Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3 (Item 0536 8122): FDOT Unit Price History
26 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure EA
- Weighted average (12 mo)
- $3,461.91/EA
- Contracts (12 mo)
- 26
- Total quantity (12 mo)
- 120 EA
- Total amount (12 mo)
- $415,429
Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.
Weighted average by period
| Period | Dates | Contracts | Weighted avg | Total quantity | Total amount |
|---|---|---|---|---|---|
| 2024 | 2024-01-01 – 2024-12-31 | 30 | $3,658.10 | 177 | $647,483 |
| 2025 | 2025-01-01 – 2025-12-31 | 27 | $3,662.28 | 119 | $435,812 |
| Latest 12 months | 2025-11-01 – 2026-10-31 | 26 | $3,461.91 | 120 | $415,429 |
By FDOT market area (latest 12 months)
| Market area | Contracts | Weighted avg | vs. statewide | Total quantity |
|---|---|---|---|---|
| 02 | 5 | $3,990.05 | +15.3% | 18 |
| 03 | 2 | $3,456.53 | -0.2% | 21 |
| 04 | 2 | $3,532.01 | +2% | 9 |
| 05 | 5 | $3,052.05 | -11.8% | 49 |
| 08 | 3 | $3,226.54 | -6.8% | 4 |
| 10 | 2 | $4,108.95 | +18.7% | 5 |
| 11 | 2 | $3,408.88 | -1.5% | 5 |
| 12 | 3 | $4,537.41 | +31.1% | 5 |
| 13 | 2 | $4,125.00 | +19.2% | 4 |
FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.
Summary
FDOT pay item 0536 8122 (Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3) is measured in EA. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 26 contracts with a quantity-weighted average of $3,461.91 per EA, on 120 EA worth $415,429 in total.
The same report run for earlier periods shows $3,658.10 in 2024 (30 contracts, 177 EA), $3,662.28 in 2025 (27 contracts, 119 EA), $3,461.91 in the latest 12 months (26 contracts, 120 EA). From 2024 to the latest 12 months the weighted average fell 5.4%.
Quantity let statewide shrank 32% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.
FDOT's market-area reports for the same 12 months show how location moves the price. Among the 4 market areas with at least three contracts, market area 05 had the lowest weighted average ($3,052.05 per EA, 5 contracts) and market area 12 the highest ($4,537.41, 3 contracts), 1.5 times as much. Market area 02 let the most contracts with this item (5). 9 of FDOT's 14 market areas reported the item in this window.
FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.
Other items in FDOT section 0536: 0536 73 Guardrail Removal ($1.23 per LF, 84 contracts); 0536 1 1 Guardrail -Roadway, General TL-3 ($24.61 per LF, 76 contracts); 0536 85 24 Guardrail END Treatment- Parallel Approach Terminal ($3,264.12 per EA, 76 contracts); 0536 85 20 Guardrail END Treatment- Trailing Anchorage ($1,643.44 per EA, 55 contracts); 0536 8112 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-001, Approach TL-3 ($3,224.76 per EA, 23 contracts).
Related items in section 0536
- 0536 73 · Guardrail Removal ($1.23/LF)
- 0536 1 1 · Guardrail -Roadway, General TL-3 ($24.61/LF)
- 0536 85 24 · Guardrail END Treatment- Parallel Approach Terminal ($3,264.12/EA)
- 0536 85 20 · Guardrail END Treatment- Trailing Anchorage ($1,643.44/EA)
- 0536 8112 · Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-001, Approach TL-3 ($3,224.76/EA)
- 0536 8113 · Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-001, Trailing ($1,546.11/EA)
- 0536 1 0 · Guardrail -Roadway, General/LOW Speed TL-2 ($20.79/LF)
- 0536 7 2 · Special Guardrail Post- Special Steel Post FOR Concrete Structure Mount ($250.49/EA)
Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.
Benchmark a bid tabHow these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.