Guardrail- Roadway, Double Face (Item 0536 1 3): FDOT Unit Price History

11 contracts · Nov 1, 2025 to Oct 31, 2026 · unit of measure LF

Weighted average (12 mo)
$36.87/LF
Contracts (12 mo)
11
Total quantity (12 mo)
18,558 LF
Total amount (12 mo)
$684,154

Source: FDOT Historical Item Average Cost report, statewide, fdot.gov, report run Nov 23, 2026, retrieved Nov 24, 2026. Figures as published by FDOT.

Weighted average by period

PeriodDatesContractsWeighted avgTotal quantityTotal amount
20242024-01-01 – 2024-12-3117$32.6793,710$3,061,345
20252025-01-01 – 2025-12-3114$36.9155,161$2,035,813
Latest 12 months2025-11-01 – 2026-10-3111$36.8718,558$684,154

By FDOT market area (latest 12 months)

Market areaContractsWeighted avgvs. statewideTotal quantity
053$29.56-19.8%1,944
061$40.50+9.8%125
073$43.47+17.9%3,172
083$32.20-12.7%569
121$36.51-1%12,748

FDOT Historical Item Average Cost reports by market area, Nov 1, 2025 to Oct 31, 2026. FDOT defines its 14 market areas; see the report page on fdot.gov.

Summary

FDOT pay item 0536 1 3 (Guardrail- Roadway, Double Face) is measured in LF. In FDOT's Historical Item Average Cost report for Nov 1, 2025 to Oct 31, 2026, it appeared on 11 contracts with a quantity-weighted average of $36.87 per LF, on 18,558 LF worth $684,154 in total.

The same report run for earlier periods shows $32.67 in 2024 (17 contracts, 93,710 LF), $36.91 in 2025 (14 contracts, 55,161 LF), $36.87 in the latest 12 months (11 contracts, 18,558 LF). From 2024 to the latest 12 months the weighted average rose 12.9%.

Quantity let statewide shrank 80% over the same span, which can move a weighted average on its own because large contracts often carry lower unit prices.

FDOT's market-area reports for the same 12 months show how location moves the price. Among the 3 market areas with at least three contracts, market area 05 had the lowest weighted average ($29.56 per LF, 3 contracts) and market area 07 the highest ($43.47, 3 contracts), 1.5 times as much. Market area 05 let the most contracts with this item (3). 5 of FDOT's 14 market areas reported the item in this window.

FDOT weights its average on quantity at the contract level, so a single very large contract can pull the figure toward its price. The report does not publish quartiles or individual bids; FDOT's bid tabulation PDFs list every bidder's unit prices for a letting.

Other items in FDOT section 0536: 0536 73 Guardrail Removal ($1.23 per LF, 84 contracts); 0536 1 1 Guardrail -Roadway, General TL-3 ($24.61 per LF, 76 contracts); 0536 85 24 Guardrail END Treatment- Parallel Approach Terminal ($3,264.12 per EA, 76 contracts); 0536 85 20 Guardrail END Treatment- Trailing Anchorage ($1,643.44 per EA, 55 contracts); 0536 8122 Guardrail Transition Connection TO Rigid Barrier, F&I- Index 536-002, Approach TL-3 ($3,461.91 per EA, 26 contracts).

Related items in section 0536

Pricing an FDOT job? Upload your bid tab and compare every line with FDOT's published averages.

Benchmark a bid tab

How these figures are used: methodology. FDOT also posts a bid tabulation PDF for each letting.