Mobilization (Callout) (Item 500-7002): TxDOT Unit Price History
3,081 bids · 740 bid lines · Nov 6, 2024 to Nov 19, 2026 · unit of measure EA
TxDOT 500-7002 · MOBILIZATION (CALLOUT) · Unit: EA
- Low bid
- $1.00/EA
- Quantity-weighted median of winning unit prices
- Weighted median
- $100.00/EA
- Quantity-weighted median of every bid
- Engineer’s estimate
- $350.00/EA
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- +60%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 19, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 500-7002 (Mobilization (Callout)) is measured in EA. Between Nov 6, 2024 and Nov 19, 2026, contractors entered 3,081 bids for it on 740 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,485 bids was $100.00 per EA, and the winning low bidders priced it at a weighted median of $1.00 per EA.
TxDOT's engineer's estimate for the same lines had a weighted median of $350.00 per EA, so winning bids came in 99.7% below the estimate.
By calendar year, the median bid moved from $500.00 in 2025 (1,635 bids) to $750.00 in 2026 (1,291 bids), up 50.0%. The middle half of 2026 bids fell between $1.00 and $2,659.00.
Comparing the last 12 months with the 12 months before, the median unit price rose 60%.
Quantity matters for this item. Lines of 1 to 6 EA had a weighted median of $1,000.00, while lines above 14 EA had $9.98, a 99% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 686 lines where both a winning and a second-place bid were published, the median winning unit price was $100.00 against $500.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 22 TxDOT districts with at least ten bids, Abilene had the lowest weighted median ($1.00) and Corpus Christi the highest ($1,528.65). The busiest district for this item was Houston.
The most recent letting with this item was on Nov 19, 2026 in Lamar County, where Austin Barricade Company, L.L.C. was the low bidder at $1.00 per EA for 14 EA against an estimate of $400.00.
52 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 500-7001 Mobilization (weighted median $128,675.16 per LS); 502-7001 Barricades, Signs AND Traffic Handling (weighted median $6,500.00 per MO); 503-7001 Portable Changeable Message Sign (weighted median $95.00 per DAY); 503-7002 Portable Changeable Message Sign (weighted median $9,010.00 per EA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 155 | 40 | $1,200.99 | $600.00 | $300.00 | $1.00 | $1,925.00 |
| 2025 | 1,635 | 376 | $1,043.64 | $1.00 | $500.00 | $1.00 | $2,984.00 |
| 2026 | 1,291 | 326 | $1,213.04 | $100.00 | $750.00 | $1.00 | $2,659.00 |
Quantity bands
| Band | Quantity (EA) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–6 | 1,151 | $5,073.17 | $1,000.00 | $1.00–$5,000.00 |
| Medium | 7–13 | 923 | $3,284.09 | $750.00 | $1.00–$3,000.00 |
| Large | 14–2,200 | 1,007 | $550.75 | $9.98 | $1.00–$1,000.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $100.00
- Median second-low unit price
- $500.00
- Median engineer’s estimate
- $1,000.00
- Median gap, second vs. low
- +0%
686 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 6510-75-001 · let Nov 19, 2026 · Ector County, Odessa District
Line quantity 6 EA · Engineer’s estimate $500.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Relmco, Inc.LOW BID | $2,500.00/EA | $15,000.00 | — | +400% | $669,750 | $33,975 (5.07%) left on table |
| 2 | Scr Civil Construction, LLC | $50.00/EA | $300.00 | -$14,700 | -90% | $703,725 | +$33,975 |
| 3 | Premier Contractors LLC | $1.00/EA | $6.00 | -$14,994 | -99.8% | $721,231 | +$51,481 |
| 4 | Scott Tucker Construction Company, LLC | $9,000.00/EA | $54,000.00 | +$39,000 | +1,700% | $912,950 | +$243,200 |
1. Relmco, Inc.
LOW BID · WINNER- Unit price
- $2,500.00/EA
- Extension
- $15,000.00
- Proposal total
- $669,750
- Money left on the table
- $33,975 (5.07%)
- vs. engineer’s estimate
- +400%
- Unit price
- $50.00/EA
- Extension
- $300.00
- Proposal total
- $703,725
- vs. low bid
- +$33,975
- vs. engineer’s estimate
- -90%
- Unit price
- $1.00/EA
- Extension
- $6.00
- Proposal total
- $721,231
- vs. low bid
- +$51,481
- vs. engineer’s estimate
- -99.8%
- Unit price
- $9,000.00/EA
- Extension
- $54,000.00
- Proposal total
- $912,950
- vs. low bid
- +$243,200
- vs. engineer’s estimate
- +1,700%
Proposal 6506-50-001 · let Nov 17, 2026 · Bosque County, Waco District
Line quantity 6 EA · Engineer’s estimate $250.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | JascoLOW BID | $1.00/EA | $6.00 | — | -99.6% | $261,287 | $24,478 (9.37%) left on table |
| 2 | Boen Landscaping & Irrigation, LLC | $500.00/EA | $3,000.00 | +$2,994 | +100% | $285,766 | +$24,478 |
| 3 | T&l Cleaning Services LLC | $1.00/EA | $6.00 | $0.000 | -99.6% | $288,947 | +$27,660 |
| 4 | Marlane Construction, LLC | $1.00/EA | $6.00 | $0.000 | -99.6% | $300,920 | +$39,632 |
| 5 | Abescape Landscaping, LLC | $1.00/EA | $6.00 | $0.000 | -99.6% | $357,010 | +$95,722 |
| 6 | Central North Construction, LLC | $500.00/EA | $3,000.00 | +$2,994 | +100% | $403,896 | +$142,608 |
| 7 | Yellowstone Landscape - Central, Inc. | $2,659.00/EA | $15,954.00 | +$15,948 | +963.6% | $634,626 | +$373,339 |
1. Jasco
LOW BID · WINNER- Unit price
- $1.00/EA
- Extension
- $6.00
- Proposal total
- $261,287
- Money left on the table
- $24,478 (9.37%)
- vs. engineer’s estimate
- -99.6%
- Unit price
- $500.00/EA
- Extension
- $3,000.00
- Proposal total
- $285,766
- vs. low bid
- +$24,478
- vs. engineer’s estimate
- +100%
- Unit price
- $1.00/EA
- Extension
- $6.00
- Proposal total
- $288,947
- vs. low bid
- +$27,660
- vs. engineer’s estimate
- -99.6%
- Unit price
- $1.00/EA
- Extension
- $6.00
- Proposal total
- $300,920
- vs. low bid
- +$39,632
- vs. engineer’s estimate
- -99.6%
- Unit price
- $1.00/EA
- Extension
- $6.00
- Proposal total
- $357,010
- vs. low bid
- +$95,722
- vs. engineer’s estimate
- -99.6%
- Unit price
- $500.00/EA
- Extension
- $3,000.00
- Proposal total
- $403,896
- vs. low bid
- +$142,608
- vs. engineer’s estimate
- +100%
- Unit price
- $2,659.00/EA
- Extension
- $15,954.00
- Proposal total
- $634,626
- vs. low bid
- +$373,339
- vs. engineer’s estimate
- +963.6%
Proposal 6506-52-001 · let Nov 17, 2026 · Coryell County, Waco District
Line quantity 4 EA · Engineer’s estimate $250.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | JascoLOW BID | $1.00/EA | $4.00 | — | -99.6% | $254,153 | $12,683 (4.99%) left on table |
| 2 | Boen Landscaping & Irrigation, LLC | $1,500.00/EA | $6,000.00 | +$5,996 | +500% | $266,837 | +$12,683 |
| 3 | T&l Cleaning Services LLC | $1.00/EA | $4.00 | $0.000 | -99.6% | $274,622 | +$20,469 |
| 4 | Marlane Construction, LLC | $1.00/EA | $4.00 | $0.000 | -99.6% | $286,767 | +$32,614 |
| 5 | Abescape Landscaping, LLC | $1.00/EA | $4.00 | $0.000 | -99.6% | $335,669 | +$81,516 |
| 6 | Central North Construction, LLC | $500.00/EA | $2,000.00 | +$1,996 | +100% | $380,910 | +$126,756 |
| 7 | A M Fabrication Inc. | $1.00/EA | $4.00 | $0.000 | -99.6% | $488,447 | +$234,294 |
| 8 | Yellowstone Landscape - Central, Inc. | $2,659.00/EA | $10,636.00 | +$10,632 | +963.6% | $583,982 | +$329,828 |
1. Jasco
LOW BID · WINNER- Unit price
- $1.00/EA
- Extension
- $4.00
- Proposal total
- $254,153
- Money left on the table
- $12,683 (4.99%)
- vs. engineer’s estimate
- -99.6%
- Unit price
- $1,500.00/EA
- Extension
- $6,000.00
- Proposal total
- $266,837
- vs. low bid
- +$12,683
- vs. engineer’s estimate
- +500%
- Unit price
- $1.00/EA
- Extension
- $4.00
- Proposal total
- $274,622
- vs. low bid
- +$20,469
- vs. engineer’s estimate
- -99.6%
- Unit price
- $1.00/EA
- Extension
- $4.00
- Proposal total
- $286,767
- vs. low bid
- +$32,614
- vs. engineer’s estimate
- -99.6%
- Unit price
- $1.00/EA
- Extension
- $4.00
- Proposal total
- $335,669
- vs. low bid
- +$81,516
- vs. engineer’s estimate
- -99.6%
- Unit price
- $500.00/EA
- Extension
- $2,000.00
- Proposal total
- $380,910
- vs. low bid
- +$126,756
- vs. engineer’s estimate
- +100%
7. A M Fabrication Inc.
- Unit price
- $1.00/EA
- Extension
- $4.00
- Proposal total
- $488,447
- vs. low bid
- +$234,294
- vs. engineer’s estimate
- -99.6%
- Unit price
- $2,659.00/EA
- Extension
- $10,636.00
- Proposal total
- $583,982
- vs. low bid
- +$329,828
- vs. engineer’s estimate
- +963.6%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-19 | 6510-23-001 | Lamar | Paris | 14 | 2 | Austin Barricade Company, L.L.C. | $1.00 | $400.00 |
| 2026-11-19 | 6510-75-001 | Ector | Odessa | 6 | 4 | Relmco, Inc. | $2,500.00 | $500.00 |
| 2026-11-18 | 6510-96-001 | Brazos | Bryan | 6 | 2 | Anthony Services | $1.00 | $1,000.00 |
| 2026-11-17 | 6506-50-001 | Bosque | Waco | 6 | 7 | Jasco | $1.00 | $250.00 |
| 2026-11-17 | 6506-52-001 | Coryell | Waco | 4 | 8 | Jasco | $1.00 | $250.00 |
| 2026-11-17 | 6508-25-001 | Jefferson | Beaumont | 40 | 7 | Ace Contractors, Inc. | $1,000.00 | $1,350.00 |
| 2026-11-17 | 6508-77-001 | Liberty | Beaumont | 20 | 9 | L & M Mowing Contractors, LLC | $1.00 | $1,400.00 |
| 2026-11-17 | 6508-79-001 | Jasper | Beaumont | 30 | 8 | Ace Contractors, Inc. | $1,000.00 | $1,350.00 |
| 2026-11-17 | 6510-61-001 | Brazos | Bryan | 4 | 9 | Ortega's Lawn and Landscaping, LLC | $5,000.00 | $400.00 |
| 2026-11-12 | 6504-57-001 | Dallas | Dallas | 75 | 5 | Highway Intelligent Traffic Solutions, LLC | $1,084.07 | $2,000.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 46 | $1.00 | $1.00 | $720.00 | -99.99% |
| Amarillo | 34 | $1.00 | $1.00 | $2,000.00 | 0% |
| Atlanta | 112 | $50.00 | $1,200.00 | $550.00 | +100% |
| Austin | 80 | $1.00 | $1.00 | $360.00 | +249900% |
| Beaumont | 119 | $200.00 | $800.00 | $1,000.00 | +230.03% |
| Brownwood | 36 | $1.00 | $100.00 | $100.00 | +33.33% |
| Bryan | 253 | $1.00 | $537.00 | $1,000.00 | +2.56% |
| Childress | 28 | $1.00 | $500.00 | $250.00 | — |
| Corpus Christi | 46 | $500.00 | $1,528.65 | $6,230.00 | +610.33% |
| Dallas | 320 | $100.00 | $75.00 | $290.00 | +100% |
| El Paso | 7 | $1.00 | $6,500.00 | $5,000.00 | — |
| Fort Worth | 282 | $1,000.00 | $1,000.00 | $1,000.00 | 0% |
| Houston | 425 | $50.00 | $250.00 | $490.00 | -25.33% |
| Lubbock | 87 | $1,000.00 | $1,000.00 | $1,000.00 | +89900% |
| Lufkin | 261 | $100.00 | $500.00 | $1,000.00 | +114.29% |
| Odessa | 93 | $1,000.00 | $1.00 | $500.00 | -77.5% |
| Paris | 234 | $1.00 | $1.00 | $534.00 | -99% |
| Pharr | 3 | $7,500.00 | $7,500.00 | $10,516.67 | — |
| San Angelo | 64 | $1.00 | $500.00 | $250.00 | +400% |
| San Antonio | 105 | $1.00 | $100.00 | $100.00 | +549900% |
| Tyler | 109 | $1,000.00 | $1,500.00 | $1,000.00 | +5.26% |
| Waco | 261 | $10.00 | $100.00 | $262.00 | +45% |
| Wichita Falls | 14 | $1.00 | $1.00 | $1,500.00 | — |
| Yoakum | 51 | $100.00 | $100.00 | $1,200.00 | -72.34% |
Related items
- 500-7001 · Mobilization ($128,675.16/LS)
- 502-7001 · Barricades, Signs AND Traffic Handling ($6,500.00/MO)
- 503-7001 · Portable Changeable Message Sign ($95.00/DAY)
- 503-7002 · Portable Changeable Message Sign ($9,010.00/EA)
- 496-7007 · Remov STR (Pipe) ($21.40/LF)
- 496-7004 · Remov STR (SET) ($450.00/EA)
- 505-7001 · TMA (Stationary) ($236.87/DAY)
- 505-7003 · TMA (Mobile Operation) ($200.00/DAY)
Is your price for item 500-7002 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.