Guardrail -Roadway, General/LOW Speed TL-2 (Item 0536 1 0): FDOT Unit Price History

15 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$20.79/LF
Contracts (12 mo)
15
Total quantity (12 mo)
9,319 LF
Total amount (12 mo)
$193,776

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3120$22.6615,983$362,194
20252025-01-01 – 2025-12-3113$21.5011,348$243,961
Latest 12 months2025-11-01 – 2026-10-3115$20.799,319$193,776

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
012$23.75+14.2%763
022$20.69-0.5%344
031$34.80+67.4%259
041$17.00-18.2%116
051$17.31-16.7%1,292
071$20.00-3.8%2,717
081$35.00+68.4%16
101$19.00-8.6%592
122$21.00+1%2,438
133$22.82+9.8%782

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0536 1 0 (Guardrail -Roadway, General/LOW Speed TL-2) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 15 contracts with a quantity-weighted average of $20.79 per LF, on 9,319 LF worth $193,776 in total.

The same report run for earlier periods shows $22.66 in 2024 (20 contracts, 15,983 LF), $21.50 in 2025 (13 contracts, 11,348 LF), $20.79 in the latest 12 months (15 contracts, 9,319 LF). From 2024 to the latest 12 months the weighted average fell 8.3%.

Quantity let statewide shrank 42% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

In the same 12 months, 10 of FDOT's 14 market areas reported this item: area 01 at $23.75 (2 contracts), area 02 at $20.69 (2 contracts), area 03 at $34.80 (1 contract), area 04 at $17.00 (1 contract), area 05 at $17.31 (1 contract), area 07 at $20.00 (1 contract), area 08 at $35.00 (1 contract), area 10 at $19.00 (1 contract), area 12 at $21.00 (2 contracts), area 13 at $22.82 (3 contracts).

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0536: 0536 73 Guardrail Removal ($1.23 per LF, 84 contracts); 0536 1 1 Guardrail -Roadway, General TL-3 ($24.61 per LF, 76 contracts); 0536 85 24 Guardrail END Treatment- Parallel Approach Terminal ($3,264.12 per EA, 76 contracts); 0536 85 20 Guardrail END Treatment- Trailing Anchorage ($1,643.44 per EA, 55 contracts); 0536 8122 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3 ($3,461.91 per EA, 26 contracts).

Related items in section 0536

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.