MTL W-Beam GD FEN (Steel Post) (Item 540-7002): TxDOT Unit Price History

1,434 bids · 244 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF

TxDOT 540-7002 · MTL W-BEAM GD FEN (STEEL POST) · Unit: LF

Low bid
$32.60/LF
Quantity-weighted median of winning unit prices
Weighted median
$31.00/LF
Quantity-weighted median of every bid
Engineer’s estimate
$32.54/LF
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-2.94%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$30.00$40.00$50.00$60.00$70.00101001K10K100KQuantity (LF), log scaleUnit price ($/LF)
Winning (low) bid Other bid Fitted price curve (ln price = 3.98 − 0.068·ln qty, R² 0.13)320 plotted bids, 5 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 540-7002 (MTL W-Beam GD FEN (Steel Post)) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,434 bids for it on 244 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 689 bids was $31.00 per LF, and the winning low bidders priced it at a weighted median of $32.60 per LF.

Winning unit prices sat close to TxDOT's own engineer's estimate ($32.54 per LF), within two percent.

By calendar year, the median bid moved from $33.69 in 2025 (711 bids) to $33.00 in 2026 (636 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $30.00 and $39.61.

Comparing the last 12 months with the 12 months before, the median unit price fell 2.94%.

Quantity matters for this item. Lines of 5 to 350 LF had a weighted median of $35.00, while lines above 1,175 LF had $30.75, a 12% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 220 lines where both a winning and a second-place bid were published, the median winning unit price was $33.00 against $32.53 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 17 TxDOT districts with at least ten bids, Bryan had the lowest weighted median ($25.00) and Lufkin the highest ($40.00). The busiest district for this item was Paris.

The most recent letting with this item was on Nov 4, 2026 in Denton County, where Indus Road & Bridge, Inc. was the low bidder at $33.00 per LF for 1,025 LF against an estimate of $38.00.

66 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 540-7001 MTL W-Beam GD FEN (TIM Post) (weighted median $25.75 per LF); 540-7005 MTL Beam GD FEN Trans (Thrie-Beam) (weighted median $2,208.14 per EA); 540-7015 Downstream Anchor Terminal Section (weighted median $1,485.00 per EA); 542-7001 Remove Metal Beam Guard Fence (weighted median $2.55 per LF).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
20248714$32.81$31.00$35.00$31.80$42.00
2025711127$32.45$30.16$33.69$30.00$40.00
2026636103$32.88$31.00$33.00$30.00$39.61

Quantity bands

BandQuantity (LF)BidsWeighted avgWeighted median25th–75th pct
Small5–350488$38.75$35.00$32.00–$46.06
Medium355–1,137.5473$34.22$32.50$29.40–$38.00
Large1,175–40,812.5473$32.18$30.75$29.50–$35.00

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$33.00
Median second-low unit price
$32.53
Median engineer’s estimate
$35.00
Median gap, second vs. low
+0%

220 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District

Line quantity 1,025 LF · Engineer’s estimate $38.00/LF

  • 1. Indus Road & Bridge, Inc.

    LOW BID · WINNER
    Unit price
    $33.00/LF
    Extension
    $33,825.00
    Proposal total
    $138,145,038
    Money left on the table
    $5,131,824 (3.71%)
    vs. engineer’s estimate
    -13.2%
  • 2. Rpm Xconstruction, LLC

    Unit price
    $32.00/LF
    Extension
    $32,800.00
    Proposal total
    $143,276,861
    vs. low bid
    +$5,131,824
    vs. engineer’s estimate
    -15.8%
  • Unit price
    $32.00/LF
    Extension
    $32,800.00
    Proposal total
    $152,579,077
    vs. low bid
    +$14,434,039
    vs. engineer’s estimate
    -15.8%
  • Unit price
    $30.77/LF
    Extension
    $31,539.25
    Proposal total
    $153,499,152
    vs. low bid
    +$15,354,114
    vs. engineer’s estimate
    -19%
  • 5. Sema Construction, Inc.

    Unit price
    $30.00/LF
    Extension
    $30,750.00
    Proposal total
    $154,136,028
    vs. low bid
    +$15,990,990
    vs. engineer’s estimate
    -21.1%
  • 6. Zachry Construction Corporation

    Unit price
    $31.13/LF
    Extension
    $31,908.25
    Proposal total
    $154,873,429
    vs. low bid
    +$16,728,392
    vs. engineer’s estimate
    -18.1%

Proposal 1017-03-040 · let Nov 4, 2026 · Hunt County, Paris District

Line quantity 850 LF · Engineer’s estimate $23.00/LF

  • 1. Highway 19 Construction LLC

    LOW BID · WINNER
    Unit price
    $30.00/LF
    Extension
    $25,500.00
    Proposal total
    $6,803,596
    Money left on the table
    $438,151 (6.44%)
    vs. engineer’s estimate
    +30.4%
  • Unit price
    $32.74/LF
    Extension
    $27,829.00
    Proposal total
    $7,241,746
    vs. low bid
    +$438,151
    vs. engineer’s estimate
    +42.3%
  • Unit price
    $32.50/LF
    Extension
    $27,625.00
    Proposal total
    $7,366,754
    vs. low bid
    +$563,159
    vs. engineer’s estimate
    +41.3%
  • Unit price
    $30.00/LF
    Extension
    $25,500.00
    Proposal total
    $7,400,348
    vs. low bid
    +$596,752
    vs. engineer’s estimate
    +30.4%
  • Unit price
    $30.45/LF
    Extension
    $25,882.50
    Proposal total
    $7,514,717
    vs. low bid
    +$711,122
    vs. engineer’s estimate
    +32.4%
  • Unit price
    $30.00/LF
    Extension
    $25,500.00
    Proposal total
    $7,794,981
    vs. low bid
    +$991,385
    vs. engineer’s estimate
    +30.4%
  • Unit price
    $29.00/LF
    Extension
    $24,650.00
    Proposal total
    $7,795,159
    vs. low bid
    +$991,563
    vs. engineer’s estimate
    +26.1%
  • Unit price
    $32.00/LF
    Extension
    $27,200.00
    Proposal total
    $8,325,506
    vs. low bid
    +$1,521,910
    vs. engineer’s estimate
    +39.1%
  • Unit price
    $32.00/LF
    Extension
    $27,200.00
    Proposal total
    $9,159,173
    vs. low bid
    +$2,355,578
    vs. engineer’s estimate
    +39.1%

Proposal 0022-03-032 · let Nov 3, 2026 · Terrell County, Odessa District

Line quantity 350 LF · Engineer’s estimate $34.90/LF

  • 1. The Truesdell Corporation

    LOW BID · WINNER
    Unit price
    $38.00/LF
    Extension
    $13,300.00
    Proposal total
    $2,888,888
    Money left on the table
    $89,789 (3.11%)
    vs. engineer’s estimate
    +8.9%
  • Unit price
    $37.40/LF
    Extension
    $13,090.00
    Proposal total
    $2,978,677
    vs. low bid
    +$89,789
    vs. engineer’s estimate
    +7.2%
  • Unit price
    $35.00/LF
    Extension
    $12,250.00
    Proposal total
    $3,052,152
    vs. low bid
    +$163,264
    vs. engineer’s estimate
    +0.3%
  • Unit price
    $35.00/LF
    Extension
    $12,250.00
    Proposal total
    $3,205,119
    vs. low bid
    +$316,231
    vs. engineer’s estimate
    +0.3%
  • Unit price
    $35.00/LF
    Extension
    $12,250.00
    Proposal total
    $3,332,351
    vs. low bid
    +$443,463
    vs. engineer’s estimate
    +0.3%
  • Unit price
    $42.00/LF
    Extension
    $14,700.00
    Proposal total
    $3,557,553
    vs. low bid
    +$668,665
    vs. engineer’s estimate
    +20.3%
  • Unit price
    $35.00/LF
    Extension
    $12,250.00
    Proposal total
    $3,982,565
    vs. low bid
    +$1,093,677
    vs. engineer’s estimate
    +0.3%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040195-02-092DentonDallas1,0256Indus Road & Bridge, Inc.$33.00$38.00
2026-11-041017-03-040HuntParis8509Highway 19 Construction LLC$30.00$23.00
2026-11-030022-03-032TerrellOdessa3507The Truesdell Corporation$38.00$34.90
2026-11-030168-09-191RandallAmarillo9758Coppell Construction Co., Inc.$38.00$35.00
2026-10-070022-01-034TerrellOdessa9007Relmco, Inc.$44.00$32.00
2026-10-070092-02-145DallasDallas3,262.56Sice, Inc.$36.60$35.50
2026-10-070143-03-049WilsonSan Antonio2758Hunter Industries, Ltd.$38.22$34.00
2026-10-070510-06-024FanninParis5,7006A. K. Gillis & Sons, LLC$27.55$25.00
2026-10-060009-11-248DallasDallas257Ragle Construction, Inc.$32.00$30.50
2026-10-060410-02-047GraysonParis9757Highway 19 Construction LLC$28.00$27.50

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Amarillo92$32.60$32.60$32.00-7.5%
Atlanta6$91.00$90.00$32.00—
Austin47$26.28$37.00$43.100%
Beaumont2$42.25$46.13$30.00—
Brownwood88$33.00$33.00$32.00+3.13%
Bryan25$25.00$25.00$35.00-42.53%
Childress108$37.40$31.50$40.00-10.53%
Corpus Christi7$33.70$35.00$48.00—
Dallas110$36.60$33.00$35.50+0.79%
El Paso40$28.00$31.00$32.00-10.71%
Fort Worth51$32.00$30.00$45.00-18.51%
Houston58$34.10$38.00$30.00+14.29%
Laredo5$50.00$45.00$80.00—
Lubbock66$33.00$35.00$45.00+1.45%
Lufkin10$40.00$40.00$250.00—
Odessa98$41.00$38.00$32.54-2.62%
Paris216$30.75$29.00$25.80-1.03%
Pharr2$37.00$38.50$35.00—
San Angelo59$28.00$32.00$35.00+7.35%
San Antonio38$38.00$38.20$33.00+29.39%
Tyler145$26.00$27.06$35.00-2.42%
Waco154$30.50$32.50$35.00+1.56%
Wichita Falls7$32.32$34.00$40.00—

Related items

Is your price for item 540-7002 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.