Guardrail END Treatment- Parallel Approach Terminal (Item 0536 85 24): FDOT Unit Price History

76 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA

Weighted average (12 mo)
$3,264.12/EA
Contracts (12 mo)
76
Total quantity (12 mo)
452 EA
Total amount (12 mo)
$1,475,382

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3196$3,664.17498$1,824,755
20252025-01-01 – 2025-12-3198$3,380.31633$2,139,737
Latest 12 months2025-11-01 – 2026-10-3176$3,264.12452$1,475,382

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
015$4,168.44+27.7%12
029$3,135.76-3.9%64
035$3,294.73+0.9%56
047$3,728.11+14.2%64
057$3,024.62-7.3%54
061$3,431.00+5.1%1
079$2,813.58-13.8%73
0813$3,308.24+1.4%39
091$1,500.00-54%3
104$3,846.10+17.8%22
113$3,004.23-8%8
127$3,254.70-0.3%43
134$3,532.05+8.2%11
141$4,221.42+29.3%2

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0536 85 24 (Guardrail END Treatment- Parallel Approach Terminal) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 76 contracts with a quantity-weighted average of $3,264.12 per EA, on 452 EA worth $1,475,382 in total.

The same report run for earlier periods shows $3,664.17 in 2024 (96 contracts, 498 EA), $3,380.31 in 2025 (98 contracts, 633 EA), $3,264.12 in the latest 12 months (76 contracts, 452 EA). From 2024 to the latest 12 months the weighted average fell 10.9%.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 11 market areas with at least three contracts, market area 07 had the lowest weighted average ($2,813.58 per EA, 9 contracts) and market area 01 the highest ($4,168.44, 5 contracts), 1.5 times as much. Market area 08 let the most contracts with this item (13). 14 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0536: 0536 73 Guardrail Removal ($1.23 per LF, 84 contracts); 0536 1 1 Guardrail -Roadway, General TL-3 ($24.61 per LF, 76 contracts); 0536 85 20 Guardrail END Treatment- Trailing Anchorage ($1,643.44 per EA, 55 contracts); 0536 8122 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3 ($3,461.91 per EA, 26 contracts); 0536 8112 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-001, Approach TL-3 ($3,224.76 per EA, 23 contracts).

Related items in section 0536

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.