Luminaire, F&I, Under Deck, Wall Mount (Item 0715 11125): FDOT Unit Price History
12 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $1,556.82/EA
- Contracts (12 mo)
- 12
- Total quantity (12 mo)
- 176 EA
- Total amount (12 mo)
- $274,000
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 15 | $1,619.36 | 232 | $375,693 |
| 2025 | 2025-01-01 – 2025-12-31 | 18 | $1,461.93 | 307 | $448,812 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 12 | $1,556.82 | 176 | $274,000 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 06 | 1 | $2,215.00 | +42.3% | 2 |
| 07 | 2 | $1,889.22 | +21.4% | 51 |
| 08 | 2 | $1,299.00 | -16.6% | 20 |
| 10 | 1 | $1,100.00 | -29.3% | 7 |
| 11 | 1 | $3,635.00 | +133.5% | 4 |
| 12 | 5 | $1,358.70 | -12.7% | 92 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 11125 (Luminaire, F&I, Under Deck, Wall Mount) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 12 contracts with a quantity-weighted average of $1,556.82 per EA, on 176 EA worth $274,000 in total.
The same report run for earlier periods shows $1,619.36 in 2024 (15 contracts, 232 EA), $1,461.93 in 2025 (18 contracts, 307 EA), $1,556.82 in the latest 12 months (12 contracts, 176 EA). From 2024 to the latest 12 months the weighted average fell 3.9%.
Quantity let statewide shrank 24% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 6 of FDOT's 14 market areas reported this item: area 06 at $2,215.00 (1 contract), area 07 at $1,889.22 (2 contracts), area 08 at $1,299.00 (2 contracts), area 10 at $1,100.00 (1 contract), area 11 at $3,635.00 (1 contract), area 12 at $1,358.70 (5 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts).
Related items in section 0715
- 0715 1 12 · Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53/LF)
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 1 13 · Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93/LF)
- 0715 11211 · Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16/EA)
- 0715 7 41 · Load Center, Remove, Secondary Voltage ($1,036.38/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.