Elim EXT PM & Mrks (Arrow) (Item 677-7009): TxDOT Unit Price History

1,615 bids · 339 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure EA

TxDOT 677-7009 · ELIM EXT PM & MRKS (ARROW) · Unit: EA

Low bid
$40.00/EA
Quantity-weighted median of winning unit prices
Weighted median
$50.00/EA
Quantity-weighted median of every bid
Engineer’s estimate
$45.00/EA
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-14.52%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$50.00$100.00$150.00$200.00$250.001101001KQuantity (EA), log scaleUnit price ($/EA)
Winning (low) bid Other bid Fitted price curve (ln price = 4.55 − 0.125·ln qty, R² 0.12)320 plotted bids, 2 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 677-7009 (Elim EXT PM & Mrks (Arrow)) is measured in EA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,615 bids for it on 339 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 922 bids was $50.00 per EA, and the winning low bidders priced it at a weighted median of $40.00 per EA.

TxDOT's engineer's estimate for the same lines had a weighted median of $45.00 per EA, so winning bids came in 11.1% below the estimate.

By calendar year, the median bid moved from $80.00 in 2025 (687 bids) to $70.00 in 2026 (872 bids), down 12.5%. The middle half of 2026 bids fell between $47.98 and $100.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 14.52%.

Quantity matters for this item. Lines of 1 to 4 EA had a weighted median of $95.31, while lines above 22 EA had $50.00, a 48% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 327 lines where both a winning and a second-place bid were published, the median winning unit price was $75.00 against $75.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Odessa had the lowest weighted median ($38.70) and Paris the highest ($105.00). The busiest district for this item was Dallas.

The most recent letting with this item was on Nov 4, 2026 in Eastland County, where Northeastern Pavers, LLC was the low bidder at $100.00 per EA for 16 EA against an estimate of $55.00.

10 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 677-7001 Elim EXT PM & Mrks (4") (weighted median $0.150 per LF); 677-7008 Elim EXT PM & Mrks (24") (weighted median $2.80 per LF); 677-7002 Elim EXT PM & Mrks (6") (weighted median $0.290 per LF); 677-7004 Elim EXT PM & Mrks (8") (weighted median $0.550 per LF).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
20245615$73.29$70.00$94.40$70.00$126.25
2025687156$74.45$60.00$80.00$55.00$110.00
2026872168$58.98$50.00$70.00$47.98$100.00

Quantity bands

BandQuantity (EA)BidsWeighted avgWeighted median25th–75th pct
Small1–4565$117.31$95.31$60.00–$150.00
Medium5–21515$90.51$75.90$55.00–$107.60
Large22–867535$63.85$50.00$42.80–$80.00

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$75.00
Median second-low unit price
$75.00
Median engineer’s estimate
$72.00
Median gap, second vs. low
+0%

327 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0007-05-016 · let Nov 4, 2026 · Eastland County, Brownwood District

Line quantity 16 EA · Engineer’s estimate $55.00/EA

  • 1. Northeastern Pavers, LLC

    LOW BID · WINNER
    Unit price
    $100.00/EA
    Extension
    $1,600.00
    Proposal total
    $9,329,948
    Money left on the table
    $150,839 (1.62%)
    vs. engineer’s estimate
    +81.8%
  • Unit price
    $50.00/EA
    Extension
    $800.00
    Proposal total
    $9,480,787
    vs. low bid
    +$150,839
    vs. engineer’s estimate
    -9.1%
  • Unit price
    $100.00/EA
    Extension
    $1,600.00
    Proposal total
    $10,598,437
    vs. low bid
    +$1,268,489
    vs. engineer’s estimate
    +81.8%
  • Unit price
    $100.00/EA
    Extension
    $1,600.00
    Proposal total
    $11,265,688
    vs. low bid
    +$1,935,740
    vs. engineer’s estimate
    +81.8%

Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District

Line quantity 6 EA · Engineer’s estimate $58.00/EA

  • Unit price
    $45.00/EA
    Extension
    $270.00
    Proposal total
    $35,766,135
    Money left on the table
    $890,797 (2.49%)
    vs. engineer’s estimate
    -22.4%
  • Unit price
    $57.75/EA
    Extension
    $346.50
    Proposal total
    $36,656,931
    vs. low bid
    +$890,797
    vs. engineer’s estimate
    -0.4%
  • 3. Tiseo Paving Company, LLC

    Unit price
    $58.00/EA
    Extension
    $348.00
    Proposal total
    $38,169,956
    vs. low bid
    +$2,403,821
    vs. engineer’s estimate
    0%
  • 4. Harper Brothers Construction LLC

    Unit price
    $65.00/EA
    Extension
    $390.00
    Proposal total
    $40,441,503
    vs. low bid
    +$4,675,368
    vs. engineer’s estimate
    +12.1%

Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District

Line quantity 60 EA · Engineer’s estimate $43.53/EA

  • Unit price
    $55.00/EA
    Extension
    $3,300.00
    Proposal total
    $412,233,374
    Money left on the table
    $3,506,193 (0.85%)
    vs. engineer’s estimate
    +26.3%
  • 2. Pulice Construction, Inc.

    Unit price
    $45.92/EA
    Extension
    $2,755.20
    Proposal total
    $415,739,567
    vs. low bid
    +$3,506,193
    vs. engineer’s estimate
    +5.5%
  • 3. Fluor Enterprises, Inc.

    Unit price
    $48.15/EA
    Extension
    $2,889.00
    Proposal total
    $473,353,333
    vs. low bid
    +$61,119,959
    vs. engineer’s estimate
    +10.6%
  • 4. Harper Brothers Construction LLC

    Unit price
    $200.00/EA
    Extension
    $12,000.00
    Proposal total
    $477,550,553
    vs. low bid
    +$65,317,180
    vs. engineer’s estimate
    +359.5%
  • Unit price
    $45.00/EA
    Extension
    $2,700.00
    Proposal total
    $477,564,067
    vs. low bid
    +$65,330,694
    vs. engineer’s estimate
    +3.4%
  • 6. Balfour Beatty Infrastructure, Inc.

    Unit price
    $55.00/EA
    Extension
    $3,300.00
    Proposal total
    $492,134,823
    vs. low bid
    +$79,901,450
    vs. engineer’s estimate
    +26.3%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040007-05-016EastlandBrownwood164Northeastern Pavers, LLC$100.00$55.00
2026-11-040047-04-032CollinDallas64Mario Sinacola & Sons Excavating, Inc.$45.00$58.00
2026-11-030015-13-432TravisAustin606Austin Bridge & Road Services, LP$55.00$43.53
2026-11-030044-06-079MontagueWichita Falls1206Breedon Investments USA Inc.$50.00$50.00
2026-11-030059-05-048ShelbyLufkin515Clark Construction of Texas, Inc.$100.00$65.00
2026-11-032552-01-062El PasoEl Paso426Allen Concrete, LLC$96.00$58.62
2026-10-070092-05-058EllisDallas1431Clark Construction of Texas, Inc.$50.00$57.51
2026-10-070907-00-217Tom GreenSan Angelo147Flat Line, Inc.$100.00$110.00
2026-10-060009-11-248DallasDallas47Ragle Construction, Inc.$40.00$56.00
2026-10-066496-83-001GreggTyler252Striping Technology, L.P.$100.00$40.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene32$85.10$100.00$37.00-28.15%
Amarillo32$15.00$50.00$100.00-18.18%
Atlanta21$40.00$44.00$75.00—
Austin139$78.75$70.00$50.00+5.26%
Beaumont49$25.00$40.00$37.51-9.42%
Brownwood21$100.00$100.00$55.00—
Bryan48$50.00$60.00$88.20-6.49%
Childress7$18.00$58.50$25.00—
Corpus Christi44$20.00$40.00$2.80+53.75%
Dallas296$50.00$52.72$50.00-27.94%
El Paso33$50.00$81.50$75.00-35.8%
Fort Worth103$30.00$40.00$29.61-28.57%
Houston207$40.00$40.00$45.00-28.57%
Laredo47$76.53$65.00$77.94+33.33%
Lubbock30$70.00$75.00$100.00+33.33%
Lufkin23$100.00$81.60$65.00—
Odessa20$38.50$38.70$80.00—
Paris33$105.00$105.00$85.00+53.28%
Pharr145$25.00$50.00$40.00-5.06%
San Angelo19$100.00$60.00$110.00—
San Antonio80$100.00$60.00$125.00+11.11%
Tyler56$80.00$70.50$75.00+38.75%
Waco77$40.00$55.00$41.35-5.71%
Wichita Falls45$50.00$50.00$50.00+16.67%
Yoakum8$55.00$55.00$60.00—

Related items

Is your price for item 677-7009 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.