Light Pole Complete, Remove Pole AND Foundation (Item 0715 69000): FDOT Unit Price History

46 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$835.22/EA
Contracts (12 mo)
46
Total quantity (12 mo)
1,022 EA
Total amount (12 mo)
$853,593

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3151$1,133.821,118$1,267,607
20252025-01-01 – 2025-12-3153$945.542,048$1,936,464
Latest 12 months2025-11-01 – 2026-10-3146$835.221,022$853,593

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
011$2,667.00+219.3%11
052$874.08+4.7%7
064$992.76+18.9%15
073$941.83+12.8%33
089$1,093.10+30.9%114
107$985.31+18%80
112$712.76-14.7%29
128$729.17-12.7%558
135$811.11-2.9%81
141$1,224.98+46.7%2

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0715 69000 (Light Pole Complete, Remove Pole AND Foundation) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 46 contracts with a quantity-weighted average of $835.22 per EA, on 1,022 EA worth $853,593 in total.

The same report run for earlier periods shows $1,133.82 in 2024 (51 contracts, 1,118 EA), $945.54 in 2025 (53 contracts, 2,048 EA), $835.22 in the latest 12 months (46 contracts, 1,022 EA). From 2024 to the latest 12 months the weighted average fell 26.3%.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 12 had the lowest weighted average ($729.17 per EA, 8 contracts) and market area 08 the highest ($1,093.10, 9 contracts), 1.5 times as much. Market area 08 let the most contracts with this item (9). 10 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts); 0715 11211 Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16 per EA, 38 contracts).

Related items in section 0715

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.