +$2,977,718
    vs. engineer’s estimate
    +100%
  • Unit price
    $0.31/LF
    Extension
    $7,614.22
    Proposal total
    $33,911,798
    vs. low bid
    +$3,701,922
    vs. engineer’s estimate
    -48.3%
  • Unit price
    $0.60/LF
    Extension
    $14,737.20
    Proposal total
    $34,862,676
    vs. low bid
    +$4,652,800
    vs. engineer’s estimate
    0%
  • Unit price
    $1.00/LF
    Extension
    $24,562.00
    Proposal total
    $39,237,828
    vs. low bid
    +$9,027,952
    vs. engineer’s estimate
    +66.7%
  • Unit price
    $1.00/LF
    Extension
    $24,562.00
    Proposal total
    $39,562,405
    vs. low bid
    +$9,352,529
    vs. engineer’s estimate
    +66.7%
  • Unit price
    $1.05/LF
    Extension
    $25,790.10
    Proposal total
    $39,630,699
    vs. low bid
    +$9,420,823
    vs. engineer’s estimate
    +75%
  • Unit price
    $0.58/LF
    Extension
    $14,245.96
    Proposal total
    $39,994,995
    vs. low bid
    +$9,785,119
    vs. engineer’s estimate
    -3.3%
  • 9. Zachry Construction Corporation

    Unit price
    $0.31/LF
    Extension
    $7,614.22
    Proposal total
    $42,444,061
    vs. low bid
    +$12,234,185
    vs. engineer’s estimate
    -48.3%
  • 10. Brizo Construction, LLC

    Unit price
    $0.61/LF
    Extension
    $14,982.82
    Proposal total
    $43,708,350
    vs. low bid
    +$13,498,474
    vs. engineer’s estimate
    +1.7%
  • Unit price
    $0.30/LF
    Extension
    $7,368.60
    Proposal total
    $44,387,970
    vs. low bid
    +$14,178,094
    vs. engineer’s estimate
    -50%
  • Unit price
    $0.53/LF
    Extension
    $13,017.86
    Proposal total
    $48,396,973
    vs. low bid
    +$18,187,097
    vs. engineer’s estimate
    -11.7%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040047-04-032CollinDallas31,2104Mario Sinacola & Sons Excavating, Inc.$0.510$0.560
2026-11-040195-02-092DentonDallas66,9676Indus Road & Bridge, Inc.$0.600$0.500
2026-11-040212-03-058BrazosBryan24,56212Fluor Enterprises, Inc.$0.550$0.600
2026-11-030044-06-079MontagueWichita Falls2,053,2216Breedon Investments USA Inc.$0.145$0.500
2026-11-030059-05-048ShelbyLufkin1,651,3675Clark Construction of Texas, Inc.$0.130$0.200
2026-10-146502-76-001EllisDallas100,0002Stripe-A-Zone, LLC$0.450$0.300
2026-10-070017-13-013AtascosaSan Antonio1,755,0053Ronald R. Wagner & Co., LP$0.150$0.500
2026-10-070022-01-034TerrellOdessa6,2167Relmco, Inc.$1.38$1.00
2026-10-070049-14-015RobertsonBryan4,844,5214Clark Construction of Texas, Inc.$0.130$0.160
2026-10-070143-03-049WilsonSan Antonio116,2578Hunter Industries, Ltd.$0.350$0.450

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene38$0.090$0.090$0.110-60.63%
Amarillo48$2.19$2.30$1.00+100%
Atlanta23$0.650$0.750$0.950—
Austin264$0.150$0.350$0.250-0.62%
Beaumont31$0.200$0.500$0.350+8.16%
Brownwood48$1.75$1.90$1.00+375%
Bryan123$0.130$0.130$0.160+7.14%
Childress42$0.440$0.440$0.450-4.76%
Corpus Christi79$0.330$0.350$0.500+67%
Dallas428$0.520$0.530$0.3000%
El Paso28$0.320$0.320$0.730—
Fort Worth162$0.310$0.440$0.340-41.21%
Houston28$0.400$0.400$0.300—
Laredo53$0.360$0.450$0.400-10%
Lubbock36$0.350$0.450$0.500-21.88%
Lufkin54$0.130$0.130$0.200+7.14%
Odessa121$0.600$0.800$0.570-20%
Paris43$0.550$0.500$0.870-15%
Pharr171$0.450$0.450$0.300-12.28%
San Angelo44$3.49$3.00$1.00+93.55%
San Antonio183$0.150$0.150$0.500-50%
Tyler81$0.580$0.550$0.850-42.5%
Waco34$0.500$1.00$0.750—
Wichita Falls63$0.140$0.140$0.500-73.19%
Yoakum133$3.00$0.750$0.500-50%

Related items

Is your price for item 677-7001 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.