Aluminum Signs (TY A) (Item 636-7001): TxDOT Unit Price History
1,494 bids · 285 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure SF
TxDOT 636-7001 · ALUMINUM SIGNS (TY A) · Unit: SF
- Low bid
- $45.00/SF
- Quantity-weighted median of winning unit prices
- Weighted median
- $45.00/SF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $35.00/SF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- +5.26%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 636-7001 (Aluminum Signs (TY A)) is measured in SF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,494 bids for it on 285 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 834 bids was $45.00 per SF, and the winning low bidders priced it at a weighted median of $45.00 per SF.
TxDOT's engineer's estimate for the same lines had a weighted median of $35.00 per SF, so winning bids came in 28.6% above the estimate.
By calendar year, the median bid moved from $39.00 in 2025 (674 bids) to $40.00 in 2026 (789 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $32.00 and $51.00.
Comparing the last 12 months with the 12 months before, the median unit price rose 5.26%.
Quantity matters for this item. Lines of 1.33 to 40 SF had a weighted median of $38.50, while lines above 169 SF had $41.73; larger lines were priced higher here, which is unusual and worth checking against the individual lettings.
Across 275 lines where both a winning and a second-place bid were published, the median winning unit price was $39.10 against $39.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 23 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($30.00) and El Paso the highest ($100.36). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Denton County, where Indus Road & Bridge, Inc. was the low bidder at $55.00 per SF for 138 SF against an estimate of $30.00.
18 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 644-7073 Remove SM RD SN Sup&am (weighted median $100.00 per EA); 644-7001 IN SM RD SN Sup&am TY10BWG(1)SA(P) (weighted median $683.00 per EA); 644-7004 IN SM RD SN Sup&am TY10BWG(1)SA(T) (weighted median $790.00 per EA); 644-7028 IN SM RD SN Sup&am TYS80(1)SA(T) (weighted median $990.00 per EA).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 31 | 6 | $38.78 | $37.75 | $39.00 | $30.75 | $50.00 |
| 2025 | 674 | 140 | $39.46 | $35.00 | $39.00 | $30.00 | $50.00 |
| 2026 | 789 | 139 | $57.02 | $45.00 | $40.00 | $32.00 | $51.00 |
Quantity bands
| Band | Quantity (SF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1.33–40 | 501 | $44.77 | $38.50 | $31.00–$50.00 |
| Medium | 41–168 | 501 | $45.97 | $40.00 | $31.32–$52.00 |
| Large | 169–11,294 | 492 | $50.50 | $41.73 | $30.00–$50.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $39.10
- Median second-low unit price
- $39.00
- Median engineer’s estimate
- $44.00
- Median gap, second vs. low
- +0%
275 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 138 SF · Engineer’s estimate $30.00/SF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $55.00/SF | $7,590.00 | — | +83.3% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $37.00/SF | $5,106.00 | -$2,484 | +23.3% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $53.00/SF | $7,314.00 | -$276.00 | +76.7% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $53.00/SF | $7,314.00 | -$276.00 | +76.7% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $53.00/SF | $7,314.00 | -$276.00 | +76.7% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $55.00/SF | $7,590.00 | $0.000 | +83.3% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $55.00/SF
- Extension
- $7,590.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- +83.3%
2. Rpm Xconstruction, LLC
- Unit price
- $37.00/SF
- Extension
- $5,106.00
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +23.3%
- Unit price
- $53.00/SF
- Extension
- $7,314.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- +76.7%
4. Webber, LLC
- Unit price
- $53.00/SF
- Extension
- $7,314.00
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +76.7%
5. Sema Construction, Inc.
- Unit price
- $53.00/SF
- Extension
- $7,314.00
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +76.7%
6. Zachry Construction Corporation
- Unit price
- $55.00/SF
- Extension
- $7,590.00
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +83.3%
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 54.5 SF · Engineer’s estimate $50.00/SF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $75.50/SF | $4,114.75 | — | +51% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $40.00/SF | $2,180.00 | -$1,935 | -20% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $130.00/SF | $7,085.00 | +$2,970 | +160% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $60.00/SF | $3,270.00 | -$844.75 | +20% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $31.17/SF | $1,698.77 | -$2,416 | -37.7% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $77.00/SF | $4,196.50 | +$81.75 | +54% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $35.00/SF | $1,907.50 | -$2,207 | -30% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $32.75/SF | $1,784.88 | -$2,330 | -34.5% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $64.02/SF | $3,489.09 | -$625.66 | +28% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $34.29/SF | $1,868.81 | -$2,246 | -31.4% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $31.45/SF | $1,714.03 | -$2,401 | -37.1% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $33.00/SF | $1,798.50 | -$2,316 | -34% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $75.50/SF
- Extension
- $4,114.75
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- +51%
- Unit price
- $40.00/SF
- Extension
- $2,180.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- -20%
- Unit price
- $130.00/SF
- Extension
- $7,085.00
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- +160%
- Unit price
- $60.00/SF
- Extension
- $3,270.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- +20%
- Unit price
- $31.17/SF
- Extension
- $1,698.77
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- -37.7%
- Unit price
- $77.00/SF
- Extension
- $4,196.50
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- +54%
- Unit price
- $35.00/SF
- Extension
- $1,907.50
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- -30%
- Unit price
- $32.75/SF
- Extension
- $1,784.88
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- -34.5%
9. Zachry Construction Corporation
- Unit price
- $64.02/SF
- Extension
- $3,489.09
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- +28%
10. Brizo Construction, LLC
- Unit price
- $34.29/SF
- Extension
- $1,868.81
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- -31.4%
- Unit price
- $31.45/SF
- Extension
- $1,714.03
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- -37.1%
- Unit price
- $33.00/SF
- Extension
- $1,798.50
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- -34%
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 10 SF · Engineer’s estimate $45.00/SF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $46.00/SF | $460.00 | — | +2.2% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $27.50/SF | $275.00 | -$185.00 | -38.9% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $31.50/SF | $315.00 | -$145.00 | -30% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $71.00/SF | $710.00 | +$250.00 | +57.8% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $27.50/SF | $275.00 | -$185.00 | -38.9% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $30.00/SF | $300.00 | -$160.00 | -33.3% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $22.42/SF | $224.20 | -$235.80 | -50.2% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $40.00/SF | $400.00 | -$60.00 | -11.1% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $50.00/SF | $500.00 | +$40.00 | +11.1% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $46.00/SF
- Extension
- $460.00
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- +2.2%
2. Stx Civil
- Unit price
- $27.50/SF
- Extension
- $275.00
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- -38.9%
3. Rucoba & Maya Construction, LLC
- Unit price
- $31.50/SF
- Extension
- $315.00
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- -30%
4. Myers Concrete Construction, LP
- Unit price
- $71.00/SF
- Extension
- $710.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +57.8%
- Unit price
- $27.50/SF
- Extension
- $275.00
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- -38.9%
- Unit price
- $30.00/SF
- Extension
- $300.00
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- -33.3%
7. Ratliff Hardscape, Ltd.
- Unit price
- $22.42/SF
- Extension
- $224.20
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- -50.2%
- Unit price
- $40.00/SF
- Extension
- $400.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- -11.1%
- Unit price
- $50.00/SF
- Extension
- $500.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +11.1%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 138 | 6 | Indus Road & Bridge, Inc. | $55.00 | $30.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 54.5 | 12 | Fluor Enterprises, Inc. | $75.50 | $50.00 |
| 2026-11-04 | 0285-03-066 | Hays | Austin | 10 | 9 | Lone Star Sitework, LLC | $46.00 | $45.00 |
| 2026-11-04 | 0353-01-031 | Wise | Fort Worth | 2 | 7 | Xit Paving and Construction Inc. | $58.00 | $85.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 96 | 6 | Austin Bridge & Road Services, LP | $28.00 | $45.00 |
| 2026-11-03 | 3330-01-011 | McLennan | Waco | 21 | 9 | The Levy Company, LLC | $29.43 | $39.00 |
| 2026-10-13 | 6508-18-001 | Harris | Houston | 500 | 2 | Rhino Equity, LLC | $25.00 | $33.04 |
| 2026-10-07 | 0092-02-145 | Dallas | Dallas | 612 | 6 | Sice, Inc. | $43.08 | $30.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 9 | 8 | Hunter Industries, Ltd. | $27.00 | $30.00 |
| 2026-10-07 | 0196-03-288 | Dallas | Dallas | 18 | 9 | Garret Shields Infrastructure | $40.00 | $45.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 15 | $55.00 | $32.96 | $65.00 | — |
| Amarillo | 33 | $44.00 | $44.00 | $40.00 | — |
| Atlanta | 17 | $10.00 | $50.00 | $55.00 | — |
| Austin | 114 | $39.22 | $39.22 | $50.00 | 0% |
| Beaumont | 26 | $50.00 | $40.09 | $63.65 | -12.66% |
| Brownwood | 11 | $117.30 | $46.61 | $50.00 | — |
| Bryan | 65 | $64.00 | $35.35 | $45.00 | -12.5% |
| Corpus Christi | 32 | $28.00 | $60.00 | $35.00 | +122.48% |
| Dallas | 310 | $40.00 | $42.00 | $44.00 | +3.26% |
| El Paso | 21 | $112.00 | $100.36 | $35.00 | — |
| Fort Worth | 93 | $36.00 | $45.00 | $46.00 | +17.16% |
| Houston | 103 | $25.00 | $33.86 | $30.00 | +10.94% |
| Laredo | 30 | $46.00 | $46.00 | $50.00 | — |
| Lubbock | 33 | $28.60 | $35.65 | $44.00 | +34.09% |
| Odessa | 65 | $90.75 | $52.00 | $46.00 | -6.67% |
| Paris | 28 | $35.00 | $35.00 | $55.00 | -8.75% |
| Pharr | 122 | $27.05 | $30.00 | $31.50 | +30.42% |
| San Angelo | 23 | $50.00 | $44.00 | $50.00 | — |
| San Antonio | 139 | $30.26 | $32.00 | $45.00 | -23.29% |
| Tyler | 29 | $70.00 | $55.00 | $38.00 | — |
| Waco | 61 | $84.00 | $30.00 | $80.00 | +28.21% |
| Wichita Falls | 12 | $18.75 | $39.94 | $45.00 | — |
| Yoakum | 112 | $37.50 | $33.00 | $30.00 | 0% |
Related items
- 644-7073 · Remove SM RD SN Sup&am ($100.00/EA)
- 644-7001 · IN SM RD SN Sup&am TY10BWG(1)SA(P) ($683.00/EA)
- 644-7004 · IN SM RD SN Sup&am TY10BWG(1)SA(T) ($790.00/EA)
- 644-7028 · IN SM RD SN Sup&am TYS80(1)SA(T) ($990.00/EA)
- 644-7031 · IN SM RD SN Sup&am TYS80(1)SA(U) ($1,203.60/EA)
- 644-7007 · IN SM RD SN Sup&am TY10BWG(1)SA(U) ($1,000.00/EA)
- 644-7065 · Relocate SM RD SN Sup&am TY 10BWG ($642.60/EA)
- 624-7008 · Ground BOX TY D (162922)W/Apron ($1,613.17/EA)
Is your price for item 636-7001 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.