Cement (Item 275-7001): TxDOT Unit Price History
1,294 bids · 212 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure TON
TxDOT 275-7001 · CEMENT · Unit: TON
- Low bid
- $210.00/TON
- Quantity-weighted median of winning unit prices
- Weighted median
- $220.00/TON
- Quantity-weighted median of every bid
- Engineer’s estimate
- $220.00/TON
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -5.77%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 275-7001 (Cement) is measured in TON. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,294 bids for it on 212 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 609 bids was $220.00 per TON, and the winning low bidders priced it at a weighted median of $210.00 per TON.
TxDOT's engineer's estimate for the same lines had a weighted median of $220.00 per TON, so winning bids came in 4.5% below the estimate.
By calendar year, the median bid moved from $255.00 in 2025 (738 bids) to $245.00 in 2026 (517 bids), down 3.9%. The middle half of 2026 bids fell between $215.00 and $280.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 5.77%.
Quantity matters for this item. Lines of 3 to 116 TON had a weighted median of $280.00, while lines above 800 TON had $220.00, a 21% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 206 lines where both a winning and a second-place bid were published, the median winning unit price was $242.50 against $240.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 20 TxDOT districts with at least ten bids, Houston had the lowest weighted median ($167.30) and Brownwood the highest ($500.00). The busiest district for this item was Yoakum.
The most recent letting with this item was on Nov 4, 2026 in Brazos County, where Fluor Enterprises, Inc. was the low bidder at $185.00 per TON for 2,113 TON against an estimate of $215.00.
14 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 260-7001 Lime (COM OR QK)(Slurry) OR QK(DRY) (weighted median $345.92 per TON); 341-7082 Tack Coat (weighted median $4.00 per GAL); 341-7001 D-GR HMA TY-B PG64-22 (weighted median $85.40 per TON); 341-7050 D-GR HMA TY-D SAC-B PG70-22 (weighted median $125.00 per TON).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 39 | 6 | $277.75 | $269.25 | $300.00 | $257.97 | $347.50 |
| 2025 | 738 | 124 | $242.36 | $229.00 | $255.00 | $225.00 | $310.90 |
| 2026 | 517 | 82 | $228.33 | $220.00 | $245.00 | $215.00 | $280.00 |
Quantity bands
| Band | Quantity (TON) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 3–116 | 434 | $297.58 | $280.00 | $246.38–$350.00 |
| Medium | 116.25–792 | 431 | $261.21 | $250.00 | $225.00–$299.75 |
| Large | 800–14,516.86 | 429 | $230.01 | $220.00 | $209.31–$260.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $242.50
- Median second-low unit price
- $240.00
- Median engineer’s estimate
- $250.00
- Median gap, second vs. low
- +0%
206 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 2,113 TON · Engineer’s estimate $215.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $185.00/TON | $390,905.00 | — | -14% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $220.00/TON | $464,860.00 | +$73,955 | +2.3% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $215.85/TON | $456,091.05 | +$65,186 | +0.4% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $220.00/TON | $464,860.00 | +$73,955 | +2.3% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $217.31/TON | $459,176.03 | +$68,271 | +1.1% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $216.00/TON | $456,408.00 | +$65,503 | +0.5% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $220.00/TON | $464,860.00 | +$73,955 | +2.3% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $250.00/TON | $528,250.00 | +$137,345 | +16.3% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $173.71/TON | $367,049.23 | -$23,856 | -19.2% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $225.50/TON | $476,481.50 | +$85,577 | +4.9% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $200.00/TON | $422,600.00 | +$31,695 | -7% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $220.00/TON | $464,860.00 | +$73,955 | +2.3% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $185.00/TON
- Extension
- $390,905.00
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- -14%
- Unit price
- $220.00/TON
- Extension
- $464,860.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- +2.3%
- Unit price
- $215.85/TON
- Extension
- $456,091.05
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- +0.4%
- Unit price
- $220.00/TON
- Extension
- $464,860.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- +2.3%
- Unit price
- $217.31/TON
- Extension
- $459,176.03
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- +1.1%
- Unit price
- $216.00/TON
- Extension
- $456,408.00
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- +0.5%
- Unit price
- $220.00/TON
- Extension
- $464,860.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- +2.3%
- Unit price
- $250.00/TON
- Extension
- $528,250.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- +16.3%
9. Zachry Construction Corporation
- Unit price
- $173.71/TON
- Extension
- $367,049.23
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- -19.2%
10. Brizo Construction, LLC
- Unit price
- $225.50/TON
- Extension
- $476,481.50
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- +4.9%
- Unit price
- $200.00/TON
- Extension
- $422,600.00
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- -7%
- Unit price
- $220.00/TON
- Extension
- $464,860.00
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- +2.3%
Proposal 0262-01-034 · let Nov 4, 2026 · Milam County, Bryan District
Line quantity 3,559 TON · Engineer’s estimate $215.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Big Creek Construction, Ltd.LOW BID | $210.00/TON | $747,390.00 | — | -2.3% | $9,787,627 | $395,153 (4.04%) left on table |
| 2 | Larry Young Paving, Inc. | $200.00/TON | $711,800.00 | -$35,590 | -7% | $10,182,780 | +$395,153 |
| 3 | Knife River Corporation - South | $183.50/TON | $653,076.50 | -$94,314 | -14.7% | $10,424,591 | +$636,964 |
| 4 | Texas Materials Group, Inc. | $210.00/TON | $747,390.00 | $0.000 | -2.3% | $12,020,138 | +$2,232,511 |
| 5 | A. L. Helmcamp, Inc. | $230.00/TON | $818,570.00 | +$71,180 | +7% | $12,374,454 | +$2,586,827 |
| 6 | Patin Construction LLC | $260.00/TON | $925,340.00 | +$177,950 | +20.9% | $15,629,317 | +$5,841,690 |
| 7 | Joe Bland Construction LLC | $240.00/TON | $854,160.00 | +$106,770 | +11.6% | $18,492,861 | +$8,705,235 |
1. Big Creek Construction, Ltd.
LOW BID · WINNER- Unit price
- $210.00/TON
- Extension
- $747,390.00
- Proposal total
- $9,787,627
- Money left on the table
- $395,153 (4.04%)
- vs. engineer’s estimate
- -2.3%
- Unit price
- $200.00/TON
- Extension
- $711,800.00
- Proposal total
- $10,182,780
- vs. low bid
- +$395,153
- vs. engineer’s estimate
- -7%
- Unit price
- $183.50/TON
- Extension
- $653,076.50
- Proposal total
- $10,424,591
- vs. low bid
- +$636,964
- vs. engineer’s estimate
- -14.7%
- Unit price
- $210.00/TON
- Extension
- $747,390.00
- Proposal total
- $12,020,138
- vs. low bid
- +$2,232,511
- vs. engineer’s estimate
- -2.3%
- Unit price
- $230.00/TON
- Extension
- $818,570.00
- Proposal total
- $12,374,454
- vs. low bid
- +$2,586,827
- vs. engineer’s estimate
- +7%
6. Patin Construction LLC
- Unit price
- $260.00/TON
- Extension
- $925,340.00
- Proposal total
- $15,629,317
- vs. low bid
- +$5,841,690
- vs. engineer’s estimate
- +20.9%
7. Joe Bland Construction LLC
- Unit price
- $240.00/TON
- Extension
- $854,160.00
- Proposal total
- $18,492,861
- vs. low bid
- +$8,705,235
- vs. engineer’s estimate
- +11.6%
Proposal 0143-03-049 · let Oct 7, 2026 · Wilson County, San Antonio District
Line quantity 3,518 TON · Engineer’s estimate $210.00/TON
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Hunter Industries, Ltd.LOW BID | $190.80/TON | $671,234.40 | — | -9.1% | $39,881,467 | $3,757,182 (9.42%) left on table |
| 2 | Ck Newberry, LLC | $200.00/TON | $703,600.00 | +$32,366 | -4.8% | $43,638,649 | +$3,757,182 |
| 3 | Webber, LLC | $183.80/TON | $646,608.40 | -$24,626 | -12.5% | $44,378,700 | +$4,497,232 |
| 4 | Jordan Foster Construction, LLC | $195.00/TON | $686,010.00 | +$14,776 | -7.1% | $47,525,791 | +$7,644,324 |
| 5 | E-Z Bel Construction, LLC | $250.00/TON | $879,500.00 | +$208,266 | +19% | $48,723,770 | +$8,842,303 |
| 6 | Posillico Civil, Inc. | $185.00/TON | $650,830.00 | -$20,404 | -11.9% | $48,887,304 | +$9,005,837 |
| 7 | Joe Bland Construction LLC | $240.00/TON | $844,320.00 | +$173,086 | +14.3% | $51,897,341 | +$12,015,874 |
| 8 | J3 Company, LLC | $195.00/TON | $686,010.00 | +$14,776 | -7.1% | $52,863,113 | +$12,981,645 |
- LOW BID · WINNER
- Unit price
- $190.80/TON
- Extension
- $671,234.40
- Proposal total
- $39,881,467
- Money left on the table
- $3,757,182 (9.42%)
- vs. engineer’s estimate
- -9.1%
- Unit price
- $200.00/TON
- Extension
- $703,600.00
- Proposal total
- $43,638,649
- vs. low bid
- +$3,757,182
- vs. engineer’s estimate
- -4.8%
3. Webber, LLC
- Unit price
- $183.80/TON
- Extension
- $646,608.40
- Proposal total
- $44,378,700
- vs. low bid
- +$4,497,232
- vs. engineer’s estimate
- -12.5%
- Unit price
- $195.00/TON
- Extension
- $686,010.00
- Proposal total
- $47,525,791
- vs. low bid
- +$7,644,324
- vs. engineer’s estimate
- -7.1%
- Unit price
- $250.00/TON
- Extension
- $879,500.00
- Proposal total
- $48,723,770
- vs. low bid
- +$8,842,303
- vs. engineer’s estimate
- +19%
- Unit price
- $185.00/TON
- Extension
- $650,830.00
- Proposal total
- $48,887,304
- vs. low bid
- +$9,005,837
- vs. engineer’s estimate
- -11.9%
7. Joe Bland Construction LLC
- Unit price
- $240.00/TON
- Extension
- $844,320.00
- Proposal total
- $51,897,341
- vs. low bid
- +$12,015,874
- vs. engineer’s estimate
- +14.3%
8. J3 Company, LLC
- Unit price
- $195.00/TON
- Extension
- $686,010.00
- Proposal total
- $52,863,113
- vs. low bid
- +$12,981,645
- vs. engineer’s estimate
- -7.1%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 2,113 | 12 | Fluor Enterprises, Inc. | $185.00 | $215.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 3,559 | 7 | Big Creek Construction, Ltd. | $210.00 | $215.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 3,518 | 8 | Hunter Industries, Ltd. | $190.80 | $210.00 |
| 2026-10-07 | 0200-01-093 | Angelina | Lufkin | 655 | 7 | Longview Bridge and Road, Ltd. | $240.00 | $230.00 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 606 | 6 | A. K. Gillis & Sons, LLC | $230.00 | $225.00 |
| 2026-10-07 | 0921-02-527 | Hidalgo | Pharr | 20 | 1 | Digg Commercial, LLC | $300.00 | $200.00 |
| 2026-10-06 | 0387-01-016 | Collin | Dallas | 522 | 8 | A. K. Gillis & Sons, LLC | $217.00 | $250.00 |
| 2026-10-06 | 1122-01-034 | Karnes | Corpus Christi | 3,584 | 7 | Ck Newberry, LLC | $185.00 | $190.00 |
| 2026-09-03 | 0275-03-072 | Carson | Amarillo | 193 | 7 | Gilvin-Terrill, Ltd. | $230.00 | $300.00 |
| 2026-09-03 | 1505-01-016 | Cameron | Pharr | 1,350 | 5 | Reim Construction, Inc. | $190.00 | $190.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 34 | $250.00 | $250.00 | $265.00 | — |
| Amarillo | 29 | $255.00 | $255.00 | $310.00 | — |
| Atlanta | 72 | $210.00 | $245.00 | $192.00 | -13.58% |
| Austin | 8 | $215.00 | $300.41 | $300.00 | — |
| Beaumont | 6 | $295.00 | $322.50 | $272.50 | — |
| Brownwood | 15 | $450.00 | $500.00 | $500.00 | — |
| Bryan | 144 | $210.00 | $217.31 | $215.00 | -11.54% |
| Childress | 17 | $299.00 | $275.00 | $231.62 | — |
| Corpus Christi | 53 | $185.00 | $190.80 | $190.00 | +0.8% |
| Dallas | 113 | $223.00 | $232.00 | $250.00 | -7.69% |
| El Paso | 18 | $253.00 | $261.50 | $385.00 | — |
| Fort Worth | 72 | $233.00 | $233.00 | $160.00 | 0% |
| Houston | 16 | $167.30 | $167.30 | $205.00 | — |
| Laredo | 3 | $200.00 | $230.00 | $293.00 | — |
| Lubbock | 5 | $277.60 | $265.00 | $245.01 | — |
| Lufkin | 83 | $230.00 | $235.00 | $250.00 | -15.63% |
| Paris | 43 | $230.00 | $255.00 | $225.00 | -2.26% |
| Pharr | 102 | $183.25 | $200.00 | $220.00 | -4.76% |
| San Angelo | 14 | $300.00 | $307.04 | $275.00 | — |
| San Antonio | 41 | $190.80 | $196.00 | $210.00 | -15.78% |
| Tyler | 115 | $263.00 | $265.00 | $270.00 | -10.44% |
| Waco | 35 | $219.00 | $222.00 | $250.00 | +1.69% |
| Wichita Falls | 77 | $250.00 | $250.00 | $220.00 | -11.61% |
| Yoakum | 179 | $205.20 | $215.00 | $180.00 | +6.82% |
Related items
- 260-7001 · Lime (COM OR QK)(Slurry) OR QK(DRY) ($345.92/TON)
- 341-7082 · Tack Coat ($4.00/GAL)
- 341-7001 · D-GR HMA TY-B PG64-22 ($85.40/TON)
- 341-7050 · D-GR HMA TY-D SAC-B PG70-22 ($125.00/TON)
- 344-7077 · Tack Coat ($4.50/GAL)
- 344-7001 · SP Mixes SP-B PG64-22 ($127.00/TON)
- 168-7001 · Vegetative Watering ($7.00/TGL)
- 164-7005 · Broadcast Seed (Temp_Warm) ($0.150/SY)
Is your price for item 275-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.