Lighting Conductors, F&I, Insulated, NO. 10 OR < (Item 0715 1 11): FDOT Unit Price History
11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF
- Weighted average (12 mo)
- $5.65/LF
- Contracts (12 mo)
- 11
- Total quantity (12 mo)
- 24,804 LF
- Total amount (12 mo)
- $140,041
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 14 | $1.41 | 34,242 | $48,265 |
| 2025 | 2025-01-01 – 2025-12-31 | 12 | $1.88 | 30,433 | $57,315 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 11 | $5.65 | 24,804 | $140,041 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 03 | 2 | $2.59 | -54.2% | 356 |
| 05 | 1 | $1.25 | -77.9% | 592 |
| 07 | 1 | $10.29 | +82.1% | 378 |
| 08 | 2 | $0.940 | -83.4% | 2,586 |
| 10 | 1 | $1.10 | -80.5% | 9,028 |
| 12 | 3 | $1.81 | -68% | 1,434 |
| 13 | 1 | $11.46 | +102.8% | 10,430 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0715 1 11 (Lighting Conductors, F&I, Insulated, NO. 10 OR <) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $5.65 per LF, on 24,804 LF worth $140,041 in total.
The same report run for earlier periods shows $1.41 in 2024 (14 contracts, 34,242 LF), $1.88 in 2025 (12 contracts, 30,433 LF), $5.65 in the latest 12 months (11 contracts, 24,804 LF). From 2024 to the latest 12 months the weighted average rose 300.7%.
Quantity let statewide shrank 28% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 7 of FDOT's 14 market areas reported this item: area 03 at $2.59 (2 contracts), area 05 at $1.25 (1 contract), area 07 at $10.29 (1 contract), area 08 at $0.940 (2 contracts), area 10 at $1.10 (1 contract), area 12 at $1.81 (3 contracts), area 13 at $11.46 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0715: 0715 1 12 Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53 per LF, 79 contracts); 0715 1 60 Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540 per LF, 53 contracts); 0715 69000 Light Pole Complete, Remove Pole AND Foundation ($835.22 per EA, 46 contracts); 0715 7 11 Load Center, F&I, Secondary Voltage ($20,487.97 per EA, 45 contracts); 0715 1 13 Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93 per LF, 40 contracts).
Related items in section 0715
- 0715 1 12 · Lighting Conductors, F&I, Insulated, NO.8 - 6 ($2.53/LF)
- 0715 1 60 · Lighting Conductors, Remove & Dispose, Contractor Owns ($0.540/LF)
- 0715 69000 · Light Pole Complete, Remove Pole AND Foundation ($835.22/EA)
- 0715 7 11 · Load Center, F&I, Secondary Voltage ($20,487.97/EA)
- 0715 1 13 · Lighting Conductors, F&I, Insulated, NO 4 TO NO 2 ($3.93/LF)
- 0715 11211 · Luminaire, F&I- Replace Existing Luminaire ON Existing Pole/ARM, Roadway, Cobra Head ($1,013.16/EA)
- 0715 7 41 · Load Center, Remove, Secondary Voltage ($1,036.38/EA)
- 0715 61300 · Light Pole Complete, F&I, Standard Pole Standard Foundation, 40' Mounting Height, 0' ARM Length ($8,528.16/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.