Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 (Item 0715 1 13): FDOT Unit Price History
40 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $3.93/LF
- Contracts (12 mo)
- 40
- Total quantity (12 mo)
- 1,590,532 LF
- Total amount (12 mo)
- $6,246,281
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 48 | $3.98 | 807,390 | $3,214,823 |
| 2025 | 2025-01-01 – 2025-12-31 | 46 | $4.52 | 1,708,789 | $7,722,199 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 40 | $3.93 | 1,590,532 | $6,246,281 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 1 | $6.50 | +65.4% | 306 |
| 06 | 4 | $4.69 | +19.3% | 49,306 |
| 07 | 4 | $3.59 | -8.7% | 233,164 |
| 08 | 7 | $3.80 | -3.3% | 344,123 |
| 10 | 4 | $3.14 | -20.1% | 29,172 |
| 11 | 2 | $3.41 | -13.2% | 64,485 |
| 12 | 7 | $4.46 | +13.5% | 598,441 |
| 13 | 7 | $5.01 | +27.5% | 80,197 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 1 13 (Lighting Conductors, F&I, Insulated, NO 4 TO NO 2) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 40 contracts with a quantity-weighted average of $3.93 per LF, on 1,590,532 LF worth $6,246,281 in total.
The same report run for earlier periods shows $3.98 in 2024 (48 contracts, 807,390 LF), $4.52 in 2025 (46 contracts, 1,708,789 LF), $3.93 in the latest 12 months (40 contracts, 1,590,532 LF). Across those periods the weighted average stayed within three percent.
Quantity let statewide grew 97% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 6 market areas with at least three contracts, market area 10 had the lowest weighted average ($3.14 per LF, 4 contracts) and market area 13 the highest ($5.01, 7 contracts), 1.6 times as much. Market area 08 let the most contracts with this item (7). 8 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 11211 Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16 per EA, 38 contracts).
Related items in section 0715
- 0715 1 12 · Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53/LF)
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 11211 · Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16/EA)
- 0715 7 41 · Load Center, Remove, Secondary Voltage ($1,036.38/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
- 0715 11125 · Luminaire, F&I, Under Deck, Wall Mount ($1,556.82/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.