Elim EXT PM & Mrks (8") (Item 677-7004): TxDOT Unit Price History
1,857 bids · 380 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 677-7004 · ELIM EXT PM & MRKS (8") · Unit: LF
- Low bid
- $0.420/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $0.550/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $0.650/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -9.09%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 677-7004 (Elim EXT PM & Mrks (8")) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,857 bids for it on 380 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,018 bids was $0.550 per LF, and the winning low bidders priced it at a weighted median of $0.420 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $0.650 per LF, so winning bids came in 35.4% below the estimate.
By calendar year, the median bid moved from $1.10 in 2025 (797 bids) to $1.00 in 2026 (966 bids), down 9.1%. The middle half of 2026 bids fell between $0.700 and $2.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 9.09%.
Quantity matters for this item. Lines of 1 to 444 LF had a weighted median of $2.00, while lines above 2,600 LF had $0.600, a 70% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 369 lines where both a winning and a second-place bid were published, the median winning unit price was $1.00 against $1.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Fort Worth had the lowest weighted median ($0.350) and Abilene the highest ($2.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Eastland County, where Northeastern Pavers, LLC was the low bidder at $0.500 per LF for 6,503 LF against an estimate of $0.560.
14 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 677-7001 Elim EXT PM & Mrks (4") (weighted median $0.150 per LF); 677-7008 Elim EXT PM & Mrks (24") (weighted median $2.80 per LF); 677-7002 Elim EXT PM & Mrks (6") (weighted median $0.290 per LF); 677-7009 Elim EXT PM & Mrks (Arrow) (weighted median $50.00 per EA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 94 | 19 | $0.930 | $0.850 | $1.05 | $0.800 | $3.00 |
| 2025 | 797 | 173 | $0.910 | $0.750 | $1.10 | $0.750 | $2.20 |
| 2026 | 966 | 188 | $0.640 | $0.600 | $1.00 | $0.700 | $2.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–444 | 621 | $3.36 | $2.00 | $1.02–$4.00 |
| Medium | 450–2,583 | 619 | $1.55 | $1.00 | $0.770–$2.00 |
| Large | 2,600–474,077 | 617 | $0.670 | $0.600 | $0.600–$1.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $1.00
- Median second-low unit price
- $1.00
- Median engineer’s estimate
- $1.03
- Median gap, second vs. low
- +0%
369 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0007-05-016 · let Nov 4, 2026 · Eastland County, Brownwood District
Line quantity 6,503 LF · Engineer’s estimate $0.560/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Northeastern Pavers, LLCLOW BID | $0.50/LF | $3,251.50 | — | -10.7% | $9,329,948 | $150,839 (1.62%) left on table |
| 2 | Ronald R. Wagner & Co., LP | $1.00/LF | $6,503.00 | +$3,252 | +78.6% | $9,480,787 | +$150,839 |
| 3 | Clark Construction of Texas, Inc. | $0.50/LF | $3,251.50 | $0.000 | -10.7% | $10,598,437 | +$1,268,489 |
| 4 | Ck Newberry, LLC | $0.50/LF | $3,251.50 | $0.000 | -10.7% | $11,265,688 | +$1,935,740 |
- LOW BID · WINNER
- Unit price
- $0.50/LF
- Extension
- $3,251.50
- Proposal total
- $9,329,948
- Money left on the table
- $150,839 (1.62%)
- vs. engineer’s estimate
- -10.7%
- Unit price
- $1.00/LF
- Extension
- $6,503.00
- Proposal total
- $9,480,787
- vs. low bid
- +$150,839
- vs. engineer’s estimate
- +78.6%
- Unit price
- $0.50/LF
- Extension
- $3,251.50
- Proposal total
- $10,598,437
- vs. low bid
- +$1,268,489
- vs. engineer’s estimate
- -10.7%
- Unit price
- $0.50/LF
- Extension
- $3,251.50
- Proposal total
- $11,265,688
- vs. low bid
- +$1,935,740
- vs. engineer’s estimate
- -10.7%
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 3,000 LF · Engineer’s estimate $1.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $0.68/LF | $2,040.00 | — | -32% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $0.91/LF | $2,730.00 | +$690.00 | -9% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $0.90/LF | $2,700.00 | +$660.00 | -10% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $0.75/LF | $2,250.00 | +$210.00 | -25% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $0.68/LF
- Extension
- $2,040.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -32%
- Unit price
- $0.91/LF
- Extension
- $2,730.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- -9%
3. Tiseo Paving Company, LLC
- Unit price
- $0.90/LF
- Extension
- $2,700.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -10%
4. Harper Brothers Construction LLC
- Unit price
- $0.75/LF
- Extension
- $2,250.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -25%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 1,909 LF · Engineer’s estimate $2.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $0.80/LF | $1,527.20 | — | -60% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $0.70/LF | $1,336.30 | -$190.90 | -65% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $0.90/LF | $1,718.10 | +$190.90 | -55% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $0.67/LF | $1,279.03 | -$248.17 | -66.5% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $0.67/LF | $1,279.03 | -$248.17 | -66.5% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $0.70/LF | $1,336.30 | -$190.90 | -65% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $0.80/LF
- Extension
- $1,527.20
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -60%
2. Rpm Xconstruction, LLC
- Unit price
- $0.70/LF
- Extension
- $1,336.30
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -65%
- Unit price
- $0.90/LF
- Extension
- $1,718.10
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -55%
4. Webber, LLC
- Unit price
- $0.67/LF
- Extension
- $1,279.03
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -66.5%
5. Sema Construction, Inc.
- Unit price
- $0.67/LF
- Extension
- $1,279.03
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -66.5%
6. Zachry Construction Corporation
- Unit price
- $0.70/LF
- Extension
- $1,336.30
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -65%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0007-05-016 | Eastland | Brownwood | 6,503 | 4 | Northeastern Pavers, LLC | $0.500 | $0.560 |
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 3,000 | 4 | Mario Sinacola & Sons Excavating, Inc. | $0.680 | $1.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 1,909 | 6 | Indus Road & Bridge, Inc. | $0.800 | $2.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 20,860 | 6 | Austin Bridge & Road Services, LP | $0.690 | $0.900 |
| 2026-11-03 | 0038-01-107 | Webb | Laredo | 90 | 4 | Hjc Farms, Inc. | $2.10 | $0.600 |
| 2026-11-03 | 2552-01-062 | El Paso | El Paso | 7,312 | 6 | Allen Concrete, LLC | $0.700 | $0.910 |
| 2026-10-14 | 6502-76-001 | Ellis | Dallas | 5,000 | 2 | Stripe-A-Zone, LLC | $1.05 | $0.470 |
| 2026-10-07 | 0092-05-058 | Ellis | Dallas | 644 | 1 | Clark Construction of Texas, Inc. | $1.00 | $0.660 |
| 2026-10-07 | 0907-00-217 | Tom Green | San Angelo | 1,217 | 7 | Flat Line, Inc. | $1.00 | $7.00 |
| 2026-10-06 | 0009-11-248 | Dallas | Dallas | 5,554 | 7 | Ragle Construction, Inc. | $0.650 | $0.420 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 18 | $3.31 | $2.00 | $1.00 | — |
| Amarillo | 21 | $0.600 | $0.700 | $0.700 | — |
| Atlanta | 35 | $0.700 | $0.730 | $1.00 | — |
| Austin | 168 | $0.690 | $0.690 | $0.900 | -4.76% |
| Beaumont | 55 | $0.500 | $0.500 | $0.700 | -23.13% |
| Brownwood | 34 | $0.500 | $0.500 | $0.560 | +87.5% |
| Bryan | 46 | $1.00 | $1.00 | $1.50 | -13.04% |
| Childress | 8 | $2.00 | $2.00 | $1.00 | — |
| Corpus Christi | 44 | $0.350 | $0.770 | $2.00 | -63.64% |
| Dallas | 378 | $0.700 | $0.720 | $0.700 | -9.09% |
| El Paso | 28 | $0.700 | $0.560 | $0.750 | -57.14% |
| Fort Worth | 119 | $0.350 | $0.350 | $0.560 | -37.5% |
| Houston | 223 | $0.500 | $0.550 | $0.500 | -7.06% |
| Laredo | 55 | $0.710 | $0.600 | $0.680 | -18.24% |
| Lubbock | 75 | $0.700 | $0.700 | $0.800 | +27.78% |
| Lufkin | 4 | $0.900 | $0.840 | $0.600 | — |
| Odessa | 58 | $0.700 | $1.00 | $1.51 | +16.43% |
| Paris | 34 | $1.05 | $1.00 | $1.30 | -22.5% |
| Pharr | 134 | $0.450 | $0.500 | $0.750 | 0% |
| San Angelo | 20 | $1.00 | $1.00 | $7.00 | — |
| San Antonio | 114 | $0.500 | $0.650 | $1.00 | -34.92% |
| Tyler | 78 | $0.500 | $0.700 | $0.600 | -8.51% |
| Waco | 68 | $0.420 | $0.450 | $0.850 | +42.86% |
| Wichita Falls | 12 | $0.750 | $1.38 | $1.00 | — |
| Yoakum | 28 | $1.00 | $1.11 | $2.00 | -63% |
Related items
- 677-7001 · Elim EXT PM & Mrks (4") ($0.150/LF)
- 677-7008 · Elim EXT PM & Mrks (24") ($2.80/LF)
- 677-7002 · Elim EXT PM & Mrks (6") ($0.290/LF)
- 677-7009 · Elim EXT PM & Mrks (Arrow) ($50.00/EA)
- 677-7015 · Elim EXT PM & Mrks (Word) ($50.00/EA)
- 677-7006 · Elim EXT PM & Mrks (12") ($1.00/LF)
- 678-7002 · PAV Surf Prep FOR MRK (6") ($0.020/LF)
- 678-7008 · PAV Surf Prep FOR MRK (24") ($0.500/LF)
Is your price for item 677-7004 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.