Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Trailing (Item 0536 8123): FDOT Unit Price History

10 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$2,354.50/EA
Contracts (12 mo)
10
Total quantity (12 mo)
30 EA
Total amount (12 mo)
$70,635

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3118$1,612.87103$166,125
20252025-01-01 – 2025-12-3114$2,101.1945$94,554
Latest 12 months2025-11-01 – 2026-10-3110$2,354.5030$70,635

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
022$3,392.23+44.1%3
031$2,600.00+10.4%2
051$3,000.00+27.4%2
082$1,913.55-18.7%14
091$2,000.00-15.1%2
101$3,103.61+31.8%4
111$1,654.31-29.7%1
131$2,200.00-6.6%2

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0536 8123 (Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Trailing) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 10 contracts with a quantity-weighted average of $2,354.50 per EA, on 30 EA worth $70,635 in total.

The same report run for earlier periods shows $1,612.87 in 2024 (18 contracts, 103 EA), $2,101.19 in 2025 (14 contracts, 45 EA), $2,354.50 in the latest 12 months (10 contracts, 30 EA). From 2024 to the latest 12 months the weighted average rose 46.0%.

Quantity let statewide shrank 71% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 8 of FDOT's 14 market areas reported this item: area 02 at $3,392.23 (2 contracts), area 03 at $2,600.00 (1 contract), area 05 at $3,000.00 (1 contract), area 08 at $1,913.55 (2 contracts), area 09 at $2,000.00 (1 contract), area 10 at $3,103.61 (1 contract), area 11 at $1,654.31 (1 contract), area 13 at $2,200.00 (1 contract).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0536: 0536 73 Guardrail Removal ($1.23 per LF, 84 contracts); 0536 1 1 Guardrail -Roadway, General TL-3 ($24.61 per LF, 76 contracts); 0536 85 24 Guardrail END Treatment- Parallel Approach Terminal ($3,264.12 per EA, 76 contracts); 0536 85 20 Guardrail END Treatment- Trailing Anchorage ($1,643.44 per EA, 55 contracts); 0536 8122 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3 ($3,461.91 per EA, 26 contracts).

Related items in section 0536

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.