Remov STR (Pipe) (Item 496-7007): TxDOT Unit Price History
2,189 bids · 360 bid lines · Nov 6, 2024 to Nov 10, 2026 · unit of measure LF
TxDOT 496-7007 · REMOV STR (PIPE) · Unit: LF
- Low bid
- $20.00/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $21.40/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $20.00/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -4.37%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 10, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 496-7007 (Remov STR (Pipe)) is measured in LF. Between Nov 6, 2024 and Nov 10, 2026, contractors entered 2,189 bids for it on 360 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,165 bids was $21.40 per LF, and the winning low bidders priced it at a weighted median of $20.00 per LF.
Winning unit prices sat close to TxDOT's own engineer's estimate ($20.00 per LF), within two percent.
By calendar year, the median bid moved from $26.98 in 2025 (1,049 bids) to $27.17 in 2026 (1,072 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $18.22 and $45.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 4.37%.
Quantity matters for this item. Lines of 2 to 143 LF had a weighted median of $33.10, while lines above 786 LF had $22.00, a 34% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 355 lines where both a winning and a second-place bid were published, the median winning unit price was $24.00 against $25.00 from the second-lowest bidder, a median gap of 1.19% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 21 TxDOT districts with at least ten bids, Wichita Falls had the lowest weighted median ($10.80) and Amarillo the highest ($50.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 10, 2026 in Ector County, where Scr Civil Construction, LLC was the low bidder at $150.00 per LF for 10 LF against an estimate of $80.00.
6 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 496-7004 Remov STR (SET) (weighted median $450.00 per EA); 500-7001 Mobilization (weighted median $128,675.16 per LS); 500-7002 Mobilization (Callout) (weighted median $100.00 per EA); 502-7001 Barricades, Signs AND Traffic Handling (weighted median $6,500.00 per MO).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 68 | 11 | $34.80 | $29.50 | $31.45 | $20.00 | $50.00 |
| 2025 | 1,049 | 181 | $26.14 | $22.00 | $26.98 | $17.50 | $50.00 |
| 2026 | 1,072 | 168 | $26.92 | $23.06 | $27.17 | $18.22 | $45.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 2–143 | 730 | $46.61 | $33.10 | $22.33–$59.87 |
| Medium | 145–781 | 732 | $32.85 | $25.00 | $18.00–$44.73 |
| Large | 786–50,973 | 727 | $25.71 | $22.00 | $12.97–$31.69 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $24.00
- Median second-low unit price
- $25.00
- Median engineer’s estimate
- $25.00
- Median gap, second vs. low
- +1.19%
355 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6496-11-001 · let Nov 10, 2026 · Ector County, Odessa District
Line quantity 10 LF · Engineer’s estimate $80.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Scr Civil Construction, LLCLOW BID | $150.00/LF | $1,500.00 | — | +87.5% | $274,692 | $13,868 (5.05%) left on table |
| 2 | Rb Contracting, LLC | $145.00/LF | $1,450.00 | -$50.00 | +81.3% | $288,560 | +$13,868 |
| 3 | Scott Tucker Construction Company, LLC | $241.00/LF | $2,410.00 | +$910.00 | +201.3% | $288,914 | +$14,222 |
1. Scr Civil Construction, LLC
LOW BID · WINNER- Unit price
- $150.00/LF
- Extension
- $1,500.00
- Proposal total
- $274,692
- Money left on the table
- $13,868 (5.05%)
- vs. engineer’s estimate
- +87.5%
- Unit price
- $145.00/LF
- Extension
- $1,450.00
- Proposal total
- $288,560
- vs. low bid
- +$13,868
- vs. engineer’s estimate
- +81.3%
- Unit price
- $241.00/LF
- Extension
- $2,410.00
- Proposal total
- $288,914
- vs. low bid
- +$14,222
- vs. engineer’s estimate
- +201.3%
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 1,650 LF · Engineer’s estimate $20.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $35.00/LF | $57,750.00 | — | +75% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $40.00/LF | $66,000.00 | +$8,250 | +100% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $12.50/LF | $20,625.00 | -$37,125 | -37.5% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $19.50/LF | $32,175.00 | -$25,575 | -2.5% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $35.00/LF
- Extension
- $57,750.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- +75%
- Unit price
- $40.00/LF
- Extension
- $66,000.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- +100%
3. Tiseo Paving Company, LLC
- Unit price
- $12.50/LF
- Extension
- $20,625.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -37.5%
4. Harper Brothers Construction LLC
- Unit price
- $19.50/LF
- Extension
- $32,175.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -2.5%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 2,933 LF · Engineer’s estimate $20.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $43.00/LF | $126,119.00 | — | +115% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $20.75/LF | $60,859.75 | -$65,259 | +3.8% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $56.00/LF | $164,248.00 | +$38,129 | +180% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $21.14/LF | $62,003.62 | -$64,115 | +5.7% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $26.10/LF | $76,551.30 | -$49,568 | +30.5% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $27.08/LF | $79,425.64 | -$46,693 | +35.4% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $43.00/LF
- Extension
- $126,119.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- +115%
2. Rpm Xconstruction, LLC
- Unit price
- $20.75/LF
- Extension
- $60,859.75
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +3.8%
- Unit price
- $56.00/LF
- Extension
- $164,248.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- +180%
4. Webber, LLC
- Unit price
- $21.14/LF
- Extension
- $62,003.62
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +5.7%
5. Sema Construction, Inc.
- Unit price
- $26.10/LF
- Extension
- $76,551.30
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +30.5%
6. Zachry Construction Corporation
- Unit price
- $27.08/LF
- Extension
- $79,425.64
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +35.4%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-10 | 6496-11-001 | Ector | Odessa | 10 | 3 | Scr Civil Construction, LLC | $150.00 | $80.00 |
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 1,650 | 4 | Mario Sinacola & Sons Excavating, Inc. | $35.00 | $20.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 2,933 | 6 | Indus Road & Bridge, Inc. | $43.00 | $20.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 425 | 12 | Fluor Enterprises, Inc. | $54.00 | $32.00 |
| 2026-11-04 | 0353-01-031 | Wise | Fort Worth | 37 | 7 | Xit Paving and Construction Inc. | $40.00 | $49.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 2,937 | 9 | Highway 19 Construction LLC | $20.00 | $5.00 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 40 | 5 | J E Construction Services, LLC | $26.00 | $20.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 21,449 | 6 | Austin Bridge & Road Services, LP | $60.97 | $11.25 |
| 2026-11-03 | 3330-01-011 | McLennan | Waco | 6 | 9 | The Levy Company, LLC | $341.57 | $23.00 |
| 2026-10-13 | 6505-28-001 | Anderson | Tyler | 172 | 7 | Icos Management, LLC | $12.00 | $35.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 50 | $15.00 | $20.00 | $25.00 | -12% |
| Amarillo | 71 | $34.15 | $50.00 | $75.00 | +85.48% |
| Atlanta | 117 | $20.00 | $16.00 | $20.00 | +5% |
| Austin | 175 | $60.97 | $38.35 | $11.25 | -15% |
| Beaumont | 43 | $15.00 | $45.00 | $30.00 | -23.69% |
| Brownwood | 38 | $40.00 | $40.00 | $28.00 | — |
| Bryan | 138 | $20.00 | $35.00 | $22.40 | +1.3% |
| Childress | 3 | $65.00 | $65.00 | $35.00 | — |
| Corpus Christi | 48 | $20.00 | $17.00 | $25.00 | +47.73% |
| Dallas | 403 | $13.50 | $25.00 | $21.50 | -6.49% |
| El Paso | 8 | $28.00 | $29.00 | $29.00 | — |
| Fort Worth | 102 | $46.00 | $25.50 | $30.00 | +49.26% |
| Houston | 176 | $20.00 | $25.20 | $30.00 | -37.8% |
| Laredo | 46 | $43.40 | $28.67 | $14.00 | -16.72% |
| Lubbock | 5 | $45.15 | $40.50 | $50.00 | — |
| Lufkin | 14 | $26.00 | $31.20 | $18.00 | — |
| Odessa | 65 | $16.50 | $30.78 | $24.00 | -21.43% |
| Paris | 154 | $17.00 | $17.00 | $8.00 | -20% |
| Pharr | 130 | $10.00 | $13.10 | $20.00 | -18.18% |
| San Antonio | 142 | $27.00 | $26.59 | $20.05 | +6.28% |
| Tyler | 48 | $60.00 | $21.50 | $40.00 | -50.6% |
| Waco | 124 | $17.50 | $20.00 | $12.00 | 0% |
| Wichita Falls | 73 | $10.80 | $10.80 | $19.86 | +12.82% |
| Yoakum | 16 | $20.00 | $42.25 | $25.00 | — |
Related items
- 496-7004 · Remov STR (SET) ($450.00/EA)
- 500-7001 · Mobilization ($128,675.16/LS)
- 500-7002 · Mobilization (Callout) ($100.00/EA)
- 502-7001 · Barricades, Signs AND Traffic Handling ($6,500.00/MO)
- 503-7001 · Portable Changeable Message Sign ($95.00/DAY)
- 503-7002 · Portable Changeable Message Sign ($9,010.00/EA)
- 505-7001 · TMA (Stationary) ($236.87/DAY)
- 505-7003 · TMA (Mobile Operation) ($200.00/DAY)
Is your price for item 496-7007 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.