Condt (PVC) (SCH 80) (2") (Bore) (Item 618-7055): TxDOT Unit Price History

1,252 bids · 222 bid lines · Nov 6, 2024 to Nov 12, 2026 · unit of measure LF

TxDOT 618-7055 · CONDT (PVC) (SCH 80) (2") (BORE) · Unit: LF

Low bid
$21.34/LF
Quantity-weighted median of winning unit prices
Weighted median
$21.00/LF
Quantity-weighted median of every bid
Engineer’s estimate
$25.00/LF
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-12.67%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$20.00$40.00$60.00101001K10K100KQuantity (LF), log scaleUnit price ($/LF)
Winning (low) bid Other bid Fitted price curve (ln price = 3.96 − 0.099·ln qty, R² 0.09)320 plotted bids, 6 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 12, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 618-7055 (Condt (PVC) (SCH 80) (2") (Bore)) is measured in LF. Between Nov 6, 2024 and Nov 12, 2026, contractors entered 1,252 bids for it on 222 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 753 bids was $21.00 per LF, and the winning low bidders priced it at a weighted median of $21.34 per LF.

TxDOT's engineer's estimate for the same lines had a weighted median of $25.00 per LF, so winning bids came in 14.6% below the estimate.

By calendar year, the median bid moved from $30.00 in 2025 (515 bids) to $25.98 in 2026 (689 bids), down 13.4%. The middle half of 2026 bids fell between $20.00 and $33.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 12.67%.

Quantity matters for this item. Lines of 25 to 405 LF had a weighted median of $30.19, while lines above 1,460 LF had $17.96, a 41% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 218 lines where both a winning and a second-place bid were published, the median winning unit price was $25.03 against $28.00 from the second-lowest bidder, a median gap of 4.38% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 22 TxDOT districts with at least ten bids, Houston had the lowest weighted median ($12.96) and Beaumont the highest ($41.76). The busiest district for this item was Houston.

The most recent letting with this item was on Nov 12, 2026 in Dallas County, where Highway Intelligent Traffic Solutions, LLC was the low bidder at $24.65 per LF for 25 LF against an estimate of $25.00.

1 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 618-7030 Condt (PVC) (SCH 40) (2") (weighted median $12.10 per LF); 618-7054 Condt (PVC) (SCH 80) (2") (weighted median $10.30 per LF); 620-7009 Elec Condr (NO.6) Bare (weighted median $2.22 per LF); 620-7010 Elec Condr (NO.6) Insulated (weighted median $2.52 per LF).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
2024488$42.93$36.35$34.50$28.17$48.04
2025515103$23.92$18.72$30.00$20.23$38.00
2026689111$21.66$20.00$25.98$20.00$33.00

Quantity bands

BandQuantity (LF)BidsWeighted avgWeighted median25th–75th pct
Small25–405423$33.72$30.19$25.00–$40.82
Medium410–1,445416$32.74$29.45$20.97–$36.76
Large1,460–77,800413$21.27$17.96$15.70–$29.89

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$25.03
Median second-low unit price
$28.00
Median engineer’s estimate
$28.00
Median gap, second vs. low
+4.38%

218 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 6504-57-001 · let Nov 12, 2026 · Dallas County, Dallas District

Line quantity 25 LF · Engineer’s estimate $25.00/LF

  • Unit price
    $24.65/LF
    Extension
    $616.25
    Proposal total
    $792,536
    Money left on the table
    $105,738 (13.34%)
    vs. engineer’s estimate
    -1.4%
  • Unit price
    $40.00/LF
    Extension
    $1,000.00
    Proposal total
    $898,274
    vs. low bid
    +$105,738
    vs. engineer’s estimate
    +60%
  • Unit price
    $31.00/LF
    Extension
    $775.00
    Proposal total
    $900,000
    vs. low bid
    +$107,464
    vs. engineer’s estimate
    +24%
  • 4. Road Solutions L.L.C.

    Unit price
    $16.85/LF
    Extension
    $421.25
    Proposal total
    $940,478
    vs. low bid
    +$147,942
    vs. engineer’s estimate
    -32.6%
  • Unit price
    $61.00/LF
    Extension
    $1,525.00
    Proposal total
    $1,358,810
    vs. low bid
    +$566,274
    vs. engineer’s estimate
    +144%

Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District

Line quantity 375 LF · Engineer’s estimate $27.00/LF

  • 1. Fluor Enterprises, Inc.

    LOW BID · WINNER
    Unit price
    $19.00/LF
    Extension
    $7,125.00
    Proposal total
    $30,209,876
    Money left on the table
    $2,977,718 (9.86%)
    vs. engineer’s estimate
    -29.6%
  • Unit price
    $20.00/LF
    Extension
    $7,500.00
    Proposal total
    $33,187,594
    vs. low bid
    +$2,977,718
    vs. engineer’s estimate
    -25.9%
  • Unit price
    $19.66/LF
    Extension
    $7,372.50
    Proposal total
    $33,911,798
    vs. low bid
    +$3,701,922
    vs. engineer’s estimate
    -27.2%
  • Unit price
    $20.00/LF
    Extension
    $7,500.00
    Proposal total
    $34,862,676
    vs. low bid
    +$4,652,800
    vs. engineer’s estimate
    -25.9%
  • Unit price
    $18.28/LF
    Extension
    $6,855.00
    Proposal total
    $39,237,828
    vs. low bid
    +$9,027,952
    vs. engineer’s estimate
    -32.3%
  • Unit price
    $20.00/LF
    Extension
    $7,500.00
    Proposal total
    $39,562,405
    vs. low bid
    +$9,352,529
    vs. engineer’s estimate
    -25.9%
  • Unit price
    $19.00/LF
    Extension
    $7,125.00
    Proposal total
    $39,630,699
    vs. low bid
    +$9,420,823
    vs. engineer’s estimate
    -29.6%
  • Unit price
    $19.20/LF
    Extension
    $7,200.00
    Proposal total
    $39,994,995
    vs. low bid
    +$9,785,119
    vs. engineer’s estimate
    -28.9%
  • 9. Zachry Construction Corporation

    Unit price
    $19.73/LF
    Extension
    $7,398.75
    Proposal total
    $42,444,061
    vs. low bid
    +$12,234,185
    vs. engineer’s estimate
    -26.9%
  • 10. Brizo Construction, LLC

    Unit price
    $20.11/LF
    Extension
    $7,541.25
    Proposal total
    $43,708,350
    vs. low bid
    +$13,498,474
    vs. engineer’s estimate
    -25.5%
  • Unit price
    $18.45/LF
    Extension
    $6,918.75
    Proposal total
    $44,387,970
    vs. low bid
    +$14,178,094
    vs. engineer’s estimate
    -31.7%
  • Unit price
    $19.00/LF
    Extension
    $7,125.00
    Proposal total
    $48,396,973
    vs. low bid
    +$18,187,097
    vs. engineer’s estimate
    -29.6%

Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District

Line quantity 9,543 LF · Engineer’s estimate $35.00/LF

  • Unit price
    $21.34/LF
    Extension
    $203,647.62
    Proposal total
    $412,233,374
    Money left on the table
    $3,506,193 (0.85%)
    vs. engineer’s estimate
    -39%
  • 2. Pulice Construction, Inc.

    Unit price
    $22.94/LF
    Extension
    $218,916.42
    Proposal total
    $415,739,567
    vs. low bid
    +$3,506,193
    vs. engineer’s estimate
    -34.5%
  • 3. Fluor Enterprises, Inc.

    Unit price
    $22.55/LF
    Extension
    $215,194.65
    Proposal total
    $473,353,333
    vs. low bid
    +$61,119,959
    vs. engineer’s estimate
    -35.6%
  • 4. Harper Brothers Construction LLC

    Unit price
    $40.00/LF
    Extension
    $381,720.00
    Proposal total
    $477,550,553
    vs. low bid
    +$65,317,180
    vs. engineer’s estimate
    +14.3%
  • Unit price
    $30.00/LF
    Extension
    $286,290.00
    Proposal total
    $477,564,067
    vs. low bid
    +$65,330,694
    vs. engineer’s estimate
    -14.3%
  • 6. Balfour Beatty Infrastructure, Inc.

    Unit price
    $24.90/LF
    Extension
    $237,620.70
    Proposal total
    $492,134,823
    vs. low bid
    +$79,901,450
    vs. engineer’s estimate
    -28.9%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-126504-57-001DallasDallas255Highway Intelligent Traffic Solutions, LLC$24.65$25.00
2026-11-040212-03-058BrazosBryan37512Fluor Enterprises, Inc.$19.00$27.00
2026-11-030015-13-432TravisAustin9,5436Austin Bridge & Road Services, LP$21.34$35.00
2026-11-030168-09-191RandallAmarillo1,2608Coppell Construction Co., Inc.$33.00$30.00
2026-11-036504-89-001HarrisHouston1,2007Traf-Tex, Inc.$20.05$22.75
2026-10-086506-29-001AngelinaLufkin3003Select Maintenance, L.L.C.$19.00$29.00
2026-10-070143-03-049WilsonSan Antonio4758Hunter Industries, Ltd.$22.00$24.00
2026-10-061414-03-043BrazoriaHouston2952Durwood Greene Construction Co.$20.00$26.00
2026-10-062502-01-024BellWaco2,7056Big Creek Construction, Ltd.$27.50$15.00
2026-09-030918-00-440DallasDallas508American Lighting and Signalization, LLC$32.00$35.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene34$40.00$35.00$32.00-7.04%
Amarillo30$23.90$24.04$30.00—
Atlanta14$20.60$21.50$27.00—
Austin25$21.34$24.90$35.00-25.3%
Beaumont28$41.00$41.76$15.00—
Brownwood13$32.20$33.89$42.00—
Bryan25$19.00$19.43$27.00—
Corpus Christi44$23.00$24.00$20.00-25%
Dallas111$11.71$27.97$25.00-14.34%
El Paso10$28.00$28.00$23.20—
Fort Worth60$32.50$31.50$38.00—
Houston251$10.32$12.96$17.50-5.3%
Laredo55$21.03$24.36$35.00-20%
Lubbock27$26.95$32.15$26.00—
Lufkin33$24.00$21.50$30.00-11.02%
Odessa35$23.00$25.00$30.00-36.35%
Paris11$25.05$34.80$41.72—
Pharr49$27.45$28.50$15.00-8.47%
San Angelo8$35.00$37.00$50.00—
San Antonio151$24.30$25.00$30.00-15.03%
Tyler65$19.00$19.75$35.00—
Waco40$27.50$34.00$15.00-32%
Wichita Falls9$25.00$27.90$25.00—
Yoakum124$19.24$22.00$20.00+7.76%

Related items

Is your price for item 618-7055 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.