Refl PAV MRK TY I (W)(Word)(100MIL) (Item 666-7066): TxDOT Unit Price History
1,741 bids · 324 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure EA
TxDOT 666-7066 · REFL PAV MRK TY I (W)(WORD)(100MIL) · Unit: EA
- Low bid
- $175.00/EA
- Quantity-weighted median of winning unit prices
- Weighted median
- $175.00/EA
- Quantity-weighted median of every bid
- Engineer’s estimate
- $200.00/EA
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -16.95%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 666-7066 (Refl PAV MRK TY I (W)(Word)(100MIL)) is measured in EA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,741 bids for it on 324 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,002 bids was $175.00 per EA, and the winning low bidders priced it at a weighted median of $175.00 per EA.
TxDOT's engineer's estimate for the same lines had a weighted median of $200.00 per EA, so winning bids came in 12.5% below the estimate.
By calendar year, the median bid moved from $230.00 in 2025 (729 bids) to $190.00 in 2026 (963 bids), down 17.4%. The middle half of 2026 bids fell between $165.01 and $231.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 16.95%.
Quantity matters for this item. Lines of 1 to 6 EA had a weighted median of $230.00, while lines above 26 EA had $176.77, a 23% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 313 lines where both a winning and a second-place bid were published, the median winning unit price was $205.00 against $200.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 15 TxDOT districts with at least ten bids, Pharr had the lowest weighted median ($130.00) and Odessa the highest ($589.50). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Hays County, where Bobcat Services, Inc. was the low bidder at $210.07 per EA for 33 EA against an estimate of $190.84.
18 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 666-7024 Refl PAV MRK TY I (W)8"(SLD)(100MIL) (weighted median $0.850 per LF); 666-7423 Refl PAV MRK TY I (Y)6"(SLD)(100MIL) (weighted median $0.450 per LF); 666-7036 Refl PAV MRK TY I (W)24"(SLD)(100MIL) (weighted median $7.00 per LF); 666-7411 Refl PAV MRK TY I (W)6"(SLD)(100MIL) (weighted median $0.450 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 49 | 10 | $218.86 | $205.00 | $250.00 | $200.00 | $270.00 |
| 2025 | 729 | 149 | $200.87 | $194.25 | $230.00 | $185.00 | $275.00 |
| 2026 | 963 | 165 | $185.78 | $175.00 | $190.00 | $165.01 | $231.00 |
Quantity bands
| Band | Quantity (EA) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 1–6 | 673 | $253.77 | $230.00 | $195.00–$298.00 |
| Medium | 7–25 | 498 | $225.13 | $200.00 | $175.00–$250.00 |
| Large | 26–1,000 | 570 | $187.58 | $176.77 | $158.00–$214.76 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $205.00
- Median second-low unit price
- $200.00
- Median engineer’s estimate
- $207.76
- Median gap, second vs. low
- +0%
313 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0016-03-125 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 33 EA · Engineer’s estimate $190.84/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Bobcat Services, Inc.LOW BID | $210.07/EA | $6,932.31 | — | +10.1% | $2,797,454 | $386,828 (13.83%) left on table |
| 2 | Hunter Industries, Ltd. | $200.00/EA | $6,600.00 | -$332.31 | +4.8% | $3,184,282 | +$386,828 |
| 3 | Dean Word Company, Ltd. | $215.25/EA | $7,103.25 | +$170.94 | +12.8% | $3,495,937 | +$698,482 |
| 4 | Texas Materials Group, Inc. | $200.00/EA | $6,600.00 | -$332.31 | +4.8% | $3,586,449 | +$788,995 |
| 5 | Lone Star Paving Company | $200.00/EA | $6,600.00 | -$332.31 | +4.8% | $3,801,261 | +$1,003,807 |
| 6 | Clark Construction of Texas, Inc. | $200.00/EA | $6,600.00 | -$332.31 | +4.8% | $3,825,058 | +$1,027,604 |
1. Bobcat Services, Inc.
LOW BID · WINNER- Unit price
- $210.07/EA
- Extension
- $6,932.31
- Proposal total
- $2,797,454
- Money left on the table
- $386,828 (13.83%)
- vs. engineer’s estimate
- +10.1%
- Unit price
- $200.00/EA
- Extension
- $6,600.00
- Proposal total
- $3,184,282
- vs. low bid
- +$386,828
- vs. engineer’s estimate
- +4.8%
- Unit price
- $215.25/EA
- Extension
- $7,103.25
- Proposal total
- $3,495,937
- vs. low bid
- +$698,482
- vs. engineer’s estimate
- +12.8%
- Unit price
- $200.00/EA
- Extension
- $6,600.00
- Proposal total
- $3,586,449
- vs. low bid
- +$788,995
- vs. engineer’s estimate
- +4.8%
- Unit price
- $200.00/EA
- Extension
- $6,600.00
- Proposal total
- $3,801,261
- vs. low bid
- +$1,003,807
- vs. engineer’s estimate
- +4.8%
- Unit price
- $200.00/EA
- Extension
- $6,600.00
- Proposal total
- $3,825,058
- vs. low bid
- +$1,027,604
- vs. engineer’s estimate
- +4.8%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 26 EA · Engineer’s estimate $100.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $158.00/EA | $4,108.00 | — | +58% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $145.00/EA | $3,770.00 | -$338.00 | +45% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $189.01/EA | $4,914.26 | +$806.26 | +89% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $140.00/EA | $3,640.00 | -$468.00 | +40% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $140.00/EA | $3,640.00 | -$468.00 | +40% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $145.29/EA | $3,777.54 | -$330.46 | +45.3% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $158.00/EA
- Extension
- $4,108.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- +58%
2. Rpm Xconstruction, LLC
- Unit price
- $145.00/EA
- Extension
- $3,770.00
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- +45%
- Unit price
- $189.01/EA
- Extension
- $4,914.26
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- +89%
4. Webber, LLC
- Unit price
- $140.00/EA
- Extension
- $3,640.00
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +40%
5. Sema Construction, Inc.
- Unit price
- $140.00/EA
- Extension
- $3,640.00
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +40%
6. Zachry Construction Corporation
- Unit price
- $145.29/EA
- Extension
- $3,777.54
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +45.3%
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 9 EA · Engineer’s estimate $240.00/EA
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $200.00/EA | $1,800.00 | — | -16.7% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $220.00/EA | $1,980.00 | +$180.00 | -8.3% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $210.00/EA | $1,890.00 | +$90.00 | -12.5% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $220.00/EA | $1,980.00 | +$180.00 | -8.3% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $195.00/EA | $1,755.00 | -$45.00 | -18.8% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $200.00/EA | $1,800.00 | $0.000 | -16.7% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $205.00/EA | $1,845.00 | +$45.00 | -14.6% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $210.00/EA | $1,890.00 | +$90.00 | -12.5% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $210.40/EA | $1,893.60 | +$93.60 | -12.3% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $220.00/EA | $1,980.00 | +$180.00 | -8.3% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $196.95/EA | $1,772.55 | -$27.45 | -17.9% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $218.00/EA | $1,962.00 | +$162.00 | -9.2% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $200.00/EA
- Extension
- $1,800.00
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- -16.7%
- Unit price
- $220.00/EA
- Extension
- $1,980.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- -8.3%
- Unit price
- $210.00/EA
- Extension
- $1,890.00
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- -12.5%
- Unit price
- $220.00/EA
- Extension
- $1,980.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- -8.3%
- Unit price
- $195.00/EA
- Extension
- $1,755.00
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- -18.8%
- Unit price
- $200.00/EA
- Extension
- $1,800.00
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- -16.7%
- Unit price
- $205.00/EA
- Extension
- $1,845.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- -14.6%
- Unit price
- $210.00/EA
- Extension
- $1,890.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- -12.5%
9. Zachry Construction Corporation
- Unit price
- $210.40/EA
- Extension
- $1,893.60
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- -12.3%
10. Brizo Construction, LLC
- Unit price
- $220.00/EA
- Extension
- $1,980.00
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- -8.3%
- Unit price
- $196.95/EA
- Extension
- $1,772.55
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- -17.9%
- Unit price
- $218.00/EA
- Extension
- $1,962.00
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- -9.2%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0016-03-125 | Hays | Austin | 33 | 6 | Bobcat Services, Inc. | $210.07 | $190.84 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 26 | 6 | Indus Road & Bridge, Inc. | $158.00 | $100.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 9 | 12 | Fluor Enterprises, Inc. | $200.00 | $240.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 2 | 7 | Big Creek Construction, Ltd. | $220.00 | $200.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 4 | 9 | Highway 19 Construction LLC | $155.00 | $175.00 |
| 2026-11-04 | 6504-98-001 | Tom Green | San Angelo | 7 | 4 | Reece Albert, Inc. | $407.62 | $177.65 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 2 | 8 | Jay Mills Contracting, Incorporated | $280.00 | $160.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 31 | 6 | Austin Bridge & Road Services, LP | $165.00 | $312.00 |
| 2026-11-03 | 0045-09-113 | Lamar | Paris | 43 | 5 | Drake Companies LLC | $242.00 | $180.00 |
| 2026-11-03 | 0901-00-066 | Lamar | Paris | 250 | 4 | Striping Technology, L.P. | $135.00 | $161.83 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Amarillo | 18 | $355.93 | $325.00 | $250.00 | — |
| Austin | 218 | $200.00 | $195.00 | $242.93 | -20% |
| Brownwood | 29 | $150.00 | $175.00 | $225.00 | — |
| Bryan | 56 | $200.00 | $218.00 | $240.00 | -34.33% |
| Childress | 30 | $130.00 | $155.00 | $214.00 | — |
| Corpus Christi | 9 | $300.00 | $222.00 | $225.00 | — |
| Dallas | 479 | $168.00 | $170.50 | $188.50 | -25.19% |
| El Paso | 23 | $205.00 | $230.00 | $200.00 | — |
| Fort Worth | 236 | $154.88 | $166.00 | $175.00 | -9.79% |
| Houston | 118 | $165.00 | $185.00 | $173.00 | -6.29% |
| Laredo | 93 | $160.00 | $168.71 | $235.00 | -30% |
| Odessa | 11 | $642.00 | $589.50 | $287.00 | — |
| Paris | 71 | $135.00 | $180.00 | $161.83 | -2.05% |
| Pharr | 42 | $85.00 | $130.00 | $85.00 | -58.16% |
| San Angelo | 31 | $407.62 | $341.13 | $303.46 | — |
| San Antonio | 268 | $176.00 | $175.00 | $190.00 | -3.24% |
| Tyler | 3 | $200.00 | $200.00 | $236.00 | — |
| Yoakum | 6 | $262.50 | $291.31 | $165.00 | — |
Related items
- 666-7024 · Refl PAV MRK TY I (W)8"(SLD)(100MIL) ($0.850/LF)
- 666-7423 · Refl PAV MRK TY I (Y)6"(SLD)(100MIL) ($0.450/LF)
- 666-7036 · Refl PAV MRK TY I (W)24"(SLD)(100MIL) ($7.00/LF)
- 666-7411 · Refl PAV MRK TY I (W)6"(SLD)(100MIL) ($0.450/LF)
- 666-7408 · Refl PAV MRK TY I (W)6"(BRK)(100MIL) ($0.520/LF)
- 666-7347 · Pavement Sler 6" ($0.190/LF)
- 666-7420 · Refl PAV MRK TY I (Y)6"(BRK)(100MIL) ($0.450/LF)
- 666-7042 · Refl PAV MRK TY I (W)(Arrow)(100MIL) ($150.00/EA)
Is your price for item 666-7066 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.