Skip to content
BidTabulation.comDOT bid tabulations & unit-price intelligence
Menu

Lighting Conductors, Remove & Dispose, Contractor Owns (Item 0715 1 60): FDOT Unit Price History

53 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$0.540/LF
Contracts (12 mo)
53
Total quantity (12 mo)
732,048 LF
Total amount (12 mo)
$397,103

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3153$0.670748,507$502,280
20252025-01-01 – 2025-12-3152$0.5001,272,491$641,830
Latest 12 months2025-11-01 – 2026-10-3153$0.540732,048$397,103

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
032$1.06+96.3%672
051$0.500-7.4%959
062$0.650+20.4%3,041
077$1.02+88.9%36,660
089$0.820+51.9%99,718
105$0.280-48.1%80,924
112$0.460-14.8%8,190
1212$0.610+13%161,149
138$0.5400%46,550
141$0.860+59.3%636

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0715 1 60 (Lighting Conductors, Remove & Dispose, Contractor Owns) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 53 contracts with a quantity-weighted average of $0.540 per LF, on 732,048 LF worth $397,103 in total.

The same report run for earlier periods shows $0.670 in 2024 (53 contracts, 748,507 LF), $0.500 in 2025 (52 contracts, 1,272,491 LF), $0.540 in the latest 12 months (53 contracts, 732,048 LF). From 2024 to the latest 12 months the weighted average fell 19.4%.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 5 market areas with at least three contracts, market area 10 had the lowest weighted average ($0.280 per LF, 5 contracts) and market area 07 the highest ($1.02, 7 contracts), 3.6 times as much. Market area 12 let the most contracts with this item (12). 10 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts); 0715 11211 Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16 per EA, 38 contracts).

Related items in section 0715

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.