Mobilization (Item 500-7001): TxDOT Unit Price History
12,240 bids · 2,199 bid lines · Sep 6, 2024 to Nov 12, 2026 · unit of measure LS
TxDOT 500-7001 · MOBILIZATION · Unit: LS
- Low bid
- $99,600.00/LS
- Quantity-weighted median of winning unit prices
- Weighted median
- $128,675.16/LS
- Quantity-weighted median of every bid
- Engineer’s estimate
- $140,810.22/LS
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -21.47%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Sep 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 500-7001 (Mobilization) is measured in LS. Between Sep 6, 2024 and Nov 12, 2026, contractors entered 12,240 bids for it on 2,199 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 6,280 bids was $128,675.16 per LS, and the winning low bidders priced it at a weighted median of $99,600.00 per LS.
TxDOT's engineer's estimate for the same lines had a weighted median of $140,810.22 per LS, so winning bids came in 29.3% below the estimate.
By calendar year, the median bid moved from $155,000.00 in 2025 (5,865 bids) to $125,990.00 in 2026 (5,807 bids), down 18.7%. The middle half of 2026 bids fell between $50,000.00 and $357,250.57.
Comparing the last 12 months with the 12 months before, the median unit price fell 21.47%.
Across 1,995 lines where both a winning and a second-place bid were published, the median winning unit price was $110,000.00 against $137,000.00 from the second-lowest bidder, a median gap of 11.68% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 25 TxDOT districts with at least ten bids, San Angelo had the lowest weighted median ($77,800.00) and Laredo the highest ($261,264.16). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 12, 2026 in Potter County, where Ti-Zack Concrete, LLC was the low bidder at $29,375.00 per LS for 1 LS against an estimate of $60,000.00.
402 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 500-7002 Mobilization (Callout) (weighted median $100.00 per EA); 502-7001 Barricades, Signs AND Traffic Handling (weighted median $6,500.00 per MO); 503-7001 Portable Changeable Message Sign (weighted median $95.00 per DAY); 503-7002 Portable Changeable Message Sign (weighted median $9,010.00 per EA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 568 | 109 | $608,841.57 | $180,764.56 | $187,482.51 | $50,000.00 | $500,000.00 |
| 2025 | 5,865 | 1,095 | $585,037.69 | $150,000.00 | $155,000.00 | $50,000.00 | $417,136.69 |
| 2026 | 5,807 | 1,000 | $706,886.54 | $125,990.00 | $125,990.00 | $50,000.00 | $357,250.57 |
Quantity bands
| Band | Quantity (LS) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| All quantities | 0.01–12 | 12,240 | $643,590.62 | $146,373.99 | $50,000.00–$400,000.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $110,000.00
- Median second-low unit price
- $137,000.00
- Median engineer’s estimate
- $165,000.00
- Median gap, second vs. low
- +11.68%
1,995 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6504-61-001 · let Nov 12, 2026 · Potter County, Amarillo District
Line quantity 1 LS · Engineer’s estimate $60,000/LS
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLCLOW BID | $29,375.00/LS | $29,375.00 | — | -51% | $734,629 | $59,414 (8.09%) left on table |
| 2 | Cross Plus Construction, LLC | $50,000.00/LS | $50,000.00 | +$20,625 | -16.7% | $794,043 | +$59,414 |
| 3 | Structural Integrity Group LLC | $85,000.00/LS | $85,000.00 | +$55,625 | +41.7% | $852,064 | +$117,434 |
| 4 | Pathfield Investments LLC | $60,000.00/LS | $60,000.00 | +$30,625 | 0% | $863,606 | +$128,977 |
| 5 | Scr Civil Construction, LLC | $60,000.00/LS | $60,000.00 | +$30,625 | 0% | $916,535 | +$181,906 |
| 6 | Icos Management, LLC | $65,500.00/LS | $65,500.00 | +$36,125 | +9.2% | $974,652 | +$240,023 |
| 7 | Road Doctors LLC | $80,000.00/LS | $80,000.00 | +$50,625 | +33.3% | $981,238 | +$246,609 |
- LOW BID · WINNER
- Unit price
- $29,375.00/LS
- Extension
- $29,375.00
- Proposal total
- $734,629
- Money left on the table
- $59,414 (8.09%)
- vs. engineer’s estimate
- -51%
- Unit price
- $50,000.00/LS
- Extension
- $50,000.00
- Proposal total
- $794,043
- vs. low bid
- +$59,414
- vs. engineer’s estimate
- -16.7%
- Unit price
- $85,000.00/LS
- Extension
- $85,000.00
- Proposal total
- $852,064
- vs. low bid
- +$117,434
- vs. engineer’s estimate
- +41.7%
- Unit price
- $60,000.00/LS
- Extension
- $60,000.00
- Proposal total
- $863,606
- vs. low bid
- +$128,977
- vs. engineer’s estimate
- 0%
- Unit price
- $60,000.00/LS
- Extension
- $60,000.00
- Proposal total
- $916,535
- vs. low bid
- +$181,906
- vs. engineer’s estimate
- 0%
- Unit price
- $65,500.00/LS
- Extension
- $65,500.00
- Proposal total
- $974,652
- vs. low bid
- +$240,023
- vs. engineer’s estimate
- +9.2%
- Unit price
- $80,000.00/LS
- Extension
- $80,000.00
- Proposal total
- $981,238
- vs. low bid
- +$246,609
- vs. engineer’s estimate
- +33.3%
Proposal 6508-80-001 · let Nov 12, 2026 · Potter County, Amarillo District
Line quantity 1 LS · Engineer’s estimate $55,753/LS
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Infratex Construction LLCLOW BID | $8,000.00/LS | $8,000.00 | — | -85.7% | $306,731 | $80,184 (26.14%) left on table |
| 2 | Rear Contractors LLC | $30,000.00/LS | $30,000.00 | +$22,000 | -46.2% | $386,915 | +$80,184 |
| 3 | Premier Contractors LLC | $40,000.00/LS | $40,000.00 | +$32,000 | -28.3% | $485,032 | +$178,301 |
| 4 | 12twelve Road and Bridge LLC | $20,000.00/LS | $20,000.00 | +$12,000 | -64.1% | $488,466 | +$181,735 |
| 5 | Scr Civil Construction, LLC | $45,500.00/LS | $45,500.00 | +$37,500 | -18.4% | $547,310 | +$240,579 |
| 6 | Ti-Zack Concrete, LLC | $13,800.00/LS | $13,800.00 | +$5,800 | -75.2% | $563,794 | +$257,063 |
| 7 | Road Doctors LLC | $50,000.00/LS | $50,000.00 | +$42,000 | -10.3% | $574,214 | +$267,483 |
| 8 | Icos Management, LLC | $59,500.00/LS | $59,500.00 | +$51,500 | +6.7% | $578,045 | +$271,314 |
| 9 | Boen Landscaping & Irrigation, LLC | $60,000.00/LS | $60,000.00 | +$52,000 | +7.6% | $600,851 | +$294,120 |
| 10 | Structural Integrity Group LLC | $62,000.00/LS | $62,000.00 | +$54,000 | +11.2% | $622,169 | +$315,438 |
| 11 | Pathfield Investments LLC | $50,000.00/LS | $50,000.00 | +$42,000 | -10.3% | $627,520 | +$320,789 |
| 12 | Winding Road Construction, Inc. | $63,000.00/LS | $63,000.00 | +$55,000 | +13% | $633,450 | +$326,719 |
| 13 | O. Trevino Construction, LLC | $73,000.00/LS | $73,000.00 | +$65,000 | +30.9% | $732,872 | +$426,141 |
| 14 | The Truesdell Corporation | $259,849.00/LS | $259,849.00 | +$251,849 | +366.1% | $844,844 | +$538,113 |
1. Infratex Construction LLC
LOW BID · WINNER- Unit price
- $8,000.00/LS
- Extension
- $8,000.00
- Proposal total
- $306,731
- Money left on the table
- $80,184 (26.14%)
- vs. engineer’s estimate
- -85.7%
- Unit price
- $30,000.00/LS
- Extension
- $30,000.00
- Proposal total
- $386,915
- vs. low bid
- +$80,184
- vs. engineer’s estimate
- -46.2%
- Unit price
- $40,000.00/LS
- Extension
- $40,000.00
- Proposal total
- $485,032
- vs. low bid
- +$178,301
- vs. engineer’s estimate
- -28.3%
- Unit price
- $20,000.00/LS
- Extension
- $20,000.00
- Proposal total
- $488,466
- vs. low bid
- +$181,735
- vs. engineer’s estimate
- -64.1%
- Unit price
- $45,500.00/LS
- Extension
- $45,500.00
- Proposal total
- $547,310
- vs. low bid
- +$240,579
- vs. engineer’s estimate
- -18.4%
- Unit price
- $13,800.00/LS
- Extension
- $13,800.00
- Proposal total
- $563,794
- vs. low bid
- +$257,063
- vs. engineer’s estimate
- -75.2%
- Unit price
- $50,000.00/LS
- Extension
- $50,000.00
- Proposal total
- $574,214
- vs. low bid
- +$267,483
- vs. engineer’s estimate
- -10.3%
- Unit price
- $59,500.00/LS
- Extension
- $59,500.00
- Proposal total
- $578,045
- vs. low bid
- +$271,314
- vs. engineer’s estimate
- +6.7%
- Unit price
- $60,000.00/LS
- Extension
- $60,000.00
- Proposal total
- $600,851
- vs. low bid
- +$294,120
- vs. engineer’s estimate
- +7.6%
- Unit price
- $62,000.00/LS
- Extension
- $62,000.00
- Proposal total
- $622,169
- vs. low bid
- +$315,438
- vs. engineer’s estimate
- +11.2%
- Unit price
- $50,000.00/LS
- Extension
- $50,000.00
- Proposal total
- $627,520
- vs. low bid
- +$320,789
- vs. engineer’s estimate
- -10.3%
- Unit price
- $63,000.00/LS
- Extension
- $63,000.00
- Proposal total
- $633,450
- vs. low bid
- +$326,719
- vs. engineer’s estimate
- +13%
- Unit price
- $73,000.00/LS
- Extension
- $73,000.00
- Proposal total
- $732,872
- vs. low bid
- +$426,141
- vs. engineer’s estimate
- +30.9%
- Unit price
- $259,849.00/LS
- Extension
- $259,849.00
- Proposal total
- $844,844
- vs. low bid
- +$538,113
- vs. engineer’s estimate
- +366.1%
Proposal 6497-55-001 · let Nov 12, 2026 · Denton County, Dallas District
Line quantity 1 LS · Engineer’s estimate $48,038/LS
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Road Doctors LLCLOW BID | $40,000.00/LS | $40,000.00 | — | -16.7% | $493,320 | $25,748 (5.22%) left on table |
| 2 | Icos Management, LLC | $51,000.00/LS | $51,000.00 | +$11,000 | +6.2% | $519,068 | +$25,748 |
| 3 | Texas Road Construction, LLC | $70,000.00/LS | $70,000.00 | +$30,000 | +45.7% | $567,220 | +$73,900 |
| 4 | Rear Contractors LLC | $50,000.00/LS | $50,000.00 | +$10,000 | +4.1% | $598,798 | +$105,478 |
| 5 | Premier Contractors LLC | $50,000.00/LS | $50,000.00 | +$10,000 | +4.1% | $654,688 | +$161,368 |
| 6 | Jr West Texas Concrete LLC | $56,000.00/LS | $56,000.00 | +$16,000 | +16.6% | $746,209 | +$252,889 |
- LOW BID · WINNER
- Unit price
- $40,000.00/LS
- Extension
- $40,000.00
- Proposal total
- $493,320
- Money left on the table
- $25,748 (5.22%)
- vs. engineer’s estimate
- -16.7%
- Unit price
- $51,000.00/LS
- Extension
- $51,000.00
- Proposal total
- $519,068
- vs. low bid
- +$25,748
- vs. engineer’s estimate
- +6.2%
- Unit price
- $70,000.00/LS
- Extension
- $70,000.00
- Proposal total
- $567,220
- vs. low bid
- +$73,900
- vs. engineer’s estimate
- +45.7%
- Unit price
- $50,000.00/LS
- Extension
- $50,000.00
- Proposal total
- $598,798
- vs. low bid
- +$105,478
- vs. engineer’s estimate
- +4.1%
- Unit price
- $50,000.00/LS
- Extension
- $50,000.00
- Proposal total
- $654,688
- vs. low bid
- +$161,368
- vs. engineer’s estimate
- +4.1%
6. Jr West Texas Concrete LLC
- Unit price
- $56,000.00/LS
- Extension
- $56,000.00
- Proposal total
- $746,209
- vs. low bid
- +$252,889
- vs. engineer’s estimate
- +16.6%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-12 | 6504-61-001 | Potter | Amarillo | 1 | 7 | Ti-Zack Concrete, LLC | $29,375.00 | $60,000.00 |
| 2026-11-12 | 6508-80-001 | Potter | Amarillo | 1 | 14 | Infratex Construction LLC | $8,000.00 | $55,752.50 |
| 2026-11-12 | 6497-55-001 | Denton | Dallas | 1 | 6 | Road Doctors LLC | $40,000.00 | $48,037.50 |
| 2026-11-12 | 6504-77-001 | Dallas | Dallas | 1 | 6 | Garret Shields Infrastructure | $30,000.00 | $31,000.00 |
| 2026-11-10 | 6496-11-001 | Ector | Odessa | 1 | 3 | Scr Civil Construction, LLC | $27,300.00 | $40,000.00 |
| 2026-11-04 | 0007-05-016 | Eastland | Brownwood | 1 | 4 | Northeastern Pavers, LLC | $1,250,000.00 | $741,000.00 |
| 2026-11-04 | 0009-06-056 | Hunt | Paris | 1 | 2 | Cdm Holdings | $750,000.00 | $1,699,790.47 |
| 2026-11-04 | 0016-03-125 | Hays | Austin | 1 | 6 | Bobcat Services, Inc. | $137,273.24 | $151,675.00 |
| 2026-11-04 | 0027-03-077 | Colorado | Yoakum | 1 | 4 | Ronald R. Wagner & Co., LP | $2,469,606.44 | $1,655,000.00 |
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 1 | 4 | Mario Sinacola & Sons Excavating, Inc. | $3,500,000.00 | $3,528,351.49 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 334 | $125,000.00 | $230,000.00 | $229,980.00 | -4.17% |
| Amarillo | 250 | $230,024.78 | $220,000.00 | $222,000.00 | -46.82% |
| Atlanta | 270 | $150,000.00 | $150,045.55 | $145,000.00 | -14.26% |
| Austin | 883 | $53,115.22 | $100,000.00 | $105,672.75 | 0% |
| Beaumont | 418 | $80,000.00 | $95,000.00 | $200,000.00 | -19.69% |
| Brownwood | 278 | $101,500.00 | $115,000.00 | $138,009.29 | -8% |
| Bryan | 524 | $60,000.00 | $91,000.00 | $45,300.00 | -9% |
| Childress | 210 | $205,000.00 | $130,000.00 | $288,347.72 | -33.33% |
| Corpus Christi | 482 | $70,000.00 | $100,000.00 | $102,000.00 | -9.09% |
| Dallas | 1,575 | $94,925.00 | $101,500.00 | $110,000.00 | -38.59% |
| El Paso | 216 | $75,000.00 | $80,000.00 | $65,000.00 | -30.43% |
| Fort Worth | 760 | $100,000.00 | $141,824.93 | $147,444.10 | -18.96% |
| Houston | 1,014 | $122,000.00 | $196,230.97 | $212,000.00 | +31.7% |
| Laredo | 205 | $250,500.00 | $261,264.16 | $270,566.50 | +68.56% |
| Lubbock | 227 | $230,000.00 | $252,750.00 | $245,850.00 | -36.01% |
| Lufkin | 343 | $80,000.00 | $121,000.00 | $250,000.00 | -11.11% |
| Odessa | 372 | $155,000.00 | $180,000.00 | $165,000.00 | -37.93% |
| Paris | 596 | $70,000.00 | $100,000.00 | $81,642.30 | -27.27% |
| Pharr | 394 | $75,000.00 | $125,000.00 | $121,840.00 | -17.52% |
| San Angelo | 198 | $74,493.87 | $77,800.00 | $60,000.00 | -48.13% |
| San Antonio | 767 | $99,500.00 | $150,000.00 | $276,719.09 | +76.47% |
| Tyler | 536 | $94,000.00 | $90,000.00 | $120,352.50 | -59.36% |
| Waco | 404 | $100,000.00 | $150,000.00 | $195,923.88 | -33.33% |
| Wichita Falls | 287 | $205,000.00 | $200,000.00 | $205,969.99 | -36.72% |
| Yoakum | 695 | $104,631.28 | $195,000.00 | $187,500.00 | -15.98% |
Related items
- 500-7002 · Mobilization (Callout) ($100.00/EA)
- 502-7001 · Barricades, Signs AND Traffic Handling ($6,500.00/MO)
- 503-7001 · Portable Changeable Message Sign ($95.00/DAY)
- 503-7002 · Portable Changeable Message Sign ($9,010.00/EA)
- 496-7007 · Remov STR (Pipe) ($21.40/LF)
- 496-7004 · Remov STR (SET) ($450.00/EA)
- 505-7001 · TMA (Stationary) ($236.87/DAY)
- 505-7003 · TMA (Mobile Operation) ($200.00/DAY)
Is your price for item 500-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.