Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY (Item 0650 1 14): FDOT Unit Price History
67 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $1,851.29/AS
- Contracts (12 mo)
- 67
- Total quantity (12 mo)
- 1,248 AS
- Total amount (12 mo)
- $2,310,414
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 103 | $1,972.79 | 1,798 | $3,547,081 |
| 2025 | 2025-01-01 – 2025-12-31 | 77 | $1,975.71 | 1,368 | $2,702,776 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 67 | $1,851.29 | 1,248 | $2,310,414 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 2 | $2,425.00 | +31% | 12 |
| 02 | 1 | $2,500.00 | +35% | 7 |
| 03 | 5 | $2,305.67 | +24.5% | 52 |
| 04 | 1 | $2,489.58 | +34.5% | 14 |
| 05 | 5 | $1,711.93 | -7.5% | 49 |
| 06 | 1 | $3,100.00 | +67.5% | 13 |
| 07 | 6 | $1,962.23 | +6% | 140 |
| 08 | 18 | $1,837.92 | -0.7% | 362 |
| 09 | 1 | $2,297.62 | +24.1% | 8 |
| 10 | 8 | $1,836.86 | -0.8% | 194 |
| 11 | 1 | $1,374.05 | -25.8% | 3 |
| 12 | 9 | $1,743.20 | -5.8% | 215 |
| 13 | 9 | $1,626.82 | -12.1% | 179 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0650 1 14 (Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 67 contracts with a quantity-weighted average of $1,851.29 per AS, on 1,248 AS worth $2,310,414 in total.
The same report run for earlier periods shows $1,972.79 in 2024 (103 contracts, 1,798 AS), $1,975.71 in 2025 (77 contracts, 1,368 AS), $1,851.29 in the latest 12 months (67 contracts, 1,248 AS). From 2024 to the latest 12 months the weighted average fell 6.2%.
Quantity let statewide shrank 31% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 7 market areas with at least three contracts, market area 13 had the lowest weighted average ($1,626.82 per AS, 9 contracts) and market area 03 the highest ($2,305.67, 5 contracts), 1.4 times as much. Market area 08 let the most contracts with this item (18). 13 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0650: 0650 2109 Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69 per EA, 42 contracts); 0650 1 16 Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98 per AS, 35 contracts); 0650 1 60 Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67 per AS, 33 contracts); 0650 1 19 Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05 per AS, 19 contracts); 0650 1 34 Vehicular Traffic Signal, Furnish & Install Polycarbonate, 3 Section, 1 WAY ($1,668.92 per AS, 16 contracts).
Related items in section 0650
- 0650 2109 · Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69/EA)
- 0650 1 16 · Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98/AS)
- 0650 1 60 · Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67/AS)
- 0650 1 19 · Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05/AS)
- 0650 1 34 · Vehicular Traffic Signal, Furnish & Install Polycarbonate, 3 Section, 1 WAY ($1,668.92/AS)
- 0650 1 70 · Vehicular Traffic Signal, Relocate- Includes Removal AND Reinstallation ($1,110.37/AS)
- 0650 1 36 · Vehicular Traffic Signal, Furnish & Install Polycarbonate, 4 Section, 1 WAY ($2,263.65/AS)
- 0650 1 18 · Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Straight, 1 WAY ($2,352.96/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.