Lighting Conductors, F&I, Insulated, NO.8 - 6 (Item 0715 1 12): FDOT Unit Price History
79 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $2.53/LF
- Contracts (12 mo)
- 79
- Total quantity (12 mo)
- 1,724,455 LF
- Total amount (12 mo)
- $4,362,415
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 106 | $2.52 | 1,785,066 | $4,491,147 |
| 2025 | 2025-01-01 – 2025-12-31 | 96 | $2.71 | 2,784,375 | $7,537,631 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 79 | $2.53 | 1,724,455 | $4,362,415 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $3.34 | +32% | 23,067 |
| 02 | 1 | $4.84 | +91.3% | 3,468 |
| 03 | 2 | $4.26 | +68.4% | 4,582 |
| 05 | 4 | $3.29 | +30% | 5,054 |
| 06 | 5 | $2.44 | -3.6% | 131,409 |
| 07 | 7 | $1.89 | -25.3% | 398,873 |
| 08 | 14 | $2.54 | +0.4% | 117,237 |
| 09 | 1 | $2.85 | +12.6% | 1,294 |
| 10 | 9 | $2.31 | -8.7% | 176,322 |
| 11 | 5 | $2.50 | -1.2% | 121,837 |
| 12 | 16 | $2.89 | +14.2% | 538,021 |
| 13 | 9 | $5.19 | +105.1% | 58,201 |
| 14 | 1 | $2.81 | +11.1% | 1,962 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 1 12 (Lighting Conductors, F&I, Insulated, NO.8 - 6) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 79 contracts with a quantity-weighted average of $2.53 per LF, on 1,724,455 LF worth $4,362,415 in total.
The same report run for earlier periods shows $2.52 in 2024 (106 contracts, 1,785,066 LF), $2.71 in 2025 (96 contracts, 2,784,375 LF), $2.53 in the latest 12 months (79 contracts, 1,724,455 LF). Across those periods the weighted average stayed within three percent.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 8 market areas with at least three contracts, market area 07 had the lowest weighted average ($1.89 per LF, 7 contracts) and market area 13 the highest ($5.19, 9 contracts), 2.7 times as much. Market area 12 let the most contracts with this item (16). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts); 0715 11211 Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16 per EA, 38 contracts).
Related items in section 0715
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 1 13 · Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93/LF)
- 0715 11211 · Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16/EA)
- 0715 7 41 · Load Center, Remove, Secondary Voltage ($1,036.38/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
- 0715 11125 · Luminaire, F&I, Under Deck, Wall Mount ($1,556.82/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.