Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Straight, 1 WAY (Item 0650 1 18): FDOT Unit Price History
10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure AS
- Weighted average (12 mo)
- $2,352.96/AS
- Contracts (12 mo)
- 10
- Total quantity (12 mo)
- 31 AS
- Total amount (12 mo)
- $72,942
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 14 | $2,445.50 | 26 | $63,583 |
| 2025 | 2025-01-01 – 2025-12-31 | 15 | $2,641.94 | 44 | $116,245 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 10 | $2,352.96 | 31 | $72,942 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 01 | 1 | $3,000.00 | +27.5% | 2 |
| 08 | 2 | $2,466.18 | +4.8% | 2 |
| 11 | 1 | $2,032.77 | -13.6% | 2 |
| 12 | 3 | $2,315.97 | -1.6% | 9 |
| 13 | 3 | $2,318.75 | -1.5% | 16 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0650 1 18 (Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Straight, 1 WAY) is measured in AS. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $2,352.96 per AS, on 31 AS worth $72,942 in total.
The same report run for earlier periods shows $2,445.50 in 2024 (14 contracts, 26 AS), $2,641.94 in 2025 (15 contracts, 44 AS), $2,352.96 in the latest 12 months (10 contracts, 31 AS). From 2024 to the latest 12 months the weighted average fell 3.8%.
Quantity let statewide grew 19% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
In the same 12 months, 5 of FDOT's 14 market areas reported this item: area 01 at $3,000.00 (1 contract), area 08 at $2,466.18 (2 contracts), area 11 at $2,032.77 (1 contract), area 12 at $2,315.97 (3 contracts), area 13 at $2,318.75 (3 contracts).
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0650: 0650 1 14 Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY ($1,851.29 per AS, 67 contracts); 0650 2109 Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69 per EA, 42 contracts); 0650 1 16 Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98 per AS, 35 contracts); 0650 1 60 Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67 per AS, 33 contracts); 0650 1 19 Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05 per AS, 19 contracts).
Related items in section 0650
- 0650 1 14 · Vehicular Traffic Signal, Furnish & Install Aluminum, 3 Section, 1 WAY ($1,851.29/AS)
- 0650 2109 · Vehicular Signal Auxiliaries, Repair/Replace/Retrofit- Furnish & Install, Backplate- Flexible Required ($641.69/EA)
- 0650 1 16 · Vehicular Traffic Signal, Furnish & Install Aluminum, 4 Section, 1 WAY ($2,345.98/AS)
- 0650 1 60 · Vehicular Traffic Signal, Remove- Poles TO Remain ($283.67/AS)
- 0650 1 19 · Vehicular Traffic Signal, Furnish & Install Aluminum, 5 Section Cluster, 1 WAY ($2,946.05/AS)
- 0650 1 34 · Vehicular Traffic Signal, Furnish & Install Polycarbonate, 3 Section, 1 WAY ($1,668.92/AS)
- 0650 1 70 · Vehicular Traffic Signal, Relocate- Includes Removal AND Reinstallation ($1,110.37/AS)
- 0650 1 36 · Vehicular Traffic Signal, Furnish & Install Polycarbonate, 4 Section, 1 WAY ($2,263.65/AS)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.