Block Sodding (Item 162-7002): TxDOT Unit Price History
1,942 bids · 309 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure SY
TxDOT 162-7002 · BLOCK SODDING · Unit: SY
- Low bid
- $3.55/SY
- Quantity-weighted median of winning unit prices
- Weighted median
- $3.50/SY
- Quantity-weighted median of every bid
- Engineer’s estimate
- $3.90/SY
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -12.5%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 162-7002 (Block Sodding) is measured in SY. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,942 bids for it on 309 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,013 bids was $3.50 per SY, and the winning low bidders priced it at a weighted median of $3.55 per SY.
TxDOT's engineer's estimate for the same lines had a weighted median of $3.90 per SY, so winning bids came in 9.0% below the estimate.
By calendar year, the median bid moved from $8.00 in 2025 (885 bids) to $6.76 in 2026 (967 bids), down 15.5%. The middle half of 2026 bids fell between $5.00 and $10.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 12.5%.
Quantity matters for this item. Lines of 3 to 1,052 SY had a weighted median of $9.45, while lines above 4,410 SY had $3.60, a 62% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 292 lines where both a winning and a second-place bid were published, the median winning unit price was $7.00 against $7.00 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 18 TxDOT districts with at least ten bids, Houston had the lowest weighted median ($3.40) and Odessa the highest ($10.00). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $3.81 per SY for 42,500 SY against an estimate of $4.18.
49 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 160-7002 Furn & Place Topsoil (4") (weighted median $1.35 per SY); 164-7005 Broadcast Seed (Temp_Warm) (weighted median $0.150 per SY); 164-7006 Broadcast Seed (Temp_Cool) (weighted median $0.150 per SY); 168-7001 Vegetative Watering (weighted median $7.00 per TGL).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 90 | 14 | $5.72 | $4.00 | $8.65 | $5.49 | $10.97 |
| 2025 | 885 | 152 | $5.23 | $4.25 | $8.00 | $6.00 | $10.25 |
| 2026 | 967 | 143 | $4.02 | $3.50 | $6.76 | $5.00 | $10.00 |
Quantity bands
| Band | Quantity (SY) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 3–1,052 | 656 | $11.36 | $9.45 | $8.00–$20.00 |
| Medium | 1,072–4,361 | 640 | $8.14 | $7.00 | $5.75–$10.00 |
| Large | 4,410–541,321 | 646 | $4.20 | $3.60 | $4.13–$7.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $7.00
- Median second-low unit price
- $7.00
- Median engineer’s estimate
- $8.00
- Median gap, second vs. low
- +0%
292 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 42,500 SY · Engineer’s estimate $4.18/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $3.81/SY | $161,925.00 | — | -8.9% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $4.20/SY | $178,500.00 | +$16,575 | +0.5% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $4.05/SY | $172,125.00 | +$10,200 | -3.1% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $4.00/SY | $170,000.00 | +$8,075 | -4.3% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $3.81/SY
- Extension
- $161,925.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -8.9%
- Unit price
- $4.20/SY
- Extension
- $178,500.00
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- +0.5%
3. Tiseo Paving Company, LLC
- Unit price
- $4.05/SY
- Extension
- $172,125.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- -3.1%
4. Harper Brothers Construction LLC
- Unit price
- $4.00/SY
- Extension
- $170,000.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -4.3%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 165,493 SY · Engineer’s estimate $5.00/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $3.60/SY | $595,774.80 | — | -28% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $3.60/SY | $595,774.80 | $0.000 | -28% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $3.50/SY | $579,225.50 | -$16,549 | -30% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $3.50/SY | $579,225.50 | -$16,549 | -30% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $3.50/SY | $579,225.50 | -$16,549 | -30% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $3.63/SY | $600,739.59 | +$4,965 | -27.4% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $3.60/SY
- Extension
- $595,774.80
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- -28%
2. Rpm Xconstruction, LLC
- Unit price
- $3.60/SY
- Extension
- $595,774.80
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -28%
- Unit price
- $3.50/SY
- Extension
- $579,225.50
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- -30%
4. Webber, LLC
- Unit price
- $3.50/SY
- Extension
- $579,225.50
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- -30%
5. Sema Construction, Inc.
- Unit price
- $3.50/SY
- Extension
- $579,225.50
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- -30%
6. Zachry Construction Corporation
- Unit price
- $3.63/SY
- Extension
- $600,739.59
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- -27.4%
Proposal 0285-03-066 · let Nov 4, 2026 · Hays County, Austin District
Line quantity 59 SY · Engineer’s estimate $10.00/SY
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Lone Star Sitework, LLCLOW BID | $15.50/SY | $914.50 | — | +55% | $950,337 | $133,497 (14.05%) left on table |
| 2 | Stx Civil | $14.85/SY | $876.15 | -$38.35 | +48.5% | $1,083,834 | +$133,497 |
| 3 | Rucoba & Maya Construction, LLC | $40.00/SY | $2,360.00 | +$1,446 | +300% | $1,103,755 | +$153,418 |
| 4 | Myers Concrete Construction, LP | $17.00/SY | $1,003.00 | +$88.50 | +70% | $1,122,792 | +$172,455 |
| 5 | Ti-Zack Concrete, LLC | $22.00/SY | $1,298.00 | +$383.50 | +120% | $1,135,337 | +$185,000 |
| 6 | Centerline Technologies, LLC | $24.50/SY | $1,445.50 | +$531.00 | +145% | $1,199,801 | +$249,464 |
| 7 | Ratliff Hardscape, Ltd. | $58.76/SY | $3,466.84 | +$2,552 | +487.6% | $1,228,710 | +$278,373 |
| 8 | E-Z Bel Construction, LLC | $47.00/SY | $2,773.00 | +$1,859 | +370% | $1,272,000 | +$321,663 |
| 9 | Tight Line Construction, LLC | $50.00/SY | $2,950.00 | +$2,036 | +400% | $1,700,314 | +$749,977 |
1. Lone Star Sitework, LLC
LOW BID · WINNER- Unit price
- $15.50/SY
- Extension
- $914.50
- Proposal total
- $950,337
- Money left on the table
- $133,497 (14.05%)
- vs. engineer’s estimate
- +55%
2. Stx Civil
- Unit price
- $14.85/SY
- Extension
- $876.15
- Proposal total
- $1,083,834
- vs. low bid
- +$133,497
- vs. engineer’s estimate
- +48.5%
3. Rucoba & Maya Construction, LLC
- Unit price
- $40.00/SY
- Extension
- $2,360.00
- Proposal total
- $1,103,755
- vs. low bid
- +$153,418
- vs. engineer’s estimate
- +300%
4. Myers Concrete Construction, LP
- Unit price
- $17.00/SY
- Extension
- $1,003.00
- Proposal total
- $1,122,792
- vs. low bid
- +$172,455
- vs. engineer’s estimate
- +70%
- Unit price
- $22.00/SY
- Extension
- $1,298.00
- Proposal total
- $1,135,337
- vs. low bid
- +$185,000
- vs. engineer’s estimate
- +120%
- Unit price
- $24.50/SY
- Extension
- $1,445.50
- Proposal total
- $1,199,801
- vs. low bid
- +$249,464
- vs. engineer’s estimate
- +145%
7. Ratliff Hardscape, Ltd.
- Unit price
- $58.76/SY
- Extension
- $3,466.84
- Proposal total
- $1,228,710
- vs. low bid
- +$278,373
- vs. engineer’s estimate
- +487.6%
- Unit price
- $47.00/SY
- Extension
- $2,773.00
- Proposal total
- $1,272,000
- vs. low bid
- +$321,663
- vs. engineer’s estimate
- +370%
- Unit price
- $50.00/SY
- Extension
- $2,950.00
- Proposal total
- $1,700,314
- vs. low bid
- +$749,977
- vs. engineer’s estimate
- +400%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 42,500 | 4 | Mario Sinacola & Sons Excavating, Inc. | $3.81 | $4.18 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 165,493 | 6 | Indus Road & Bridge, Inc. | $3.60 | $5.00 |
| 2026-11-04 | 0285-03-066 | Hays | Austin | 59 | 9 | Lone Star Sitework, LLC | $15.50 | $10.00 |
| 2026-11-03 | 0008-02-078 | Parker | Fort Worth | 2,175 | 8 | Jay Mills Contracting, Incorporated | $6.05 | $5.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 12,785 | 6 | Austin Bridge & Road Services, LP | $8.25 | $12.00 |
| 2026-11-03 | 0271-06-141 | Harris | Houston | 2,295 | 5 | Yellowstone Landscape - Central, Inc. | $5.08 | $4.35 |
| 2026-11-03 | 0619-03-068 | Collin | Dallas | 1,715 | 13 | Rcr Telecon LLC | $9.00 | $4.00 |
| 2026-11-03 | 3330-01-011 | McLennan | Waco | 200 | 9 | The Levy Company, LLC | $31.62 | $5.00 |
| 2026-11-03 | 6497-19-001 | Travis | Austin | 1,500 | 12 | Road Doctors LLC | $10.00 | $6.00 |
| 2026-10-28 | 6507-80-001 | Angelina | Lufkin | 1,000 | 7 | Blacksmith Ventures LLC | $1.00 | $5.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 14 | $6.46 | $7.17 | $12.00 | — |
| Amarillo | 8 | $9.35 | $7.00 | $10.00 | — |
| Atlanta | 52 | $5.57 | $6.50 | $4.50 | -27.66% |
| Austin | 96 | $8.25 | $8.40 | $12.00 | +28.21% |
| Beaumont | 17 | $8.00 | $7.38 | $10.00 | — |
| Brownwood | 4 | $9.20 | $8.85 | $9.00 | — |
| Bryan | 97 | $8.00 | $7.00 | $6.00 | +40% |
| Childress | 3 | $8.40 | $8.40 | $12.00 | — |
| Corpus Christi | 25 | $6.92 | $8.00 | $10.00 | -2.44% |
| Dallas | 513 | $3.60 | $3.50 | $4.00 | -23.12% |
| Fort Worth | 194 | $4.90 | $5.10 | $7.00 | -16.56% |
| Houston | 291 | $3.00 | $3.40 | $3.50 | -17.36% |
| Lubbock | 8 | $6.00 | $7.00 | $5.00 | — |
| Lufkin | 158 | $5.60 | $6.15 | $6.00 | -23.85% |
| Odessa | 12 | $4.50 | $10.00 | $10.50 | — |
| Paris | 105 | $3.55 | $3.45 | $3.90 | -12.5% |
| Pharr | 13 | $7.00 | $9.45 | $10.00 | — |
| San Angelo | 7 | $5.50 | $11.00 | $4.00 | — |
| San Antonio | 104 | $4.00 | $4.00 | $6.00 | -8.57% |
| Tyler | 55 | $6.00 | $5.00 | $4.00 | -41.54% |
| Waco | 58 | $4.25 | $4.25 | $4.00 | +118.75% |
| Wichita Falls | 21 | $4.75 | $6.00 | $7.00 | — |
| Yoakum | 87 | $4.78 | $6.50 | $12.00 | -5% |
Related items
- 160-7002 · Furn & Place Topsoil (4") ($1.35/SY)
- 164-7005 · Broadcast Seed (Temp_Warm) ($0.150/SY)
- 164-7006 · Broadcast Seed (Temp_Cool) ($0.150/SY)
- 168-7001 · Vegetative Watering ($7.00/TGL)
- 132-7003 · Embank (FNL)(OC)(TY B) ($15.00/CY)
- 132-7006 · Embank (FNL)(DC)(TY C) ($12.00/CY)
- 132-7005 · Embank (FNL)(OC)(TY C) ($15.00/CY)
- 110-7001 · Excav (Roadway) ($10.00/CY)