Pavement Sler (Arrow) (Item 666-7353): TxDOT Unit Price History

1,144 bids · 222 bid lines · Nov 6, 2024 to Nov 4, 2026 · unit of measure EA

TxDOT 666-7353 · PAVEMENT SLER (ARROW) · Unit: EA

Low bid
$23.00/EA
Quantity-weighted median of winning unit prices
Weighted median
$25.00/EA
Quantity-weighted median of every bid
Engineer’s estimate
$22.00/EA
Quantity-weighted median of TxDOT’s estimate per line
12-mo trend
-26%
Median unit price, last 12 months vs the 12 before
Price vs. quantity
$50.00$100.00$150.00$200.00$250.001101001KQuantity (EA), log scaleUnit price ($/EA)
Winning (low) bid Other bid Fitted price curve (ln price = 4.03 − 0.146·ln qty, R² 0.06)320 plotted bids, 4 above the chart range

Source: TxDOT bid tabulation dataset, data.texas.gov de7b-7dna, lettings Nov 6, 2024–Nov 4, 2026, retrieved Nov 24, 2026. Weighted figures are quantity-weighted; see how we compute them.

Export bid rows (CSV)

Summary

TxDOT pay item 666-7353 (Pavement Sler (Arrow)) is measured in EA. Between Nov 6, 2024 and Nov 4, 2026, contractors entered 1,144 bids for it on 222 published bid lines in TxDOT lettings. Over the last 12 months, the quantity-weighted median of all 675 bids was $25.00 per EA, and the winning low bidders priced it at a weighted median of $23.00 per EA.

TxDOT's engineer's estimate for the same lines had a weighted median of $22.00 per EA, so winning bids came in 4.5% above the estimate.

By calendar year, the median bid moved from $50.00 in 2025 (466 bids) to $37.00 in 2026 (645 bids), down 26.0%. The middle half of 2026 bids fell between $20.00 and $75.00.

Comparing the last 12 months with the 12 months before, the median unit price fell 26%.

Quantity matters for this item. Lines of 1 to 6 EA had a weighted median of $63.00, while lines above 39 EA had $25.00, a 60% lower price for large quantities. TxDOT itself warns that high-quantity items are often discounted, so compare your quantity band rather than the overall average.

Across 217 lines where both a winning and a second-place bid were published, the median winning unit price was $40.00 against $45.50 from the second-lowest bidder, a median gap of 0% on this line. Because the low bidder is decided on the whole proposal, the low bidder is not always the cheapest on every line.

Prices differ by district. Among the 14 TxDOT districts with at least ten bids, Laredo had the lowest weighted median ($16.00) and San Antonio the highest ($76.77). The busiest district for this item was Dallas.

The most recent letting with this item was on Nov 4, 2026 in Collin County, where Mario Sinacola & Sons Excavating, Inc. was the low bidder at $15.00 per EA for 55 EA against an estimate of $32.75.

1 bids outside a log-scale outlier fence (mostly token bids of a few cents or a dollar, typical of unbalanced bidding) are left out of these statistics but remain in the CSV export.

Related items: 666-7024 Refl PAV MRK TY I (W)8"(SLD)(100MIL) (weighted median $0.850 per LF); 666-7423 Refl PAV MRK TY I (Y)6"(SLD)(100MIL) (weighted median $0.450 per LF); 666-7036 Refl PAV MRK TY I (W)24"(SLD)(100MIL) (weighted median $7.00 per LF); 666-7411 Refl PAV MRK TY I (W)6"(SLD)(100MIL) (weighted median $0.450 per LF).

Unit price by year

YearBidsBid linesWeighted avgWeighted medianMedian25th pct75th pct
2024338$42.08$25.00$55.00$22.20$70.00
202546696$43.02$25.00$50.00$25.41$92.74
2026645118$38.92$25.00$37.00$20.00$75.00

Quantity bands

BandQuantity (EA)BidsWeighted avgWeighted median25th–75th pct
Small1–6391$91.69$63.00$28.97–$104.75
Medium7–36380$51.92$33.00$21.03–$75.00
Large39–854373$37.68$25.00$18.00–$63.30

Bands split bids into thirds by quantity. TxDOT notes that high-quantity items are often discounted, which pulls overall averages down.

Winning bid vs. second-low vs. engineer’s estimate

Median winning unit price
$40.00
Median second-low unit price
$45.50
Median engineer’s estimate
$50.00
Median gap, second vs. low
+0%

217 published lines with both a rank-1 and a rank-2 bid.

Contractor head-to-head · Money left on the table

Proposal 0047-04-032 · let Nov 4, 2026 · Collin County, Dallas District

Line quantity 55 EA · Engineer’s estimate $32.75/EA

  • Unit price
    $15.00/EA
    Extension
    $825.00
    Proposal total
    $35,766,135
    Money left on the table
    $890,797 (2.49%)
    vs. engineer’s estimate
    -54.2%
  • Unit price
    $57.75/EA
    Extension
    $3,176.25
    Proposal total
    $36,656,931
    vs. low bid
    +$890,797
    vs. engineer’s estimate
    +76.3%
  • 3. Tiseo Paving Company, LLC

    Unit price
    $58.00/EA
    Extension
    $3,190.00
    Proposal total
    $38,169,956
    vs. low bid
    +$2,403,821
    vs. engineer’s estimate
    +77.1%
  • 4. Harper Brothers Construction LLC

    Unit price
    $10.00/EA
    Extension
    $550.00
    Proposal total
    $40,441,503
    vs. low bid
    +$4,675,368
    vs. engineer’s estimate
    -69.5%

Proposal 0195-02-092 · let Nov 4, 2026 · Denton County, Dallas District

Line quantity 27 EA · Engineer’s estimate $20.00/EA

  • 1. Indus Road & Bridge, Inc.

    LOW BID · WINNER
    Unit price
    $10.10/EA
    Extension
    $272.70
    Proposal total
    $138,145,038
    Money left on the table
    $5,131,824 (3.71%)
    vs. engineer’s estimate
    -49.5%
  • 2. Rpm Xconstruction, LLC

    Unit price
    $9.30/EA
    Extension
    $251.10
    Proposal total
    $143,276,861
    vs. low bid
    +$5,131,824
    vs. engineer’s estimate
    -53.5%
  • Unit price
    $12.15/EA
    Extension
    $328.05
    Proposal total
    $152,579,077
    vs. low bid
    +$14,434,039
    vs. engineer’s estimate
    -39.2%
  • Unit price
    $9.00/EA
    Extension
    $243.00
    Proposal total
    $153,499,152
    vs. low bid
    +$15,354,114
    vs. engineer’s estimate
    -55%
  • 5. Sema Construction, Inc.

    Unit price
    $9.00/EA
    Extension
    $243.00
    Proposal total
    $154,136,028
    vs. low bid
    +$15,990,990
    vs. engineer’s estimate
    -55%
  • 6. Zachry Construction Corporation

    Unit price
    $9.34/EA
    Extension
    $252.18
    Proposal total
    $154,873,429
    vs. low bid
    +$16,728,392
    vs. engineer’s estimate
    -53.3%

Proposal 0015-13-432 · let Nov 3, 2026 · Travis County, Austin District

Line quantity 63 EA · Engineer’s estimate $86.00/EA

  • Unit price
    $19.00/EA
    Extension
    $1,197.00
    Proposal total
    $412,233,374
    Money left on the table
    $3,506,193 (0.85%)
    vs. engineer’s estimate
    -77.9%
  • 2. Pulice Construction, Inc.

    Unit price
    $40.82/EA
    Extension
    $2,571.66
    Proposal total
    $415,739,567
    vs. low bid
    +$3,506,193
    vs. engineer’s estimate
    -52.5%
  • 3. Fluor Enterprises, Inc.

    Unit price
    $42.80/EA
    Extension
    $2,696.40
    Proposal total
    $473,353,333
    vs. low bid
    +$61,119,959
    vs. engineer’s estimate
    -50.2%
  • 4. Harper Brothers Construction LLC

    Unit price
    $100.00/EA
    Extension
    $6,300.00
    Proposal total
    $477,550,553
    vs. low bid
    +$65,317,180
    vs. engineer’s estimate
    +16.3%
  • Unit price
    $40.00/EA
    Extension
    $2,520.00
    Proposal total
    $477,564,067
    vs. low bid
    +$65,330,694
    vs. engineer’s estimate
    -53.5%
  • 6. Balfour Beatty Infrastructure, Inc.

    Unit price
    $19.00/EA
    Extension
    $1,197.00
    Proposal total
    $492,134,823
    vs. low bid
    +$79,901,450
    vs. engineer’s estimate
    -77.9%

Money left on the table is the difference between the winning low bid and the second-lowest bid on the same proposal, a standard bid-analysis metric. It describes the published result, not a judgment of any bidder. See the methodology; to report an error, email bidtabulation@apps.adeptaoperations.com.

Last 10 lettings with this item

Let dateCSJCountyDistrictQtyBiddersLow bidderLow unit priceEstimate
2026-11-040047-04-032CollinDallas554Mario Sinacola & Sons Excavating, Inc.$15.00$32.75
2026-11-040195-02-092DentonDallas276Indus Road & Bridge, Inc.$10.10$20.00
2026-11-030015-13-432TravisAustin636Austin Bridge & Road Services, LP$19.00$86.00
2026-10-070143-03-049WilsonSan Antonio428Hunter Industries, Ltd.$75.00$65.00
2026-10-070907-00-217Tom GreenSan Angelo147Flat Line, Inc.$20.00$97.00
2026-10-066496-83-001GreggTyler202Striping Technology, L.P.$75.00$25.00
2026-09-086500-36-001WallerHouston41Trp Infrastructure Services, LLC$30.00$9.60
2026-09-030918-00-440DallasDallas88American Lighting and Signalization, LLC$30.00$30.00
2026-09-031414-01-025GalvestonHouston1576Mc2 Civil, LLC$21.00$1.00
2026-09-031801-01-064CameronPharr24Austin Traffic Signal Construction Co., LLC$15.00$32.00

By district

DistrictBidsLow bid (w. median)Weighted medianEstimate12-mo trend
Abilene5$75.00$75.00$110.00—
Amarillo9$111.50$101.50$75.00—
Atlanta7$90.00$58.00$125.00—
Austin70$19.00$45.50$86.00-38.27%
Beaumont41$5.00$23.00$3.50—
Brownwood4$100.00$105.25$26.00—
Bryan27$19.00$22.00$15.00—
Childress3$110.00$110.00$80.00—
Dallas272$25.00$26.90$60.00-43.5%
Fort Worth116$15.00$17.15$50.00-34.2%
Houston110$21.00$20.00$10.00-17.6%
Laredo37$15.00$16.00$26.00-52.06%
Lubbock5$126.50$126.50$50.00—
Odessa6$86.00$80.00$30.00—
Paris12$55.00$35.00$66.00—
Pharr55$22.22$26.30$30.00-52.69%
San Angelo24$20.00$49.84$97.00—
San Antonio227$65.00$76.77$54.00+9.36%
Tyler61$40.00$53.72$50.00-35.87%
Waco35$50.00$49.50$50.00-13.16%
Wichita Falls18$24.00$30.50$35.00—

Related items

Is your price for item 666-7353 in line? Benchmark your whole bid tab against TxDOT bid history.

Benchmark a bid tab

Official source: TxDOT bid tabulations open dataset (data.texas.gov, de7b-7dna) · Bid Items and Index (txdot.gov). Data as published by TxDOT; figures computed by Bid Tabulation.