Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head (Item 0715 11211): FDOT Unit Price History
38 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $1,013.16/EA
- Contracts (12 mo)
- 38
- Total quantity (12 mo)
- 3,442 EA
- Total amount (12 mo)
- $3,487,280
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 49 | $1,769.11 | 747 | $1,321,527 |
| 2025 | 2025-01-01 – 2025-12-31 | 44 | $1,398.59 | 1,389 | $1,942,648 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 38 | $1,013.16 | 3,442 | $3,487,280 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $1,434.00 | +41.5% | 88 |
| 02 | 1 | $1,650.00 | +62.9% | 2 |
| 05 | 1 | $2,120.00 | +109.2% | 2 |
| 07 | 2 | $2,409.29 | +137.8% | 5 |
| 08 | 5 | $1,068.89 | +5.5% | 91 |
| 09 | 1 | $2,453.31 | +142.1% | 10 |
| 10 | 7 | $1,735.95 | +71.3% | 54 |
| 11 | 1 | $1,063.00 | +4.9% | 7 |
| 12 | 9 | $1,324.76 | +30.8% | 303 |
| 13 | 6 | $1,453.53 | +43.5% | 49 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 11211 (Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 38 contracts with a quantity-weighted average of $1,013.16 per EA, on 3,442 EA worth $3,487,280 in total.
The same report run for earlier periods shows $1,769.11 in 2024 (49 contracts, 747 EA), $1,398.59 in 2025 (44 contracts, 1,389 EA), $1,013.16 in the latest 12 months (38 contracts, 3,442 EA). From 2024 to the latest 12 months the weighted average fell 42.7%.
Quantity let statewide grew 361% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 4 market areas with at least three contracts, market area 08 had the lowest weighted average ($1,068.89 per EA, 5 contracts) and market area 10 the highest ($1,735.95, 7 contracts), 1.6 times as much. Market area 12 let the most contracts with this item (9). 10 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts).
Related items in section 0715
- 0715 1 12 · Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53/LF)
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 1 13 · Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93/LF)
- 0715 7 41 · Load Center, Remove, Secondary Voltage ($1,036.38/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
- 0715 11125 · Luminaire, F&I, Under Deck, Wall Mount ($1,556.82/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.