Rock Filter Dams (Install) (TY 2) (Item 506-7002): TxDOT Unit Price History
1,975 bids · 314 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure LF
TxDOT 506-7002 · ROCK FILTER DAMS (INSTALL) (TY 2) · Unit: LF
- Low bid
- $42.00/LF
- Quantity-weighted median of winning unit prices
- Weighted median
- $43.17/LF
- Quantity-weighted median of every bid
- Engineer’s estimate
- $45.00/LF
- Quantity-weighted median of TxDOT’s estimate per line
- 12-mo trend
- -2.17%
- Median unit price, last 12 months vs the 12 before
Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.
Export bid rows (CSV)Summary
TxDOT pay item 506-7002 (Rock Filter Dams (Install) (TY 2)) is measured in LF. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,975 bids for it on 314 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 1,023 bids was $43.17 per LF, and the winning low bidders priced it at a weighted median of $42.00 per LF.
TxDOT's engineer's estimate for the same lines had a weighted median of $45.00 per LF, so winning bids came in 6.7% below the estimate.
By calendar year, the median bid moved from $46.00 in 2025 (943 bids) to $45.00 in 2026 (967 bids), a change small enough to sit within normal bid-to-bid variation. The middle half of 2026 bids fell between $39.58 and $55.00.
Comparing the last 12 months with the 12 months before, the median unit price fell 2.17%.
Quantity matters for this item. Lines of 8 to 156 LF had a weighted median of $50.00, while lines above 516 LF had $43.14, a 14% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.
Across 276 lines where both a winning and a second-place bid were published, the median winning unit price was $45.00 against $45.00 from the second-lowest bidder, a median gap of -0.29% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.
Prices differ by district. Among the 19 TxDOT districts with at least ten bids, Lufkin had the lowest weighted median ($35.00) and Amarillo the highest ($73.59). The busiest district for this item was Dallas.
The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $35.00 per LF for 776 LF against an estimate of $41.00.
129 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.
Related items: 506-7041 Temp Sedmt Cont Fence (Remove) (weighted median $1.00 per LF); 506-7039 Temp Sedmt Cont Fence (Install) (weighted median $3.94 per LF); 506-7046 Biodeg Erosn Cont Logs (Remove) (weighted median $1.00 per LF); 506-7011 Rock Filter Dams (Remove) (weighted median $12.00 per LF).
Unit price by year
| Year | Bids | Bid lines | Weighted avg | Weighted median | Median | 25th pct | 75th pct |
|---|---|---|---|---|---|---|---|
| 2024 | 65 | 11 | $52.96 | $50.00 | $50.00 | $39.00 | $66.00 |
| 2025 | 943 | 159 | $46.11 | $44.00 | $46.00 | $40.00 | $55.00 |
| 2026 | 967 | 144 | $44.75 | $43.17 | $45.00 | $39.58 | $55.00 |
Quantity bands
| Band | Quantity (LF) | Bids | Weighted avg | Weighted median | 25th–75th pct |
|---|---|---|---|---|---|
| Small | 8–156 | 664 | $51.99 | $50.00 | $40.00–$65.00 |
| Medium | 160–512 | 658 | $47.89 | $45.00 | $40.00–$54.00 |
| Large | 516–10,640 | 653 | $44.70 | $43.14 | $38.00–$50.00 |
Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.
Winning bid vs. second-low vs. engineer’s estimate
- Median winning unit price
- $45.00
- Median second-low unit price
- $45.00
- Median engineer’s estimate
- $48.73
- Median gap, second vs. low
- +-0.29%
276 published lines with both a rank-1 and a rank-2 bid.
Contractor head-to-head · Money left on the table
Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District
Line quantity 776 LF · Engineer’s estimate $41.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Mario Sinacola & Sons Excavating, Inc.LOW BID | $35.00/LF | $27,160.00 | — | -14.6% | $35,766,135 | $890,797 (2.49%) left on table |
| 2 | Ed Bell Construction Company | $79.88/LF | $61,986.88 | +$34,827 | +94.8% | $36,656,931 | +$890,797 |
| 3 | Tiseo Paving Company, LLC | $138.50/LF | $107,476.00 | +$80,316 | +237.8% | $38,169,956 | +$2,403,821 |
| 4 | Harper Brothers Construction LLC | $40.00/LF | $31,040.00 | +$3,880 | -2.4% | $40,441,503 | +$4,675,368 |
1. Mario Sinacola & Sons Excavating, Inc.
LOW BID · WINNER- Unit price
- $35.00/LF
- Extension
- $27,160.00
- Proposal total
- $35,766,135
- Money left on the table
- $890,797 (2.49%)
- vs. engineer’s estimate
- -14.6%
- Unit price
- $79.88/LF
- Extension
- $61,986.88
- Proposal total
- $36,656,931
- vs. low bid
- +$890,797
- vs. engineer’s estimate
- +94.8%
3. Tiseo Paving Company, LLC
- Unit price
- $138.50/LF
- Extension
- $107,476.00
- Proposal total
- $38,169,956
- vs. low bid
- +$2,403,821
- vs. engineer’s estimate
- +237.8%
4. Harper Brothers Construction LLC
- Unit price
- $40.00/LF
- Extension
- $31,040.00
- Proposal total
- $40,441,503
- vs. low bid
- +$4,675,368
- vs. engineer’s estimate
- -2.4%
Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District
Line quantity 1,454 LF · Engineer’s estimate $40.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Indus Road & Bridge, Inc.LOW BID | $45.00/LF | $65,430.00 | — | +12.5% | $138,145,038 | $5,131,824 (3.71%) left on table |
| 2 | Rpm Xconstruction, LLC | $37.75/LF | $54,888.50 | -$10,542 | -5.6% | $143,276,861 | +$5,131,824 |
| 3 | Mario Sinacola & Sons Excavating, Inc. | $40.00/LF | $58,160.00 | -$7,270 | 0% | $152,579,077 | +$14,434,039 |
| 4 | Webber, LLC | $43.96/LF | $63,917.84 | -$1,512 | +9.9% | $153,499,152 | +$15,354,114 |
| 5 | Sema Construction, Inc. | $50.00/LF | $72,700.00 | +$7,270 | +25% | $154,136,028 | +$15,990,990 |
| 6 | Zachry Construction Corporation | $45.62/LF | $66,331.48 | +$901.48 | +14% | $154,873,429 | +$16,728,392 |
- LOW BID · WINNER
- Unit price
- $45.00/LF
- Extension
- $65,430.00
- Proposal total
- $138,145,038
- Money left on the table
- $5,131,824 (3.71%)
- vs. engineer’s estimate
- +12.5%
2. Rpm Xconstruction, LLC
- Unit price
- $37.75/LF
- Extension
- $54,888.50
- Proposal total
- $143,276,861
- vs. low bid
- +$5,131,824
- vs. engineer’s estimate
- -5.6%
- Unit price
- $40.00/LF
- Extension
- $58,160.00
- Proposal total
- $152,579,077
- vs. low bid
- +$14,434,039
- vs. engineer’s estimate
- 0%
4. Webber, LLC
- Unit price
- $43.96/LF
- Extension
- $63,917.84
- Proposal total
- $153,499,152
- vs. low bid
- +$15,354,114
- vs. engineer’s estimate
- +9.9%
5. Sema Construction, Inc.
- Unit price
- $50.00/LF
- Extension
- $72,700.00
- Proposal total
- $154,136,028
- vs. low bid
- +$15,990,990
- vs. engineer’s estimate
- +25%
6. Zachry Construction Corporation
- Unit price
- $45.62/LF
- Extension
- $66,331.48
- Proposal total
- $154,873,429
- vs. low bid
- +$16,728,392
- vs. engineer’s estimate
- +14%
Proposal 0212-03-058 · let Nov 4, 2026 · Brazos County, Bryan District
Line quantity 1,739 LF · Engineer’s estimate $40.00/LF
| Rank | Contractor | Unit price | Qty × Unit Price = Extension | Line vs. low bid | Line vs. estimate | Proposal total | Proposal vs. low bid |
|---|---|---|---|---|---|---|---|
| 1 | Fluor Enterprises, Inc.LOW BID | $40.00/LF | $69,560.00 | — | 0% | $30,209,876 | $2,977,718 (9.86%) left on table |
| 2 | Big Creek Construction, Ltd. | $42.00/LF | $73,038.00 | +$3,478 | +5% | $33,187,594 | +$2,977,718 |
| 3 | Knife River Corporation - South | $43.00/LF | $74,777.00 | +$5,217 | +7.5% | $33,911,798 | +$3,701,922 |
| 4 | R Construction Civil, LLC | $50.00/LF | $86,950.00 | +$17,390 | +25% | $34,862,676 | +$4,652,800 |
| 5 | James Construction Group, LLC | $40.00/LF | $69,560.00 | $0.000 | 0% | $39,237,828 | +$9,027,952 |
| 6 | Texas Materials Group, Inc. | $41.00/LF | $71,299.00 | +$1,739 | +2.5% | $39,562,405 | +$9,352,529 |
| 7 | A. L. Helmcamp, Inc. | $42.00/LF | $73,038.00 | +$3,478 | +5% | $39,630,699 | +$9,420,823 |
| 8 | Posillico Civil, Inc. | $44.00/LF | $76,516.00 | +$6,956 | +10% | $39,994,995 | +$9,785,119 |
| 9 | Zachry Construction Corporation | $43.16/LF | $75,055.24 | +$5,495 | +7.9% | $42,444,061 | +$12,234,185 |
| 10 | Brizo Construction, LLC | $44.00/LF | $76,516.00 | +$6,956 | +10% | $43,708,350 | +$13,498,474 |
| 11 | Granite Construction Company | $63.50/LF | $110,426.50 | +$40,867 | +58.8% | $44,387,970 | +$14,178,094 |
| 12 | Isi Contracting, Inc. | $46.00/LF | $79,994.00 | +$10,434 | +15% | $48,396,973 | +$18,187,097 |
1. Fluor Enterprises, Inc.
LOW BID · WINNER- Unit price
- $40.00/LF
- Extension
- $69,560.00
- Proposal total
- $30,209,876
- Money left on the table
- $2,977,718 (9.86%)
- vs. engineer’s estimate
- 0%
- Unit price
- $42.00/LF
- Extension
- $73,038.00
- Proposal total
- $33,187,594
- vs. low bid
- +$2,977,718
- vs. engineer’s estimate
- +5%
- Unit price
- $43.00/LF
- Extension
- $74,777.00
- Proposal total
- $33,911,798
- vs. low bid
- +$3,701,922
- vs. engineer’s estimate
- +7.5%
- Unit price
- $50.00/LF
- Extension
- $86,950.00
- Proposal total
- $34,862,676
- vs. low bid
- +$4,652,800
- vs. engineer’s estimate
- +25%
- Unit price
- $40.00/LF
- Extension
- $69,560.00
- Proposal total
- $39,237,828
- vs. low bid
- +$9,027,952
- vs. engineer’s estimate
- 0%
- Unit price
- $41.00/LF
- Extension
- $71,299.00
- Proposal total
- $39,562,405
- vs. low bid
- +$9,352,529
- vs. engineer’s estimate
- +2.5%
- Unit price
- $42.00/LF
- Extension
- $73,038.00
- Proposal total
- $39,630,699
- vs. low bid
- +$9,420,823
- vs. engineer’s estimate
- +5%
- Unit price
- $44.00/LF
- Extension
- $76,516.00
- Proposal total
- $39,994,995
- vs. low bid
- +$9,785,119
- vs. engineer’s estimate
- +10%
9. Zachry Construction Corporation
- Unit price
- $43.16/LF
- Extension
- $75,055.24
- Proposal total
- $42,444,061
- vs. low bid
- +$12,234,185
- vs. engineer’s estimate
- +7.9%
10. Brizo Construction, LLC
- Unit price
- $44.00/LF
- Extension
- $76,516.00
- Proposal total
- $43,708,350
- vs. low bid
- +$13,498,474
- vs. engineer’s estimate
- +10%
- Unit price
- $63.50/LF
- Extension
- $110,426.50
- Proposal total
- $44,387,970
- vs. low bid
- +$14,178,094
- vs. engineer’s estimate
- +58.8%
- Unit price
- $46.00/LF
- Extension
- $79,994.00
- Proposal total
- $48,396,973
- vs. low bid
- +$18,187,097
- vs. engineer’s estimate
- +15%
Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.
Last 10 lettings with this item
| Let date | CSJ | County | District | Qty | Bidders | Low bidder | Low unit price | Estimate |
|---|---|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 776 | 4 | Mario Sinacola & Sons Excavating, Inc. | $35.00 | $41.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 1,454 | 6 | Indus Road & Bridge, Inc. | $45.00 | $40.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 1,739 | 12 | Fluor Enterprises, Inc. | $40.00 | $40.00 |
| 2026-11-04 | 0262-01-034 | Milam | Bryan | 2,275 | 7 | Big Creek Construction, Ltd. | $35.00 | $35.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 210 | 7 | Stx Civil | $42.14 | $49.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 720 | 9 | Highway 19 Construction LLC | $45.00 | $60.00 |
| 2026-11-04 | 1052-02-098 | Nueces | Corpus Christi | 58 | 5 | J E Construction Services, LLC | $76.00 | $30.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 165 | 6 | Austin Bridge & Road Services, LP | $38.50 | $46.45 |
| 2026-10-07 | 0014-23-041 | Hill | Waco | 156 | 5 | Northeastern Pavers, LLC | $52.00 | $30.00 |
| 2026-10-07 | 0092-03-064 | Ellis | Dallas | 22 | 7 | Xit Paving and Construction Inc. | $60.00 | $45.00 |
By district
| District | Bids | Low bid (w. median) | Weighted median | Estimate | 12-mo trend |
|---|---|---|---|---|---|
| Abilene | 24 | $55.00 | $55.00 | $45.00 | — |
| Amarillo | 12 | $72.18 | $73.59 | $70.00 | — |
| Atlanta | 87 | $45.00 | $44.00 | $45.00 | -3.87% |
| Austin | 194 | $50.00 | $46.00 | $46.45 | -2.95% |
| Beaumont | 55 | $55.00 | $50.00 | $50.00 | +2.04% |
| Brownwood | 7 | $28.00 | $38.36 | $40.00 | — |
| Bryan | 215 | $35.00 | $43.00 | $35.00 | +3.1% |
| Corpus Christi | 41 | $30.00 | $50.00 | $40.00 | — |
| Dallas | 339 | $40.75 | $43.17 | $40.00 | +3.58% |
| El Paso | 10 | $40.00 | $40.00 | $60.00 | — |
| Fort Worth | 145 | $45.80 | $44.00 | $45.00 | -10% |
| Houston | 73 | $81.60 | $47.00 | $50.00 | -10.75% |
| Laredo | 19 | $49.44 | $49.44 | $50.00 | — |
| Lubbock | 5 | $123.15 | $56.00 | $50.00 | — |
| Lufkin | 111 | $33.00 | $35.00 | $42.00 | -22.92% |
| Paris | 179 | $50.00 | $52.05 | $55.00 | +6.02% |
| Pharr | 51 | $38.00 | $46.75 | $55.50 | +15.38% |
| San Angelo | 9 | $44.00 | $44.00 | $50.00 | — |
| San Antonio | 112 | $49.53 | $45.00 | $45.00 | +2.94% |
| Tyler | 148 | $40.00 | $38.00 | $45.00 | -9.09% |
| Waco | 89 | $37.00 | $40.00 | $40.00 | -3.89% |
| Wichita Falls | 50 | $47.00 | $44.00 | $46.00 | -14.18% |
Related items
- 506-7041 · Temp Sedmt Cont Fence (Remove) ($1.00/LF)
- 506-7039 · Temp Sedmt Cont Fence (Install) ($3.94/LF)
- 506-7046 · Biodeg Erosn Cont Logs (Remove) ($1.00/LF)
- 506-7011 · Rock Filter Dams (Remove) ($12.00/LF)
- 506-7044 · Biodeg Erosn Cont Logs (Instl) (12") ($5.65/LF)
- 506-7024 · Construction Exits (Remove) ($10.00/SY)
- 506-7020 · Construction Exits (Install) (TY 1) ($36.00/SY)
- 506-7043 · Biodeg Erosn Cont Logs (Instl) (8") ($5.00/LF)
Is your price for item 506-7002 in line? Benchmark your whole bid tab against TxDOT bid history.
Benchmark a bid tabOfficial source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.