Relocate SM RD SN Sup&am TY 10BWG (Item 644-7065): TxDOT Unit Price History
1,058 bids · 180 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure EA
TxDOT 644-7065 · RELOCATE SM RD SN SUP&AM TY 10BWG · Unit: EA
- Low bid
- $547.30/EA
- Quantity-weighted median of winning unit prices
- Weighted median
- $642.60/EA
- Quantity-weighted median of every bid
- Engineer’s estimate
- $610.00/EA
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -7.14%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 644-7065 (Relocate SM RD SN Sup&am TY 10BWG) is measured in EA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,058 bids for it on 180 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 515 bids was $642.60 per EA, and the winning low bidders priced it at a weighted median of $547.30 per EA.
TxDOT's engineer's estimate for the same lines had a weighted median of $610.00 per EA, so winning bids came in 10.3% below the estimate.
By calendar year, the median bid moved from $700.00 in 2025 (550 bids) to $650.00 in 2026 (469 bids), down 7.1%. The middle half of 2026 bids fell between $500.00 and $821.48.
Comparing the last 12 months with the 12 months before, the median unit price fell 7.14%.
Quantity matters for this item. Lines of 1 to 2 EA had a weighted median of $700.00, while lines above 9 EA had $650.00, a 7% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 171 lines where both a winning and a second-place bid were published, the median winning unit price was $635.00 against $685.00 from the second-lowest bidder, a median gap of 10.19% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 21 TxDOT districts with at least ten bids, Waco had the lowest weighted median ($500.00) and Corpus Christi the highest ($1,413.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $635.00 per EA for 4 EA against an estimate of $610.00.
9 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 644-7073 Remove SM RD SN Sup&am (weighted median $100.00 per EA); 644-7001 IN SM RD SN Sup&am TY10BWG(1)SA(P) (weighted median $683.00 per EA); 644-7004 IN SM RD SN Sup&am TY10BWG(1)SA(T) (weighted median $790.00 per EA); 644-7028 IN SM RD SN Sup&am TYS80(1)SA(T) (weighted median $990.00 per EA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 39 | 6 | $757.13 | $750.00 | $750.00 | $575.00 | $1,100.00 |
| 2025 | 550 | 100 | $711.85 | $665.00 | $700.00 | $525.00 | $865.50 |
| 2026 | 469 | 74 | $710.23 | $625.00 | $650.00 | $500.00 | $821.48 |
Quantity bands
| Band | Quantity (EA) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–2 | 366 | $782.61 | $700.00 | $553.39–$873.25 |
| Medium | 3–8 | 348 | $758.35 | $669.00 | $500.00–$889.99 |
| Large | 9–133 | 344 | $700.50 | $650.00 | $506.53–$820.67 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $635.00
- Median second-low unit price
- $685.00
- Median engineer’s estimate
- $666.00
- Median gap, second vs. low
- +10.19%
171 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 4 EA · Engineer’s estimate $610.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $635.00/EA | $2,540.00 | — | +4.1% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $676.28/EA | $2,705.12 | +$165.12 | +10.9% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $528.00/EA | $2,112.00 | -$428.00 | -13.4% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $500.00/EA | $2,000.00 | -$540.00 | -18% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $635.00/EA
- Extension
- $2,540.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- +4.1%
- Unit price
- $676.28/EA
- Extension
- $2,705.12
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- +10.9%
3. Tiseo Paving Company, LLC
- Unit price
- $528.00/EA
- Extension
- $2,112.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -13.4%
4. Harper Brothers Construction LLC
- Unit price
- $500.00/EA
- Extension
- $2,000.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -18%
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 3 EA · Engineer’s estimate $500.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $635.00/EA | $1,905.00 | — | +27% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $591.25/EA | $1,773.75 | -$131.25 | +18.3% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $564.38/EA | $1,693.14 | -$211.86 | +12.9% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $697.00/EA | $2,091.00 | +$186.00 | +39.4% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $605.00/EA | $1,815.00 | -$90.00 | +21% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $720.00/EA | $2,160.00 | +$255.00 | +44% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $311.05/EA | $933.15 | -$971.85 | -37.8% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $538.00/EA | $1,614.00 | -$291.00 | +7.6% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $750.00/EA | $2,250.00 | +$345.00 | +50% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $635.00/EA
- Extension
- $1,905.00
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- +27%
2. Stx Civil
- Unit price
- $591.25/EA
- Extension
- $1,773.75
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- +18.3%
3. Rucoba & Maya Construction, LLC
- Unit price
- $564.38/EA
- Extension
- $1,693.14
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- +12.9%
4. Myers Concrete Construction, LP
- Unit price
- $697.00/EA
- Extension
- $2,091.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +39.4%
- Unit price
- $605.00/EA
- Extension
- $1,815.00
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- +21%
- Unit price
- $720.00/EA
- Extension
- $2,160.00
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- +44%
7. Ratliff Hardscape, Ltd.
- Unit price
- $311.05/EA
- Extension
- $933.15
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- -37.8%
- Unit price
- $538.00/EA
- Extension
- $1,614.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- +7.6%
- Unit price
- $750.00/EA
- Extension
- $2,250.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +50%
Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District
Line quantity 29 EA · Engineer’s estimate $600.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Austin Bridge & Road Services, LPLOW BID | $350.00/EA | $10,150.00 | — | -41.7% | $412,233,374 | $3,506,193 (0.85%) left on table |
| 2 | Pulice Construction, Inc. | $520.17/EA | $15,084.93 | +$4,935 | -13.3% | $415,739,567 | +$3,506,193 |
| 3 | Fluor Enterprises, Inc. | $386.22/EA | $11,200.38 | +$1,050 | -35.6% | $473,353,333 | +$61,119,959 |
| 4 | Harper Brothers Construction LLC | $630.00/EA | $18,270.00 | +$8,120 | +5% | $477,550,553 | +$65,317,180 |
| 5 | Webber, LLC | $350.00/EA | $10,150.00 | $0.000 | -41.7% | $477,564,067 | +$65,330,694 |
| 6 | Balfour Beatty Infrastructure, Inc. | $350.00/EA | $10,150.00 | $0.000 | -41.7% | $492,134,823 | +$79,901,450 |
1. Austin Bridge & Road Services, LP
LOW BID · WINNER- Unit price
- $350.00/EA
- Extension
- $10,150.00
- Proposal total
- $412,233,374
- Money left on the table
- $3,506,193 (0.85%)
- vs. engineer’s estimate
- -41.7%
2. Pulice Construction, Inc.
- Unit price
- $520.17/EA
- Extension
- $15,084.93
- Proposal total
- $415,739,567
- vs. low bid
- +$3,506,193
- vs. engineer’s estimate
- -13.3%
3. Fluor Enterprises, Inc.
- Unit price
- $386.22/EA
- Extension
- $11,200.38
- Proposal total
- $473,353,333
- vs. low bid
- +$61,119,959
- vs. engineer’s estimate
- -35.6%
4. Harper Brothers Construction LLC
- Unit price
- $630.00/EA
- Extension
- $18,270.00
- Proposal total
- $477,550,553
- vs. low bid
- +$65,317,180
- vs. engineer’s estimate
- +5%
5. Webber, LLC
- Unit price
- $350.00/EA
- Extension
- $10,150.00
- Proposal total
- $477,564,067
- vs. low bid
- +$65,330,694
- vs. engineer’s estimate
- -41.7%
6. Balfour Beatty Infrastructure, Inc.
- Unit price
- $350.00/EA
- Extension
- $10,150.00
- Proposal total
- $492,134,823
- vs. low bid
- +$79,901,450
- vs. engineer’s estimate
- -41.7%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 4 | 4 | Mario Sinacola & Sons Excavating, Inc. | $635.00 | $610.00 |
| 2026-11-04 | 0285-03-066 | Hays | Austin | 3 | 9 | Lone Star Sitework, LLC | $635.00 | $500.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 29 | 6 | Austin Bridge & Road Services, LP | $350.00 | $600.00 |
| 2026-11-03 | 0619-03-068 | Collin | Dallas | 1 | 13 | Rcr Telecon LLC | $860.00 | $800.00 |
| 2026-10-15 | 6503-97-001 | McLennan | Waco | 3 | 7 | Rhino Equity, LLC | $500.00 | $550.00 |
| 2026-10-06 | 0168-03-040 | Parmer | Lubbock | 5 | 6 | Gratiot Construction, Ltd. | $675.00 | $300.00 |
| 2026-10-06 | 2502-01-024 | Bell | Waco | 12 | 6 | Big Creek Construction, Ltd. | $500.00 | $800.00 |
| 2026-09-03 | 0051-09-127 | Galveston | Houston | 4 | 7 | Castillo Aranda LLC | $500.00 | $750.00 |
| 2026-09-03 | 0068-05-039 | Dawson | Lubbock | 20 | 5 | Gratiot Construction, Ltd. | $930.00 | $1,200.00 |
| 2026-09-03 | 0143-10-058 | Victoria | Yoakum | 30 | 7 | 3lw Civil LLC | $547.30 | $600.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 19 | $550.00 | $750.00 | $700.00 | — |
| Amarillo | 59 | $368.92 | $763.60 | $400.00 | -0.23% |
| Atlanta | 5 | $575.00 | $550.00 | $620.00 | — |
| Austin | 129 | $475.00 | $508.48 | $600.00 | -16.3% |
| Beaumont | 11 | $517.00 | $517.00 | $550.00 | — |
| Bryan | 56 | $468.69 | $530.00 | $740.00 | — |
| Childress | 16 | $1,100.00 | $829.54 | $752.00 | — |
| Corpus Christi | 16 | $765.00 | $1,413.00 | $2,000.00 | — |
| Dallas | 161 | $500.00 | $650.00 | $600.00 | -5.06% |
| El Paso | 19 | $668.25 | $1,284.00 | $700.00 | — |
| Fort Worth | 34 | $510.00 | $595.00 | $550.00 | -19.67% |
| Houston | 57 | $2,215.05 | $506.00 | $875.00 | -15.43% |
| Laredo | 8 | $725.00 | $725.00 | $1,000.00 | — |
| Lubbock | 34 | $930.00 | $730.00 | $1,200.00 | -19.02% |
| Lufkin | 15 | $700.00 | $570.00 | $815.00 | — |
| Odessa | 41 | $312.00 | $606.96 | $625.00 | -10.18% |
| Paris | 118 | $650.00 | $600.00 | $450.00 | -14.33% |
| Pharr | 14 | $900.00 | $1,080.00 | $500.00 | — |
| San Angelo | 7 | $275.00 | $1,017.75 | $600.00 | — |
| San Antonio | 61 | $550.00 | $590.00 | $500.00 | 0% |
| Tyler | 21 | $585.00 | $585.00 | $760.00 | — |
| Waco | 58 | $500.00 | $500.00 | $800.00 | -19.23% |
| Wichita Falls | 26 | $322.60 | $542.77 | $740.00 | — |
| Yoakum | 73 | $589.00 | $650.00 | $700.00 | +23.35% |
Related items
- 644-7073 · Remove SM RD SN Sup&am ($100.00/EA)
- 644-7001 · IN SM RD SN Sup&am TY10BWG(1)SA(P) ($683.00/EA)
- 644-7004 · IN SM RD SN Sup&am TY10BWG(1)SA(T) ($790.00/EA)
- 644-7028 · IN SM RD SN Sup&am TYS80(1)SA(T) ($990.00/EA)
- 644-7031 · IN SM RD SN Sup&am TYS80(1)SA(U) ($1,203.60/EA)
- 644-7007 · IN SM RD SN Sup&am TY10BWG(1)SA(U) ($1,000.00/EA)
- 636-7001 · Aluminum Signs (TY A) ($45.00/SF)
- 658-7019 · Instl DEL Assm (D-SW)SZ 1(BRF)GF2(BI) ($25.00/EA)
Is your price for item 644-7065 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.