Vehicular Traffic Signal, Furnish & Install Polycarbonate, 3 Section, 1 WAY (Item 0650 1 34): FDOT Unit Price History
16 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $1,668.92/AS
- Contracts (12 mo)
- 16
- Total quantity (12 mo)
- 362 AS
- Total amount (12 mo)
- $604,151
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 10 | $2,087.78 | 151 | $315,255 |
| 2025 | 2025-01-01 – 2025-12-31 | 16 | $1,983.70 | 111 | $220,191 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 16 | $1,668.92 | 362 | $604,151 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 5 | $1,810.28 | +8.5% | 137 |
| 03 | 2 | $1,826.67 | +9.5% | 3 |
| 05 | 1 | $1,435.00 | -14% | 1 |
| 06 | 3 | $1,511.06 | -9.5% | 109 |
| 07 | 1 | $1,400.00 | -16.1% | 36 |
| 08 | 2 | $2,032.96 | +21.8% | 31 |
| 11 | 1 | $1,638.58 | -1.8% | 26 |
| 12 | 1 | $1,499.83 | -10.1% | 19 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0650 1 34 (Vehicular Traffic Signal, Furnish & Install Polycarbonate, 3 Section, 1 WAY) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 16 contracts with a quantity-weighted average of $1,668.92 per AS, on 362 AS worth $604,151 in total.
The same report run for earlier periods shows $2,087.78 in 2024 (10 contracts, 151 AS), $1,983.70 in 2025 (16 contracts, 111 AS), $1,668.92 in the latest 12 months (16 contracts, 362 AS). From 2024 to the latest 12 months the weighted average fell 20.1%.
Quantity let statewide grew 140% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 01 at $1,810.28 (5 contracts), area 03 at $1,826.67 (2 contracts), area 05 at $1,435.00 (1 contract), area 06 at $1,511.06 (3 contracts), area 07 at $1,400.00 (1 contract), area 08 at $2,032.96 (2 contracts), area 11 at $1,638.58 (1 contract), area 12 at $1,499.83 (1 contract).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0650: 0650 1 14 Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY ($1,851.29 per AS, 67 contracts); 0650 2109 Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69 per EA, 42 contracts); 0650 1 16 Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98 per AS, 35 contracts); 0650 1 60 Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67 per AS, 33 contracts); 0650 1 19 Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05 per AS, 19 contracts).
Related items in section 0650
- 0650 1 14 · Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY ($1,851.29/AS)
- 0650 2109 · Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69/EA)
- 0650 1 16 · Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98/AS)
- 0650 1 60 · Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67/AS)
- 0650 1 19 · Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05/AS)
- 0650 1 70 · Vehicular Traffic Signal, Relocate- Includes Removal AND Reinstallation ($1,110.37/AS)
- 0650 1 36 · Vehicular Traffic Signal, Furnish & Install Polycarbonate, 4 Section, 1 WAY ($2,263.65/AS)
- 0650 1 18 · Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Straight, 1 WAY ($2,352.96/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.