Load Center, Remove, Secondary Voltage (Item 0715 7 41): FDOT Unit Price History
18 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $1,036.38/EA
- Contracts (12 mo)
- 18
- Total quantity (12 mo)
- 35 EA
- Total amount (12 mo)
- $36,273
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 17 | $1,052.07 | 29 | $30,510 |
| 2025 | 2025-01-01 – 2025-12-31 | 26 | $1,248.24 | 60 | $74,894 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 18 | $1,036.38 | 35 | $36,273 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 07 | 1 | $950.00 | -8.3% | 1 |
| 08 | 2 | $1,333.45 | +28.7% | 3 |
| 10 | 3 | $736.26 | -29% | 7 |
| 12 | 5 | $1,412.75 | +36.3% | 6 |
| 13 | 3 | $1,433.95 | +38.4% | 4 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 7 41 (Load Center, Remove, Secondary Voltage) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 18 contracts with a quantity-weighted average of $1,036.38 per EA, on 35 EA worth $36,273 in total.
The same report run for earlier periods shows $1,052.07 in 2024 (17 contracts, 29 EA), $1,248.24 in 2025 (26 contracts, 60 EA), $1,036.38 in the latest 12 months (18 contracts, 35 EA). Across those periods the weighted average stayed within three percent.
Quantity let statewide grew 21% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 10 had the lowest weighted average ($736.26 per EA, 3 contracts) and market area 13 the highest ($1,433.95, 3 contracts), 1.9 times as much. Market area 12 let the most contracts with this item (5). 5 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts).
Related items in section 0715
- 0715 1 12 · Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53/LF)
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 1 13 · Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93/LF)
- 0715 11211 · Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
- 0715 11125 · Luminaire, F&I, Under Deck, Wall Mount ($1,556.82/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.